Coverage: South Harbor piers
- This Order applies to all piers and the Muelle de San Francisco Street of South Harbor.
- The rules apply to pier decks and to specified areas within the piers, including the working apron and open storage areas.
Purpose and governing intent
- The Order prescribes load limits for the reconstructed and unrehabilitated piers.
- The Order protects pier decks from damage and premature deterioration caused by overload.
- The Order ensures the safe and continued use of the piers for the efficient movement of cargoes.
Core definitions used in the Order
- “Load Limit” is the maximum load imposed on the pier decks of:
- 500 pounds per square foot (psf) or 2.44 tons per square meter (tsm) on rehabilitated piers; and
- 200 pounds per square foot (psf) or 0.98 tons per square meter (tsm) on unrehabilitated piers.
- “Heavy Lift” means any general cargo, equipment or article with a gross weight of more than 30 tons, for purposes of this Order.
- “Low-bed Trailer” means a multi-tyred transport used to carry heavy lift cargoes.
- “Floating Crane Barge” means a water craft with a mounted derrick capable of loading and unloading heavy lift cargoes.
- “Working Apron” is a 15 meter wide area from the ledge of the pier for vessel loading and unloading operations.
- “Open Storage Area” is a space in the pier other than the working apron.
Load limits and deck protection
- Rehabilitated piers have a pier deck load limit of 500 psf or 2.44 tons/sqm.
- Unrehabilitated piers have a pier deck load limit of 200 psf or 0.98 tons/sqm.
- The Order requires compliance with load limits to prevent damage and premature deterioration of the pier decks.
Working apron rules and clearance
- The Working Apron must be used strictly for loading/unloading operations.
- During loading/unloading, temporary 1-high stacking of containers (loaded or empty) is allowed only when done using the ship’s gear or a traveling rail crane.
- Heavy equipment weighing more than 25 tons is not allowed entry into the pier for stacking of loaded containers.
- Discharging logs onto the pier is allowed only if A12" thick steel plates and/or 3–4 pieces of logs are laid out on the working apron to prevent damage to concrete curbs and pavement and to cushion the load impact.
- After loading/unloading, the working apron must be cleared of all containers, cargoes, chassis, cargo handling equipment, and other load-bearing obstructions.
Open storage area stacking limits
- In open storage areas at Finger Piers, container and cargo stacking must follow these controls:
- Empty containers may be stacked at a maximum of 3-high at Piers 3, 5, 9, and 15.
- Loaded containers may not be stacked at the open storage areas of Piers 3, 5, 9, and 15.
- 2-high stacking only is permitted in the backreach zone of the traveling rail crane for reloading to the vessel or to trucks by the rail crane.
- Containers may not be stacked directly under the spreader of the traveling rail crane.
- Pier 13 open storage areas prohibit stacking of loaded and empty containers.
- Storage of general cargoes is governed by deck-load limits:
- At open storage areas of Piers 5, 9, and 15, general cargo storage must not exceed 500 lbs./sq. ft. or 2.44 tons/sq.m.
- At open storage areas of the unrehabilitated Piers 3 and 13, the load limit must strictly be 200 lbs./sq. foot or 0.98 tons/sq.m.
- After rehabilitation of Piers 3 and 13, the 500 psf or 2.44 tons/sq.m. load limit applies there.
- Storage of bulk cargoes, steel products, lumber and logs allowed for discharge unto the pier by the Authority must be temporary and subject to the prescribed load limits.
- Allowable stacking height rules for certain commodities must comply with the conditions in the Annexes “A” and “B”.
Muelle de San Francisco street controls
- Container and general cargo stacking at the Muelle de San Francisco Street (MDSF) is governed by a development condition:
- Unless authorized in writing by the Authority, stacking at the MDSF is not allowed once CY-01 is completely developed and becomes fully operational.
Heavy lift handling requirements
- Handling of heavy lift cargoes (more than 30 tons) is generally prohibited.
- Discharge of heavy lift cargoes is allowed only when all conditions are met:
- the discharge uses a multi-tyred low-bed trailer to effect even distribution of weight and to conform with the prescribed load limits;
- the operator secures prior approval from the Authority;
- after discharge, the trailer is driven to solid ground;
- the cargo is released only after documentary requirements have been complied with and clearance has been granted.
- If the heavy lift cargo cannot be handled at the pier even with a multi-tyred low-bed trailer because the load limit would be exceeded, the cargo must be discharged shipside unto appropriate means of transport.
- If the heavy lift cargo cannot be unloaded using the ship’s derrick, a floating crane is required to discharge the heavy lift cargo unto the pier, subject to the same conditions in paragraphs 5.4.1 and 5.4.2.
Administrative violations, liabilities, and penalties
- Non-compliance with any provision of this Order constitutes an administrative violation punishable under Section 43 of P.D. 857, as amended.
- The offender is also liable for the cost of damage to facilities arising from the violation.
- The cost of damage to facilities arising from non-compliance is borne by the party responsible.
Final provisions: repeal and effectivity
- All PPA issuances inconsistent with this Order are repealed or amended accordingly.
- This Order takes effect fifteen (15) days after publication in a newspaper of general circulation.
- The Order is adopted on 10 Oct. 1996 and signed by CARLOS L. AGUSTIN, General Manager.