Title
Philippine Export and Foreign Loan Guarantee Corp. vs. V.P. Eusebio Construction Inc.
Case
G.R. No. 140047
Decision Date
Jul 13, 2004
A construction joint venture in Iraq faced delays due to non-payment by the Iraqi government. Philguarantee, acting as a guarantor, paid under a performance bond but was denied reimbursement as VPECI was not in default. The Supreme Court ruled Philguarantee’s payment was undue and unenforceable.

Case Summary (G.R. No. 140047)

Contract Formation, Joint Venture, and Assignments

SOB awarded the Project to Ajyal Trading and Contracting Company. A joint venture agreement (7 Mar 1981) had 3‑Plex undertaking project execution with Ajyal earning a commission. Because 3‑Plex was not accredited by the Philippine Overseas Construction Board (POCB), it assigned its rights to VPECI (8 Apr 1981), and subsequently 3‑Plex and VPECI agreed to joint management (2 May 1981). The formal service contract between SOB and the joint venture (VPECI–Ajyal) was executed on 11 June 1981, with a completion term of 547 days (18 months) and a payment scheme providing 25% of project cost in Iraqi dinars and 75% in U.S. dollars.

Guarantee Structure and Issuance

SOB required a performance bond and an advance payment bond, respectively amounting to 5% and 10% of specified sums in Iraqi dinars. Philguarantee approved 3‑Plex/VPECI’s application and issued letters of guarantee addressed to Al Ahli Bank of Kuwait (as counter‑guarantee) to support Al Ahli’s counter‑guarantee to Rafidain Bank, which in turn would back the Rafidain/ SOB performance bond. Thus the security chain involved three layers: Philguarantee → Al Ahli Bank (Kuwait) → Rafidain Bank (Iraq) → SOB. The guarantees (Performance Bond Guarantee No. 81-194-F and Advance Payment Guarantee No. 81-195-F) were unconditional and irrevocable, dated from 25 May 1981 and secured by a Deed of Undertaking executed by the respondents and a surety bond issued by FIBICI.

Performance, Delays, and Extensions

Work commenced late (last week of Aug 1981) and did not meet the contractual completion date (15 Nov 1982). The guarantees and surety bond were extended repeatedly: the performance bond was extended multiple times up to 8 Dec 1986; the advance payment guarantee was extended and later cancelled after full refund by the joint venture; the surety bond was extended until 8 May 1987. By March 1986 the Project was approximately 51% complete, with remaining work largely consisting of electro‑mechanical and sanitary installations requiring imported equipment and foreign currency.

Telex Call, Diplomatic Efforts, and Petitioner’s Payments

On 26 October 1986 Al Ahli Bank issued a telex calling on the performance counter‑guarantee. VPECI protested and sought to have the call recalled, asserting that delay resulted primarily from SOB’s failure to pay the 75% portion in U.S. dollars and from Iraq’s lack of foreign exchange in the Iran‑Iraq war context, and informed Philguarantee that negotiations for a foreign loan might allow completion. Despite diplomatic exchanges, Central Bank authorization for remittance was issued (27 Aug 1987) and Philguarantee paid Al Ahli US$876,564 on 21 January 1988 (performance counter‑guarantee) and later US$59,129.83 on 6 May 1988 for interest and penalties. Philguarantee then demanded reimbursement from the respondents (letters sent 19 June 1991) and filed suit (9 July 1991) after nonpayment.

Procedural History and Lower Court Rulings

Philguarantee sued in the Regional Trial Court (Makati, Branch 58). The trial court dismissed Philguarantee’s complaint, holding that the guarantee had lapsed when first called and that Philguarantee failed to secure express consent from respondents for renewals/extensions; the court also found no valid default by the joint venture because SOB’s contractual violations rendered performance impossible and no prior demand by SOB had been shown. The trial court awarded attorney’s fees to respondents. The Court of Appeals affirmed (14 June 1999), emphasizing Philguarantee’s knowledge of project difficulties, SOB’s nonpayment in U.S. dollars, the existence of amounts retained by SOB that could be set off, and Philguarantee’s prior representations that payment would be inequitable. The Supreme Court denied the petition for review and affirmed the Court of Appeals.

Issues Presented to the Supreme Court

The Supreme Court addressed whether (1) Philguarantee, having issued Letter of Guarantee No. 81‑194‑F, was entitled to reimbursement from respondents under the deed of undertaking and surety bond; (2) Philguarantee could claim subrogation; and (3) it was equitable for Philguarantee to hold respondents liable given the surrounding circumstances.

Characterization of Philguarantee’s Liability: Guarantor, Not Surety

The Court analyzed the nature of Philguarantee’s obligation under Letter No. 81‑194‑F and distinguished guaranty from surety. Although the letter was phrased as unconditional and irrevocable and promised payment “on your first written or telex demand” in the event of VPECI’s default, the Court held Philguarantee remained a guarantor (secondary, conditional in operation) rather than a surety (primary and solidary). The Court emphasized that unconditional language in a guaranty does not convert the guarantor into a surety; suretyship arises only where the guarantor binds himself solidarily with the principal debtor or by the nature of the contract. The parties’ instruments and the nature of the undertaking indicated a guaranty.

Choice of Law, Applicable Rules on Default, and Presumption on Foreign Law

Because the project involved an Iraqi contracting party and performance in Iraq, Iraqi law bore a substantial connection to the transaction and could govern matters of time, place, manner of performance, and excuses for nonperformance. However, foreign law was not pleaded or proven; hence the processual presumption applied (foreign law presumed identical to Philippine law). The Court relied on Philippine substantive rules—particularly Article 1169 (last paragraph) of the Civil Code—stating that in reciprocal obligations neither party is in delay if the other is not ready to perform properly. The Court summarized general requisites for default: demandability and liquidation of the obligation, debtor’s delay attributable to the debtor, and the creditor’s demand for performance.

Findings on Non‑Default, Cause of Delay, and Extensions

Both trial court and Court of Appeals found that VPECI had not defaulted for causes imputable to it. The unfinished portion (48.3%) required imported equipment and foreign exchange, which Iraq did not provide in the required U.S. dollars as contractually agreed (75% in USD). Evidence showed SOB delayed and paid in Iraqi dinars, retention amounts existed, and negotiations for foreign loans (e.g., with Italian entities) had been pursued but failed due to Iraq’s foreign‑exchange difficulties and broader war conditions. SOB repeatedly allowed extensions and retained amounts subject to set‑off. The courts concluded SOB’s failures excused or prevented VPECI’s performance and that no prior demand by SOB had been shown before the bank call.

Guarantor Remedies, Excussion, Subrogation, and Waiver

Under Philippine law, a guarantor who pays for a debtor generally is entitled to indemnity from the debtor and is subrogated to the creditor’s rights (Arts. 2066–206

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.