Case Summary (G.R. No. 124899)
Factual Background
Maria Romayne Miranda owned a 17,748-square-meter parcel in Cabcaben, Mariveles, Bataan, registered under TCT No. T-129442. She executed a General Power of Attorney dated 15 April 1990 appointing her cousin, Gilbert Miranda, as attorney-in-fact to manage her properties. On 9 July 1990, Gilbert, as agent, entered into a Development and Construction Contract with Renato C. Salvador, contractor and proprietor of Montariza Construction, to develop the property into the Haven of Peace Memorial Park for a contract price of P3,986,643.50.
Contractual Terms and Obligations
The written Contract provided for completion within 180 working days from receipt of the down payment, with a 45-working-day grace period. Paragraph 17 required written agreement for changes. Paragraph 18 authorized escalation of the contract price only in the event of substantial increases in prices of particular materials such as cement and G.I. sheets, and paragraph 20 excluded matters not stipulated unless agreed in writing. Paragraph 3 placed the obligation to provide materials, equipment, manpower and supervision on the Contractor.
Performance and Dispute
Work commenced in July 1990 after a 20% down payment of P797,328.70. Salvador periodically submitted progress billings which Gilbert paid. By December 1990, Salvador demanded additional sums: P39,000 as a 20% fee on P196,000 of filling materials supplied by respondents; P637,862.96 as a 20% escalation on the unpaid balance; and P399,190.46 for alleged additional works. Salvador insisted that material prices had risen up to 40% and threatened to stop work if respondents did not accede. Gilbert requested detailed substantiation. On 25 December 1990 Salvador submitted a computation applying a uniform 20% increase on outstanding balances for services. Gilbert paid additional advances totaling P350,000 but retained that only P90,772.91 remained unpaid on the Contract. Salvador ceased work on 14 January 1991 and attached to his notice a DPWH cease-and-desist notice dated 8 January 1991, received by one of his engineers on 15 January 1991. On 31 January 1991 Salvador filed a complaint for collection and damages or for declaration of lien against Romayne and Gilbert. Respondents later engaged a new contractor and ejected Salvador’s crew.
Trial Court Proceedings and Ruling
After trial the Regional Trial Court dismissed Salvador’s complaint and dismissed respondents’ counterclaims for insufficiency of basis. The court found Salvador failed to identify particular materials whose prices had increased as required by paragraph 18 and failed to prove authorization or agreement on the alleged additional works and their prices as required by Article 1724. The court also found no contractual authority for a 20% charge on filling materials supplied and delivered by respondents. The trial court concluded that plaintiff’s cause of action was insufficiently supported and ordered dismissal of the complaint and the counterclaims.
Court of Appeals Ruling
The Court of Appeals affirmed the dismissal of Salvador’s claims but reversed on respondents’ counterclaims. The appellate court found respondents established their expenditures in completing the project and held Salvador acted in bad faith by halting work. It ordered Salvador to reimburse respondents P1,685,532.48 less P90,772.91, awarded P100,000 moral damages, P50,000 exemplary damages, and P20,000 attorneys fees, with costs against plaintiff-appellant.
Issues Presented to the Supreme Court
The petition contended that the Court of Appeals erred in ordering reimbursement of respondents’ claimed expenses, in holding that Salvador’s escalation claim lacked basis, in finding that alleged additional works were unauthorized, and in concluding that Salvador stopped work for lack of payment rather than in compliance with the DPWH notice. The central questions were whether Salvador’s claims for additional works, the 20% charge on materials, and escalation were valid, and whether respondents were entitled to the counterclaim and damages awarded by the appellate court.
Standard of Review and Scope of Review
The Court observed that review under Rule 45 was generally limited to questions of law and that factual findings of the Court of Appeals are ordinarily binding when affirmed by the trial court. The Court stated it would not disturb the lower courts’ factual findings that respondents did not authorize additional works nor agree on their price, and that Salvador failed to specify the particular materials whose prices allegedly rose.
Legal Basis for Denial of Additional Works Claim
The Court applied Civil Code, Art. 1724, and held two requisites were indispensable for a contractor to recover additional costs: written authorization by the proprietor for changes in plans and specifications; and a written determination by both parties of the additional price. The Court found Salvador presented no written authority for changes, no written agreement on prices for extra work, and no prior notice to respondents. The Contract did not permit unilateral determination of changes or prices. Therefore Salvador’s claim of P399,190.46 for alleged additional works had no legal basis.
Legal Basis for Denial of Escalation Claim and 20% Charge on Materials
The Court examined paragraph 18 of the Contract and the jurisprudence on escalation clauses, citing Baylen Corporation v. Court of Appeals and other authorities. It held paragraph 18 authorized escalation only upon substantial increases in prices of particular materials used in the project and required the contractor to show such increases. Salvador, who supplied materials, had the burden to produce receipts, supplier billings or similar documents. His December 25 computation merely applied a blanket 20% increase to outstanding balances for services and failed to identify particular materials and the actual increases. The Court held such blanket escalation was contrary to the clear terms of the Contract and, even if the Contract purported to permit unilateral escalation, such a provision would be void under the principle of mutuality as expressed in Art. 1308 and the Court’s prior rulings. The Court likewise found no basis for a 20% fee on filling materials that respondents purchased and delivered, given the Contract’s allocation of material supply to the Contractor and paragraph 20’s exclusion of matters not stipulated unless agreed in writing.
Counterclaim, Damages, and Effect of DPWH Notice
The Court considered the Court of Appeals’ finding that Salvador stopped work because respondents refused escalation and found documentary support for Salvador’s threats to halt work for that reason. The Court rejected Salvador’s contention th
...continue reading
Case Syllabus (G.R. No. 124899)
Parties and Procedural Posture
- RENATO C. SALVADOR was the contractor and petitioner before the Court in a Rule 45 petition seeking review of the Court of Appeals decision of 30 April 1996 in CA-G.R. CV No. 39661.
- COURT OF APPEALS rendered the appealed decision reversing the trial court and awarding reimbursement and damages to MARIA ROMAYNE MIRANDA and GILBERT MIRANDA.
- MARIA ROMAYNE MIRANDA owned the subject property and GILBERT MIRANDA acted as her attorney-in-fact under a General Power of Attorney dated 15 April 1990.
- The trial court in San Mateo, Rizal, Branch 76 dismissed petitioner’s complaint and respondents’ counterclaims for insufficiency of basis in Civil Case No. 754 on 18 August 1992.
- Petitioner filed the present petition for review under Rule 45, Rules of Court contesting the Court of Appeals’ reversal and awards.
Key Factual Allegations
- MARIA ROMAYNE MIRANDA owned a 17,748 square meter parcel in Cabcaben, Mariveles, Bataan, covered by TCT No. T-129442.
- GILBERT MIRANDA, as attorney-in-fact, executed on 9 July 1990 a Development and Construction Contract with RENATO C. SALVADOR for the Haven of Peace Memorial Park at a Contract Price of P3,986,643.50.
- GILBERT MIRANDA paid a twenty percent down payment of P797,328.70 and thereafter paid progress billings totaling P3,775,804.80 leaving an outstanding balance the parties treated as P210,838.71.
- Petitioner demanded additional sums in December 1990 consisting of P39,000 as a twenty percent fee on P196,000 worth of filling materials supplied by respondents, an escalation of P637,862.96, and alleged additional works billed at P399,190.46.
- RENATO C. SALVADOR ceased construction on 14 January 1991 after demanding payment and attaching a DPWH cease-and-desist notice dated 8 January 1991 which his office received and which his engineer purportedly received on 15 January 1991.
- Petitioner filed suit for collection and damages on 31 January 1991, and respondents later replaced petitioner with a new contractor and completed the project.
Contract Terms
- The Development and Construction Contract expressly fixed the Contract Price at P3,986,643.50 and required completion within 180 working days with a 45 working day grace period.
- Paragraph 17 of the Contract required mutual written agreement for changes, alterations or deviations in plans and specifications.
- Paragraph 18 of the Contract provided for adjustment of the contract price only in case of substantial increases in prices of specified materials such as cement and G.I. corrugated sheets and required specification of the particular items involved.
- Paragraph 20 of the Contract stipulated that matters not contained in the contract were excluded unless the parties agreed in writing.
- Paragraph 3 of the Contract obligated the contractor to provide his own materials, equipment, manpower, supervision and administration.
- Paragraph 7 of the Contract made the project owner responsible for securing permits and licenses at his own expense.
- Paragraph 6 of the Contract treated restraining orders or injunctions from legal authorities as fortuitous events or force majeure suspending the contract completion period.
Trial Court Ruling
- The trial court dismissed petitioner’s complaint and respondents’ counterclaims for insufficiency of basis after trial on the merits.
- The trial court found petitioner failed to comply with the Contract provision requiring specification of materials whose prices had increased and therefore had no basis for escalation.
- The trial court held that petitioner failed to prove authorization or agreement for the alleged additional works and that no written basis supported the P399,190.46 claim.
- The trial court denied the P39,000 claim for a twenty percent charge on filling materials because respondents purchased and delivered the materials themselves and no contract provision authorized such a charge.
- The trial court concluded that the plaintiff’s cause of action was insufficiently supported and ordered dismissal without pronouncement as to costs.
Court of Appeals Ruling
- The Court of Appeals affirmed dismissal of petitioner’s affirmative claims but found for respondents on their counterclaims and reversed and set aside