Title
Roblett Industrial Construction Corp. vs. Court of Appeals
Case
G.R. No. 116682
Decision Date
Jan 2, 1997
RICC leased equipment from CEC, incurred unpaid accounts, and entered an offsetting agreement. RICC claimed overpayment and unauthorized agreement, but courts upheld the agreement's validity, citing estoppel and insufficient evidence, ordering RICC to pay the balance with interest and fees.

Case Summary (G.R. No. 116682)

Factual Background

In 1985 Contractors Equipment Corporation (CEC) leased construction equipment to Roblett Industrial Construction Corporation (RICC). CEC presented a statement of account in the amount of P376,350.18 covering the period March 28, 1985 to July 12, 1985. Deductions of P3,440.80 and payments of P30,000.00 left a balance of P342,909.38. On 19 December 1985 RICC, through its Assistant Vice President for Finance Candelario S. Aller Jr., signed an Agreement with CEC that confirmed the account and reflected an offset of construction materials valued at P115,000.00, reducing the balance to P227,909.38. On 18 December 1985 RICC had delivered postdated checks totaling P10,000.00 which were dishonored when deposited, causing CEC to debit that amount and increase the claimed balance to P237,909.38. CEC sent a letter of demand on 24 July 1986 seeking payment by 31 July 1986. RICC requested thirty days to secure funds and later contended that it had in fact overpaid by approximately P12,000.00 based on Equipment Daily Time Reports for May 2 to June 14, 1985 which, at P540.00 per hour for 191 hours, yielded P103,140.00 as the correct rental obligation. RICC also asserted that the Agreement lacked Board approval and that Aller Jr. lacked authority to bind the corporation.

Trial Court Proceedings

CEC sued RICC for sum of money and the Regional Trial Court, Makati, rendered judgment on 19 December 1990 in favor of CEC. The trial court ordered RICC to pay P237,909.38 with legal interest from 31 July 1986 until full payment, P2,000.00 litigation expenses, twenty percent attorney’s fees, and costs of suit. The trial court found the Agreement valid and reflective of the parties’ true intention and held that RICC’s answer, not being under oath, deemed admission of the document’s genuineness under Section 8, Rule 8, Rules of Court. The court rejected RICC’s claim of full payment or overpayment, finding RICC’s daily time reports incomplete because they covered only May 2 to June 14, 1985, whereas CEC’s exhibits covered the entire lease period from March 28 to July 12, 1985.

Court of Appeals Disposition

On 29 July 1994 the Court of Appeals affirmed the trial court decision. The appellate court agreed that RICC had limited its assignment of error in the proceedings below to the question of full payment or overpayment and had not properly challenged the Agreement’s validity. The Court of Appeals upheld the trial court’s factual findings and application of the doctrine of estoppel in pais where RICC received the statement of account and the demand without timely protest.

Issues on Appeal to the Supreme Court

RICC presented two principal grounds in its petition: first, that the Agreement was unenforceable because Aller Jr. lacked authority to execute it on behalf of the corporation; and second, that RICC had fully paid, and in fact overpaid by about P12,000.00, its obligation to CEC on the basis of the daily time reports.

Parties’ Contentions

Petitioner argued that the Agreement was an unauthorized corporate act and therefore unenforceable, and that documentary proof in Exhibits “2” through “2-Z” established usage of only 191 hours, yielding a rental liability of P103,140.00 which, after the P115,000.00 offset, resulted in overpayment. Respondent CEC maintained that its statement of account for P376,350.18 covering March 28 to July 12, 1985 was received by RICC without protest, that the Agreement reflected the true transactions between the parties, and that RICC’s evidence was incomplete and limited to a portion of the lease period.

Supreme Court Ruling

The Supreme Court denied the petition and affirmed the decisions of the Court of Appeals and the Regional Trial Court. The Court held that RICC, having limited its assignment of error before the Court of Appeals to the issue of full payment or overpayment, could not thereafter assail the validity of the Agreement. The Court sustained the factual findings that RICC’s daily time reports were incomplete as they did not cover the entire lease period reflected in CEC’s statement of account, and that RICC’s conduct — receiving the statement and failing to object and asking for time to pay — gave rise to estoppel in pais precluding denial of the indebtedness.

Legal Basis and Reasoning

The Court applied Section 8, Rule 8, Rules of Court to treat RICC’s answer, which was not under oath, as an admission of the genuineness and due execution of the Agreement. The Court invoked Art. 1431, Civil Code on estoppel and Art. 1308, New Civil C

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.