Title
Philippine Export and Foreign Loan Guarantee Corp. vs. V.P. Eusebio Construction Inc.
Case
G.R. No. 140047
Decision Date
Jul 13, 2004
A construction joint venture in Iraq faced delays due to non-payment by the Iraqi government. Philguarantee, acting as a guarantor, paid under a performance bond but was denied reimbursement as VPECI was not in default. The Supreme Court ruled Philguarantee’s payment was undue and unenforceable.

Case Digest (G.R. No. 111107)

Facts:

  • Award and Joint Venture Formation
    • On 8 November 1980, the State Organization of Buildings (SOB), Ministry of Housing and Construction, Baghdad, Iraq, awarded the construction of the Institute of Physical Therapy-Medical Rehabilitation Center, Phase II (the Project), to Ajyal Trading and Contracting Company for ID 5,416,089.046.
    • On 7 March 1981, spouses Eduardo and Iluminada Santos, on behalf of 3-Plex International, Inc., entered a joint venture with Ajyal: 3-Plex would execute the Project; Ajyal would earn a 4% commission.
    • On 8 April 1981, 3-Plex assigned its rights under the joint venture to V.P. Eusebio Construction, Inc. (VPECI), duly registered with the Philippine Overseas Construction Board (POCB).
    • On 2 May 1981, 3-Plex and VPECI agreed that the Project would be under their joint management.
  • Guarantee Requirements and Issuance
    • SOB required performance and advance payment bonds: 5% and 10% of the contract price, respectively.
    • 3-Plex and VPECI applied to the Philippine Export and Foreign Loan Guarantee Corporation (PhilGuarantee) for counter-guarantees.
    • PhilGuarantee issued Letter of Guarantee No. 81-194-F (Performance Bond, ID 271,808.610) and No. 81-195-F (Advance Payment Bond, ID 541,608.901), secured by a Deed of Undertaking and a surety bond from First Integrated Bonding and Insurance Company, Inc.
    • Because SOB required a guarantee from Rafidain Bank (Iraq), a three-layer guarantee was arranged: PhilGuarantee → Al Ahli Bank of Kuwait → Rafidain Bank → SOB.
  • Contract Execution, Delays, and Extensions
    • On 11 June 1981, SOB and the joint venture executed the service contract for completion in 547 days.
    • Construction began late August 1981 and suffered slow progress; the Performance Bond and Advance Payment Bond were extended repeatedly through December 1986 and May 1984, respectively.
    • By March 1986, only 51.7% of work was done; remaining work required imported electro-mechanical materials, payable in US dollars, which Iraq could not provide.
  • Call on Guarantee and Petitioner’s Payments
    • On 26 October 1986, Al Ahli Bank of Kuwait called the performance bond counter-guarantee. VPECI protested, citing delays due to SOB’s failure to pay in US dollars and negotiated extensions.
    • On 14 April 1987, Al Ahli Bank telexed PhilGuarantee that it had paid Rafidain Bank US $876,564 under the guarantee and demanded reimbursement plus interest and expenses.
    • Despite VPECI’s requests to withhold payment pending diplomatic efforts, PhilGuarantee paid US $876,564 on 21 January 1988 and US $59,129.83 on 6 May 1988 for interest and penalties.
  • Judicial Proceedings
    • On 19 June 1991, PhilGuarantee demanded reimbursement of P 47,872,373.98 plus interest and attorney’s fees from respondents; they did not pay.
    • PhilGuarantee filed Civil Case No. 91-1906 on 9 July 1991 in the RTC of Makati; the trial court dismissed the complaint, ruling the guarantee had lapsed and respondents incurred no valid default.
    • The Court of Appeals, on 14 June 1999, affirmed the dismissal, adding that PhilGuarantee acted with full knowledge of SOB’s contractual violations and VPECI’s defenses.
    • PhilGuarantee filed a petition for review on certiorari to the Supreme Court.

Issues:

  • Whether PhilGuarantee, as guarantor, is entitled to reimbursement from respondents under the Deed of Undertaking and surety bond for amounts it paid under Letter of Guarantee No. 81-194-F.
  • Whether PhilGuarantee can claim subrogation to the rights of Al Ahli Bank and Rafidain Bank against respondents.
  • Whether it is inequitable and unjust to hold respondents liable under their Deed of Undertaking given the circumstances.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.