Title
Supreme Court
San Ferdo Regala Trading, Inc. vs. Cargill Philippines, Inc.
Case
G.R. No. 178008
Decision Date
Oct 9, 2013
Cargill and San Fernando disputed molasses delivery contracts; Cargill breached partially in Contract 5026 and fully in Contract 5047, leading to mutual claims for unrealized profits and demurrage charges. Moral/exemplary damages denied.

Case Digest (G.R. No. 178008)
Expanded Legal Reasoning Model

Facts:

  • Background of the Parties
    • Cargill Philippines, Inc. and San Fernando Regala Trading, Inc. are both established cane molasses traders that have conducted business with each other for some time.
    • The controversy arose from alleged non-performance in their contractual dealings involving the delivery and acceptance of molasses.
  • Contractual Arrangements
    • Two separate contracts formed the basis of the dispute:
      • Contract 5026 – Covered the sale of 4,000 metric tons (mt) of molasses at P3,950.00 per mt with a delivery period set for April to May 1997.
      • Contract 5047 – Covered the sale of 5,000 mt of molasses at P2,750.00 per mt with a delivery period scheduled within October–November–December 1996.
    • The contracts were forward sales, meaning that the delivery was to occur approximately 10 months later, introducing risks related to market price fluctuations.
  • Delivery Issues and Alleged Breaches
    • Under Contract 5026:
      • Cargill claimed to have attempted timely delivery by:
        • Delivering 951 mt in March 1997.
ii. Sending a barge carrying 1,174 mt on April 2, 1997, which arrived at the designated Ajinomoto wharf.
  • San Fernando, however, is alleged to have refused acceptance of the additional 1,174 mt and, in its counterclaim, maintained that aside from the 951 mt, no further deliveries were accepted.
  • Under Contract 5047:
    • Cargill purportedly sought to deliver the molasses in the agreed period (October–November–December 1996), but no actual delivery occurred.
    • On May 14, 1997, Cargill proposed an extension of the delivery periods for both contracts, a proposal which San Fernando rejected, asserting its own contractual obligation with Ajinomoto at a different selling price.
  • Consequences of Non-Delivery
    • The refusal to accept the 1,174 mt delivery resulted in the barge remaining at the wharf for approximately 71 days, incurring demurrage charges amounting to P920,000.00 (later recalculated to P892,732.50 by the CA).
    • Cargill suffered additional damages including:
      • Losses from having to sell the delivered molasses to another buyer at a reduced price, resulting in unrealized profits calculated for the delivered portion (1,174 mt) at P2,451,405.59.
      • Losses arising from the total non-delivery under Contract 5047, where San Fernando claimed unrealized profits of P11,000,000.00.
    • San Fernando counterclaimed for:
      • Damages covering its lost profits under both contracts (P4,115,329.20 for Contract 5026 and P11,000,000.00 for Contract 5047).
      • Moral and exemplary damages, attorney’s fees, and litigation expenses.
  • Litigation History
    • The Regional Trial Court (RTC) dismissed Cargill’s complaint for lack of merit and granted San Fernando’s counterclaims, awarding significant sums on the basis of lost profits and additional damages.
    • The Court of Appeals (CA) partially modified the RTC decision:
      • It held that Cargill committed partial breach under Contract 5026 (for the remaining 1,875 mt undelivered) but was not entirely at fault due to the attempted delivery of 1,174 mt.
      • It ruled that Cargill was in outright default under Contract 5047 for failing to deliver any molasses in the agreed period.
      • The CA adjusted the damages, awarding San Fernando the unrealized profits for the breach of Contract 5047 while also ordering San Fernando to reimburse Cargill for the demurrage incurred.
      • The CA deleted the awards for moral and exemplary damages, as well as attorney’s fees and litigation costs.
    • Both parties subsequently appealed to the Supreme Court.

Issues:

  • Breach of Contract 5026
    • Whether the Court of Appeals erred in its assessment that Cargill was not entirely in breach of Contract 5026 due to its partial delivery (951 mt delivered and an attempted delivery of 1,174 mt).
    • Whether the measure of damages for the undelivered balance (1,875 mt) was appropriately computed based on the unrealized profit San Fernando would have earned.
  • Breach of Contract 5047
    • Whether the CA correctly found Cargill in breach for failing to deliver any of the 5,000 mt of molasses during the stipulated period (October–November–December 1996).
    • Whether Cargill’s proposal to extend the delivery period on May 14, 1997 was a valid modification or if its rejection by San Fernando was justified given the pre-existing obligations with Ajinomoto.
  • Award of Additional Damages
    • Whether the CA erred in deleting the awards for moral and exemplary damages, as well as attorney’s fees and cost of litigation.
    • Whether San Fernando sufficiently demonstrated that Cargill acted with bad faith, thereby justifying such additional damages.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.