Title
Spouses Francisco vs. DEAC Construction, Inc.
Case
G.R. No. 171312
Decision Date
Feb 4, 2008
Spouses Francisco engaged DEAC Construction for a residential building. DEAC breached the contract by deviating from approved plans, starting without a permit, and forging signatures. SC reinstated RTC's ruling, awarding partial rescission, refund, and damages.

Case Summary (G.R. No. 171312)

Factual Background

The parties entered into a contract for the construction of a three-storey residential building with mezzanine and roof deck on the Spouses Francisco's lot at 118 Pampanga Street, Gagalangin, Tondo, Manila for a contract price of P3,500,000.00. The contract provided for a downpayment of P2,000,000.00 and two equal installments of P750,000.00. The Spouses Francisco paid P2,000,000.00 on or about September 12, 1994, followed by payments of P200,000.00 on February 27, 1995, P550,000.00 on April 2, 1995, and P80,000.00 on June 5, 1995 for additional works. Respondent DEAC Construction, Inc. engaged a subcontractor and commenced work in October 1994 before the requisite building permit was secured. The Office of the Building Official issued notices of violations citing deviations from approved plans, including reduction of the required setback, covering of a required open patio, and excessive roof projection. The Spouses Francisco later alleged forgery of Guia Francisco's signature on amended plans and filed administrative, criminal, and civil complaints against respondents.

Procedural History

The Spouses Francisco instituted Civil Case No. 95-75430 in the Regional Trial Court of Manila, Branch 28, seeking rescission of the contract and damages. The trial court found respondents in breach, ordered partial rescission, and awarded refund and damages. The Court of Appeals reversed and awarded respondents the remaining balance of the contract price plus damages and attorneys' fees. The Spouses Francisco petitioned this Court for review. The Supreme Court granted the petition, reversed the Court of Appeals, and reinstated the RTC decision.

Issues Presented

The principal issues were whether the deviations from the approved building plans were authorized by Sps. Lino Francisco and Guia Francisco; whether respondents' commencement of construction without a building permit and the alterations justified rescission of the contract; whether the Spouses Francisco waived the right to rescind by delayed protest; and whether partial rescission and the monetary awards ordered below were appropriate.

Parties' Contentions

The Spouses Francisco contended that they did not authorize the deviations, that respondents commenced and proceeded with construction without first obtaining the building permit as required by the contract, and that their withholding of the final installment was justified and timely followed by civil and criminal actions. Respondents maintained that the Spouses Francisco requested or authorized the deviations, attributed the permit delay to a subordinate's error in designating the lot, and argued that the owners waived their right to rescind by raising complaints only after construction was several months underway.

Trial Court Findings

The Regional Trial Court found that respondents had breached their contractual obligations by commencing construction without the necessary building permit as required under Section 3, Article IV of the Construction Contract and by deviating from the approved building plan without the owners' consent. The RTC concluded that withholding the final installment was justified and that rescission of the reciprocal obligation was warranted in part because the building was already approximately seventy to seventy-five percent complete. The RTC ordered partial rescission, directed refund of P205,000.00 for unfinished work, awarded moral damages of P250,000.00, exemplary damages of P250,000.00, attorneys' fees of P100,000.00, and held Geomar A. Dadula solidarily liable with DEAC Construction, Inc.

Court of Appeals Ruling

The Court of Appeals reversed the RTC. The appellate court concluded that the Spouses Francisco had initiated or requested the deviations, and that respondents had substantially complied with the contract. The CA ordered the Spouses Francisco to pay P670,000.00 as the remaining balance of the contract price, awarded P100,000.00 as moral damages, P50,000.00 as attorneys' fees, and costs of suit.

Supreme Court Ruling

The Supreme Court granted the petition. The Court found that respondents admitted commencing construction before securing the building permit and that evidence showed forgery of petitioner Guia Francisco's signature on amended plans and unauthorized closure of the open space in violation of the National Building Code (P.D. No. 1096). The Court held that the deviations were not authorized by the Spouses Francisco and that the owners did not waive their right to seek rescission. The Court concluded that the RTC correctly ordered partial rescission of the undelivered portion of the obligation and that equitable considerations supported rescission insofar as performance remained unfinished. Accordingly, the Supreme Court reversed the Court of Appeals Decision dated July 28, 2005 and its Resolution dated January 31, 2006, and reinstated the RTC Decision dated February 2, 1998.

Legal Basis and Reasoning

The Court applied Article 1191, New Civil Code, observing that the power to rescind is implied in reciprocal obligations when one obligor fails to comply with what is incumbent upon him. The Court emphasized that rescission addresses breach of faith and violation of reciprocity rather than mere economic injury. The Court found that respondents' failure to obtain the building permit, their deviations from the approved plans, and the forgery of the owner's signature demonstrated a breach of the reciprocal obligation and caused prejudice to the owners. The Court rejected the appellate court's view of waiver because the Spouses Francisco had promptly raised complaints, filed criminal charges, and instituted this civil action within a reasonable time after d

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.