Case Summary (G.R. No. 185765)
Factual Background
The PHILIPPINE ECONOMIC ZONE AUTHORITY advertised for bids on October 4, 1997 for two new fire truck units with specified capacities. Three firms, including PILHINO SALES CORPORATION, participated. PILHINO won the contract at an agreed price of P2,900,000.00 per unit after negotiation. The contract required delivery of two FF3HP brand fire trucks within forty-five days of receipt of a purchase order. The contract also stipulated a penalty of one-tenth of one percent of the total contract price for each day of delay. A Purchase Order dated November 6, 1997 was issued to PILHINO, which thereafter failed to deliver the trucks.
Procedural History in the Trial Court
After formal demands dated July 27, 1998 and February 23, 1999 failed to produce delivery, PHILIPPINE ECONOMIC ZONE AUTHORITY filed a Complaint for rescission of contract and damages before the Regional Trial Court of Pasay City, docketed as Civil Case No. 00-0343 and raffled to Branch 108. The Regional Trial Court rendered judgment on November 2, 2005 in favor of the plaintiff. The trial court declared the contract rescinded, ordered forfeiture of the performance bond, awarded liquidated damages computed at the contractually stipulated rate commencing June 19, 1998, granted exemplary damages in the amount of PHP 100,000.00, and ordered costs against the defendant.
Court of Appeals Ruling
PILHINO appealed to the Court of Appeals. The Court of Appeals, in its May 2, 2008 Decision, partly granted the appeal by deleting the forfeiture of the performance bond and reducing the liquidated damages to PHP 1,400,000.00. The Court of Appeals found that PILHINO manifested acquiescence to the Purchase Order through submission of a Performance Bond and Indemnity Agreement, and acknowledged inability to meet specifications in a March 29, 1999 letter in which PILHINO offered new specifications at P3,600,000.00 per unit and expressed willingness to shoulder the price difference in lieu of penalty. Citing Articles 1229 and 2227 of the Civil Code, the Court of Appeals equitably reduced the liquidated damages to the difference between the original contract sum for two units (P5,800,000.00) and the price under the new specifications (P7,200,000.00), i.e., PHP 1,400,000.00. The Court of Appeals denied the petition for reconsideration in its November 25, 2008 Resolution.
Issues Presented
The petition to the Supreme Court raised two principal issues. First, whether a stipulation for liquidated damages contained in a contract may be enforced notwithstanding judicial rescission of the same contract. Second, assuming the stipulation survives rescission, whether the Court of Appeals correctly reduced the liquidated damages awarded to PHILIPPINE ECONOMIC ZONE AUTHORITY.
Parties' Contentions
PHILIPPINE ECONOMIC ZONE AUTHORITY argued that it suffered damage by reason of PILHINO's failure to deliver on time, that the contractual penalty of one-tenth of one percent per day was neither unreasonable nor contrary to law, and that the stipulated liquidated damages were freely agreed and should be enforced as written. PILHINO contended that rescission abrogated the contract ab initio and thereby negated the contractual stipulation for liquidated damages, so that the clause could not have separate life apart from the rescinded contract. PILHINO also relied on its March 29, 1999 offer to provide different specifications and to shoulder price differences as mitigation of damages.
Supreme Court's Analysis on Rescission and Liquidated Damages
The Court reviewed the nature of rescission under Article 1191 of the Civil Code, noting that rescission of reciprocal obligations implies mutual restitution but that Article 1191 expressly contemplates the payment of damages in either alternative of fulfillment or rescission. The Court surveyed its own jurisprudence in Spouses Velarde, Laperal v. Solid Homes, Inc., and related authorities to conclude that mutual restitution attendant to rescission does not automatically obliterate contractual stipulations on liquidated damages. The Court emphasized that when contracting parties expressly agreed upon the measure of damages, that stipulation constitutes the law between them and furnishes the factual anchor for judicial computation of damages even when rescission is decreed. The Court recognized that such stipulations remain subject to equitable reduction under Articles 1229 and 2227, but rejected the notion that rescission renders such clauses void as a matter of law.
Supreme Court's Analysis on the Reduction of Liquidated Damages
The Court examined the factual context in which PILHINO tendered its March 29, 1999 offer of alternative specifications and willingness to shoulder the price differential. The Court found that time was of the essence given the urgent public need for fire trucks, as underscored by the petitioner’s internal memorandum and the limited availability of serviceable units. By the time PILHINO attempted rectification, the petitioner had already filed the Complaint and was no longer in a position to accept contractual modifications arising from an originally publicly bidded contract. The Court stressed the impropriety of altering awarded publicly bidded contracts after award because such post-award modifications compromise the equal footing required among bidders. Given these circumstances, the Court held that the Court of Appeals erred in relying on the belated offer as a basis to equitably reduce the liquidated damages.
Disposition
The Supreme Court granted the Petition for Review on Certiorari. It reversed and set aside the Court of Appeals Decision dated May 2, 2008 and the November 25, 2008 Resolution, and reinstated the Regional Trial Court Decision dated November 2, 2005 in Civil Case No. 00-0343. The reinstated judgment ordered rescission of the contract, forfeiture of the performance bond, payment of liquidated damages at the contractual rate commencing June 19, 1998, exempla
...continue reading
Case Syllabus (G.R. No. 185765)
Parties and Procedural Posture
- PHILIPPINE ECONOMIC ZONE AUTHORITY was the petitioner and plaintiff below seeking rescission of contract and damages.
- PILHINO SALES CORPORATION was the respondent and defendant below accused of failing to deliver contracted fire trucks.
- The petition was filed under Rule 45, Rules of Court to review the Court of Appeals' May 2, 2008 Decision and November 25, 2008 Resolution.
- The petitioner sought reversal of the Court of Appeals rulings and reinstatement of the Regional Trial Court of Pasay City's November 2, 2005 Decision.
Key Factual Allegations
- On October 4, 1997, petitioner published an invitation to bid for the acquisition of two (2) brand new fire truck units with specified capacities and accessories.
- Three companies bid and PILHINO secured the contract to supply the two (2) fire trucks.
- The contract price was initially P3,000,000.00 per truck and was reduced by negotiation to P2,900,000.00 per truck.
- The contract required delivery of the two (2) FF3HP brand fire trucks within 45 days of receipt of a purchase order.
- The contract contained a penalty clause imposing liquidated damages at the rate of one-tenth of one percent of the total contract price for each day of delay.
- Petitioner issued a purchase order dated November 6, 1997, and PILHINO failed to deliver the trucks as committed.
- Petitioner made formal demands on July 27, 1998 and February 23, 1999, and subsequently filed Civil Case No. 00-0343 for rescission of contract and damages.
Contract Terms
- The parties agreed on a unit price of P2,900,000.00 and a total contract price of Php 5,800,000.00 for the two (2) units.
- The delivery obligation was within 45 days from receipt of the purchase order.
- The contract stipulated a penalty of one-tenth of one percent of the total contract price for each day of delay.
- PILHINO submitted a performance bond and an indemnity agreement allegedly evidencing its assent to the purchase order.
Procedural History
- The Regional Trial Court, Branch 108, Pasay City, rendered a Decision dated November 2, 2005 in favor of petitioner ordering rescission, forfeiture of the performance bond, exemplary damages of Php 100,000.00, and liquidated damages at the contractual rate commencing June 19, 1998.
- PILHINO appealed to the Court of Appeals, which in its May 2, 2008 Decision partly granted the appeal by deleting the forfeiture of the performance bond and reducing liquidated damages to P1,400,000.00.
- The Court of Appeals denied petitioner’s motion for reconsideration in its November 25, 2008 Resolution.
- Petitioner filed the present petition for review on certiorari seeking reinstatement of the RTC decision.
Issues Presented
- Whether an award based on a contractually stipulated liquidated damages clause is proper notwithstanding judicial rescission of the contract.
- Whether the Court of Appeals properly reduced the contractually stipulated liquidated damages and deleted the forfeiture of the performance bond.
Contentions of the Parties
- Petitioner contended that it suffered cognizable damage from respondent's delay and that the contractual penalty was valid, reasonable, and f