Title
Supreme Court
San Ferdo Regala Trading, Inc. vs. Cargill Philippines, Inc.
Case
G.R. No. 178008
Decision Date
Oct 9, 2013
Cargill and San Fernando disputed molasses delivery contracts; Cargill breached partially in Contract 5026 and fully in Contract 5047, leading to mutual claims for unrealized profits and demurrage charges. Moral/exemplary damages denied.

Case Summary (G.R. No. 178008)

Applicable Law

The relevant constitutional provision guiding this case is the Civil Code concerning obligations and contracts, as the dispute pertains to breach of contract, delivery obligations, and damages.

Overview of Contracts

Cargill and San Fernando entered into two contracts: Contract 5026 for the sale of 4,000 metric tons (mt) of molasses to be delivered between April and May 1997 at a price of P3,950.00 per mt, and Contract 5047 for 5,000 mt at P2,750.00 per mt, with a delivery period in the fourth quarter of 1996.

Allegations and Breach of Contract

Cargill claimed it offered to deliver the agreed amounts, but San Fernando only accepted 951 mt under Contract 5026 and refused further deliveries, asserting that its failure was due to full storage at Ajinomoto's facility. Cargill, as a result, incurred significant losses, including demurrage and unrealized profits, prompting them to file a complaint on March 2, 1998, seeking damages.

Trial Court's Findings

The Regional Trial Court (RTC) initially sided with San Fernando, dismissing Cargill's claims and awarding substantial damages to San Fernando, asserting that Cargill failed its delivery obligations under both contracts, thereby causing San Fernando to default on its obligations to Ajinomoto.

Court of Appeals' Analysis

Upon appeal, the Court of Appeals (CA) ruled that while Cargill had not breached Contract 5026 entirely (having made an initial delivery of 951 mt), it had failed to fulfill the remaining obligations, accepting that San Fernando's refusal to accept further delivery warranted demurrage reimbursement. Conversely, for Contract 5047, the CA found Cargill in breach, resulting in the award of unrealized profits to San Fernando.

Judicial Findings on Key Issues

The CA's decision outlined that:

  1. Cargill was partially liable for Contract 5026 due to its failure to provide the total agreed amount, which was deemed a breach. However, since San Fernando refused to accept the April delivery, it owed Cargill for demurrage incurred.
  2. Cargill was fully liable for breaching Contract 5047 by failing to make any deliveries during the stipulated time, thus liable for the full expected profits.

Denial of Additional Damages

The CA deleted awards for moral and exemplary damages, as San Fernando could not substantiate claims of bad faith or reputational harm against Cargill. Similarly, awards for attorney&#

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.