Question & AnswerQ&A (DPWH DEPARTMENT ORDER NO. 30, S. 2011)
The main purpose is to ensure a cost-effective design of bridges and promote the use of locally available materials for permanent bridges with total lengths up to 30.0 meters.
It applies to all permanent bridges with total lengths of up to 30.0 meters.
For span lengths of 6-12 meters, flat slab bridge shall be used.
For span lengths of 13-20 meters, reinforced concrete deck girder (RCDG) bridge shall be used.
For span lengths of 21-30 meters, prestressed concrete girder (PSCG) bridge shall be used.
No, all projects under the ongoing bridge supply contracts being implemented by the PMO-Special Bridge Projects and President's Bridge Program Office are not covered by this issuance.
The Order took effect immediately on May 16, 2011.
Using locally available materials aims to promote cost-effectiveness and sustainability in bridge construction projects.
This order applies only to permanent bridges.