Title
Subic Bay Distribution, Inc. vs. Western Guaranty Corp.
Case
G.R. No. 220613
Decision Date
Nov 11, 2021
SBDI sued WGC over a P8.5M performance bond after PASSI defaulted on petroleum payments. SC ruled WGC liable, upholding delivery proof, no material alterations, and surety obligations.

Case Summary (G.R. No. 220613)

Parties

Petitioner seeks to enforce a P 8.5 million performance bond issued by Respondent in favor of SBDI to secure PASSI’s payment obligations.

Key Dates

• Distributor Agreement effective April 16, 2001–April 16, 2003 (and renewable annually)
• Demand letters to PASSI and WGC: January–February 2002
• RTC decision: September 7, 2011
• CA decision reversing RTC: April 14, 2015
• Supreme Court decision: November 11, 2021

Applicable Law

• 1987 Philippine Constitution (decision after 1990)
• Civil Code of the Philippines (Articles 1169, 1170, 1216, 2047)
• Rule 8, Revised Rules of Court (specific denial, documentary evidence)
• Jurisprudence on suretyship, sales invoices, material alteration of principal contracts

Contractual Arrangement

• Distributor Agreement: PASSI to purchase and pay for petroleum products within 15 days, credit limit ₱5 million per year.
• Item 6.3: PASSI to furnish a performance bond from a bonding company chosen by SBDI to secure outstanding accounts and faithful performance.
• Default clause: Unpaid amounts become immediately due without further notice.

Performance Bond and Default

PASSI secured an ₱8.5 million bond from WGC. Upon PASSI’s nonpayment of ₱100.26 million, SBDI sent demand letters to both PASSI and WGC. PASSI did not settle, and WGC refused payment. SBDI sued WGC alone for sum of money.

Regional Trial Court Ruling

RTC (Makati, Branch 136) rendered judgment ordering WGC to pay ₱8.5 million plus 6% annual interest from July 12, 2002, ten percent attorney’s fees, and costs. RTC dismissed WGC’s counterclaim.

Court of Appeals Ruling

CA held SBDI failed to prove actual delivery to PASSI, noting that sales invoices alone do not establish delivery. Alternatively, CA found material alterations in the Distributor Agreement—credit limit raised to ₱8.5 million and delivery frequency changed—without WGC’s consent, releasing WGC from liability.

Issues on Appeal

Whether CA erred in ruling that WGC’s surety obligation was extinguished due to (1) insufficient proof of delivery, and (2) material alteration of the Distributor Agreement without WGC’s consent.

Nature of Suretyship and Governing Principles

• Suretyship (Art. 2047): surety binds to fulfill principal debtor’s obligation; liability is joint and several but strictly limited to bond terms.
• Demand on surety suffices; principal’s prior failure not prerequisite.
• Material alteration of a principal contract that makes the surety’s obligation more onerous releases the surety; non-material changes do not.

Proof of Delivery and Validity of Sales Invoices

• SBDI presented forty-four signed sales invoices indicating “Received goods in good condition,” supported by testimony on standard company practice.
• PASSI’s silence and absence of protest to repeated billing and demand letters imply acceptance of delivery.
• Under Rule 8, R.R.C., WGC failed to specifically deny genuineness and due execution of the invoices; such failure deems them admitted.
• Load-order manifest not exclusive proof; sales invoices bearing the distributor’s acknowledgment are competent and sufficient.

Material Alterations of Principal Contract

• Alleged changes—delivery frequency and credit term extension—were not material or onerous:
– Delivery clause contemplated “approximately equal monthly quantities” but did not fix delivery frequency; actual deliveries followed PASSI’s orders.
– Extending payment term from 15 to 30 days reduced risk, benefitting the surety.
• WGC knew PASSI sought an ₱8.5 million bond despite the original ₱5 million limit; WGC issued the bond, binding itself to the ₱8.5 million guarantee.
• No supplemental agreement altered principal contract; CA’s finding of unauthorized material alterations is unsupported and contrary to admissions



...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.