Title
Spouses Francisco vs. DEAC Construction, Inc.
Case
G.R. No. 171312
Decision Date
Feb 4, 2008
Spouses Francisco engaged DEAC Construction for a residential building. DEAC breached the contract by deviating from approved plans, starting without a permit, and forging signatures. SC reinstated RTC's ruling, awarding partial rescission, refund, and damages.
A

Case Digest (G.R. No. 75209)

Facts:

  • Parties Involved
    • Petitioners: Spouses Lino Francisco and Guia Francisco.
    • Respondents: DEAC Construction, Inc. and its President Geomar A. Dadula.
  • Background of the Construction Contract
    • A contract was executed for the construction of a 3-storey residential building with mezzanine and roof deck on the petitioners’ lot at 118 Pampanga Street, Gagalangin, Tondo, Manila.
    • The agreed contract price was P3,500,000.00 with a structured payment scheme:
      • Downpayment of P2,000,000.00 upon contract signing.
      • Two installments of P750,000.00 each – the first upon completion of the foundation and ground floor; the second upon completing the second floor to the roof deck.
    • The petitioners’ advance payments included additional amounts for extra works, evidencing their early financial commitment to the project.
  • Commencement and Permit Issues
    • Construction began in October 1994 even though DEAC had not yet secured a building permit.
    • The building permit was eventually issued on March 7, 1995, after lengthy adjustments including corrections on the building plan.
    • A significant issue arose when DEAC allegedly forged Mrs. Guia Francisco’s signature on the amended building plans to facilitate the permit approval.
  • Deviations from Approved Plans and Subsequent Violations
    • Several deviations were observed from the approved specifications:
      • Closing of the required open space (patio) as stipulated by the National Building Code.
      • Reduction of the required setback from the property line (1.45 m reduced to 1.00 m).
      • Other noted violations involved excessive roof deck projection, provision of unauthorized window openings, and improper stockpiling of construction materials.
    • The Office of the Building Official of Manila issued Notices of Violation highlighting these deviations, with one notice specifically enumerating the infractions as early as April 7, 1995.
    • The petitioners, although unaware of the official notices initially, later contested that these deviations were executed unilaterally by DEAC without their consent.
  • Dispute and Legal Actions
    • The petitioners filed a criminal case against respondent Dadula for apparent building code violations, particularly relating to unauthorized construction deviations.
    • They also initiated a civil case for rescission of the contract and damages citing:
      • Unauthorized alterations to the construction plans (closing of the open space and setback reduction).
      • Non-compliance with the contractual obligation to secure a building permit before commencement of construction.
      • Poor workmanship and failure by DEAC to inform them regarding plan corrections and permit issues.
    • The Regional Trial Court of Manila, Branch 28, in its decision dated February 2, 1998, found respondents in breach and ordered partial rescission of the contract, refunding the petitioners based on work completion.
  • Conflict in Substantive Findings
    • The trial court held that the unauthorized deviations warranted partial rescission and awarded damages.
    • In contrast, the appellate court reversed the regional decision by concluding that the petitioners had, in fact, initiated or consented to the deviations and were consequently obligated to pay the remaining balance of the contract price along with moral damages and attorney’s fees.
    • This divergence in findings over whether the petitioners authorized the deviations played a central role in the legal controversy.
  • Additional Evidentiary and Procedural Elements
    • Evidence showed the construction commenced without the proper building permit, directly linking DEAC’s negligence to both criminal and civil liabilities.
    • The record includes details on forged signatures, discrepancies in the building plans, and explicit non-compliance with the construction contract and the National Building Code.
    • Subsequent court decisions and affidavits reinforced the position that unauthorized deviations were executed solely at the behest of DEAC, thereby warranting rescission for the undelivered portion of the contract.

Issues:

  • Authorization of Deviations
    • Whether the deviations from the approved building plan—specifically, the closing of the open space (patio) and the reduction of the setback from 1.45 m to 1.00 m—were authorized by the petitioners.
    • The implications of alleged forged signatures on the amended building plans in determining actual consent.
  • Noncompliance with Permit Requirements
    • Whether commencing construction without a building permit constituted a breach of contractual and statutory obligations by DEAC.
    • The extent of DEAC’s duty to inform the petitioners about the permit status and any corrections made to the building plans.
  • Waiver of Rights
    • Whether the petitioners, by their delay in objecting to the unauthorized deviations and by their conduct following the initial infractions, implicitly waived their right to demand rescission of the contract.
    • How the timing of the petitioners’ complaints and subsequent legal actions impacts the waiver issue.
  • Extent and Equitability of Rescission
    • To what extent the contract may be rescinded—whether partially or wholly—in light of the constructed building being 70% to 75% complete.
    • What constitutes an equitable remedy in the context of partial completion and the resulting damages.
  • Liability for Additional Violations
    • Whether DEAC’s unilateral engagement of a sub-contractor and its subsequent deviations impact its overall contractual liability.
    • The role of respondent Dadula’s criminal conviction in affirming the breach of contractual obligations.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.