Title
Spouses David vs. Construction Industry and Arbitration Commission
Case
G.R. No. 159795
Decision Date
Jul 30, 2004
Construction firm CGI and its officers held liable for deviating from agreed building plans, leading to contract rescission and damages for defects and negligence.

Case Summary (G.R. No. 159795)

Contract Terms and Performance Allegations

Contract provisions required CGI to prepare working drawings, construct the building for P7,309,821.51 (plus P200,000 design fee), and complete work within nine months of securing the permit. Petitioners asserted substantial performance (80% accomplishment) and readiness to complete remaining “punch‑list” items. Respondents alleged significant deviations from approved plans and specifications, unauthorized structural revisions, and multiple construction defects.

Deficiencies, Tests and Rescission

Independent inspections and tests (Geotesting International and UP Materials Testing Laboratory) showed several concrete core and reinforcing steel samples failing specified strength requirements. Specific factual findings included: additional concrete columns (including two in the basement obstructing parking), three additional columns affecting floor plans and dimensions, misalignments and architectural deficiencies, lack of water‑proofing resulting in leaks, under‑designed cistern with inadequate capacity and no partition from sump pit, and a one‑meter encroachment beyond the property line due to absence of a relocation survey. CGI produced internal correspondence acknowledging deficiencies and proposed corrective items; however, the Quiambaos rescinded the contract and engaged another contractor to assess completion and damages.

Arbitration Proceedings and Award

Pursuant to the parties’ agreement, the dispute was submitted to the Construction Industry Arbitration Commission (CIAC). A sole arbitrator was appointed, assisted by an engineering expert who conducted two ocular inspections. The arbitrator awarded the Quiambaos a net sum of P4,073,229.94 (detailed awards included lost rentals, cost to complete/rectify, damages for erroneous staking, professional fees, miscellaneous expenses, utility bills, attorney’s fees, moral and exemplary damages), credited CGI for value of materials left on site (P238,372.75) and for 80% work accomplishment (P5,847,857.20), and ordered interest and shares of expert fees. All other claims and counterclaims were dismissed.

Court of Appeals Review

The Court of Appeals affirmed the arbitral decision but deleted the award for lost rentals. The CA accepted the arbitrator’s factual findings regarding deviations from plans, technical deficiencies revealed by tests, the unauthorized plan revisions to reduce cost, lack of relocation survey resulting in encroachment, and the under‑designed cistern as sufficient basis justifying the owners’ rescission.

Issues Raised to the Supreme Court

Petitioners advanced two principal contentions: (1) respondents had no valid basis to unilaterally rescind the contract because CGI had substantially performed and was capable of completing the work; and (2) spouses Roberto and Evelyn David should not be held personally liable jointly and severally with the corporation, invoking the doctrine of separate juridical personality.

Governing Law and Standard of Review

Applicable constitutional framework: 1987 Philippine Constitution (case decided post‑1990). Statutory and regulatory framework: Executive Order No. 1008 (Construction Industry Arbitration), which vests CIAC with original and exclusive jurisdiction over voluntarily submitted construction disputes and limits appellate review of CIAC awards to questions of law (Section 19); Section 24, Republic Act No. 876 (arbitration review exceptions); and SC administrative circulars addressing CIAC appeals. The Court reiterated the distinction between questions of law (doubts as to what the law is on given facts) and questions of fact (doubts as to the veracity of alleged facts). Review of arbitral findings of fact is severely limited: appellate courts and the Supreme Court generally do not reassess probative value of evidence or reweigh factual determinations of arbitrators absent the narrow statutory grounds (e.g., corruption, partiality, misconduct, disqualification withheld, or excess or imperfect exercise of powers) showing grave abuse or deprivation of a fair opportunity to be heard.

Supreme Court Analysis on Rescission and Factual Findings

The Court found petitioners’ challenges to rescission primarily factual: assertions of 80% completion and that defects were mere punch‑list items were contradicted by the record. The Court accepted the arbitrator’s and CA’s detailed factual findings—unauthorized structural changes (including additional columns), multiple architectural and structural defects, failed material tests, encroachment beyond property line, and an under‑designed cistern—as providing a sufficient factual and legal basis for the owners’ termination of the contract. These findings were technical, supported by expert testimony and inspections, and therefore not subject to de novo review by the Supreme Court under the limited standard of appellate review applicable to CIAC awards.

Sup

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.