Title
Philippine Charter Insurance Corp. vs. Petroleum Distributors and Services Corp.
Case
G.R. No. 180898
Decision Date
Apr 18, 2012
A case involving financial disputes, construction delays, and alleged violations, with references to prior rulings and testimonies, addressing accountability and damages.

Case Summary (G.R. No. 180898)

Petitioner, Respondent and Procedural Posture

PCIC (surety) filed a petition for review under Rule 45 contesting the Court of Appeals’ affirmance with modification of an RTC judgment that had held FCC and PCIC jointly and severally liable for damages arising from FCC’s delay in completing the Park aN Fly project. Only PCIC appealed to the Supreme Court; the Court limited its discussion to PCIC’s liability.

Key Dates

Contract executed: January 27, 1999.
Construction commencement: February 1, 1999.
PERT-CPM milestones: Phase 1 completion May 17, 1999; Phase 2 completion October 20, 1999; overall turnover scheduled October 21, 1999 (RTC: completion not later than October 15, 1999).
MOA and security instruments: Deed of assignment and chattel mortgage dated September 10, 1999; MOA dated September 10, 1999; performance bond extended to March 2, 2000.
Termination by PDSC: December 3, 1999.
Trial court decision: January 12, 2004.
CA decision: July 31, 2007 (denial of motions for reconsideration on December 28, 2007).
Supreme Court decision: April 18, 2012. Applicable constitutional framework: 1987 Constitution.

Applicable Law and Contractual Provisions

Governing law: Civil Code principles on obligations and contracts (Articles cited in record include Arts. 1292, 1306, 2047, 2226). Contractual terms: Building Contract Article 2 provided that time, quality, and reduced cost were the essence; required completion within a fixed period; and stipulated liquidated damages of 1/10 of 1% of the contract price per day of delay, described expressly as liquidated damages and not a penalty. The Performance Bond expressly guaranteed “full and faithful performance” by FCC and limited the surety’s liability to the bond face.

Contractual Undertakings and Bond Coverage

The Building Contract imposed strict time obligations, prohibited extensions for ordinary procurement delays except for force majeure, and prescribed liquidated damages for delay. The performance bond issued by PCIC expressly secured the full and faithful performance of FCC’s obligations under the building contract and limited PCIC’s exposure to the bond face amount. The bond therefore created a direct surety obligation in favor of PDSC, contingent on FCC’s failure to perform.

Project Execution, Delays and Interim Measures

Construction began February 1, 1999. PDSC tracked progress under the PERT-CPM schedule and observed successive delays: initial 16 days behind schedule, increasing to 30 and then 60 days. PDSC issued reminders and notices to FCC to catch up. On September 10, 1999 FCC assigned receivables from Caltex and executed a chattel mortgage in favor of PDSC as additional security; on the same day FCC and PDSC executed a memorandum of agreement (MOA) revising the work schedule. The performance bond was extended to March 2, 2000.

Termination, Claims and Court Proceedings

PDSC formally terminated the contract on December 3, 1999 for failure to accomplish the project within the agreed period. It demanded payment of liquidated damages (PDSC computed P9,149,962.02) and claimed under the performance bond. After receiving no response, PDSC filed suit against FCC and its officers for damages, recovery/foreclosure of security, and later impleaded PCIC via supplemental complaint seeking payment under the bond up to its face.

Defenses of FCC and PCIC

FCC’s defenses included: (a) the contract price had effectively been reduced to P19,809,822.12 due to PDSC’s sourcing/subcontracting; (b) the September 10, 1999 MOA and related arrangements constituted waiver or extinguishment of PDSC’s claims; and (c) delay was attributable in part to PDSC. PCIC’s defenses included: (a) a performance bond answers only for actual/compensatory damages and not for liquidated damages (liability determined by the bond’s terms); (b) the bond had expired on October 15, 1999 and any extension to March 2, 2000 was not binding without PCIC’s consent; (c) the MOA extinguished or waived PDSC’s claims against PCIC; (d) any liability of PCIC should be proportionate to other sureties; and (e) certain receipts (Caltex receivable P2,793,000.00 and auction proceeds P662,836.50) should be deducted from any award.

Trial Court Ruling

The RTC found FCC guilty of delay and held FCC and PCIC jointly and severally liable, ordering payment of P9,000,000.00 as damages plus attorney’s fees and interest. FCC and PCIC appealed.

Court of Appeals Ruling and Modifications

The Court of Appeals agreed that FCC incurred delay but modified the liquidated damages computation, applying the reduced contract price of P19,809,822.12 as the base. The CA adjudged FCC, its responsible officers, and PCIC solidarily liable to pay liquidated damages of P3,882,725.13 (6% interest from January 10, 2000), attorney’s fees of P50,000.00, and costs of suit, with PCIC’s liability not to exceed the bond face of P6,828,329.66. The CA also expressly allowed deduction of the Caltex receivable and auction proceeds from the award.

Issues Presented to the Supreme Court

PCIC raised three principal issues before the Supreme Court: (1) whether the performance bond rendered PCIC liable for liquidated damages (or only for actual/compensatory damages); (2) whether the September 10, 1999 MOA between PDSC and FCC, made without PCIC’s consent, extinguished PCIC’s obligation under the bond (novation or discharge); and (3) whether the sums P2,793,000.00 (Caltex receivable) and P662,836.50 (auction proceeds) should be deducted from the liquidated damages award.

Supreme Court Analysis — Surety Liability for Liquidated Damages

The Court affirmed that the performance bond guaranteed FCC’s “full and faithful” performance and thus gave PDSC the right to proceed against PCIC following FCC’s default. The Court reiterated that suretyship is accessory to the principal obligation yet creates a direct, solidary liability of the surety to the obligee. Citing Civil Code Article 2047 and controlling jurisprudence, the Court held that PCIC’s liability arose upon FCC’s non‑performance and that the bond’s language authorized PDSC to demand payment for the principal obligation’s breach. The Court rejected PCIC’s contention that the bond only covered actual/compensatory damages, concluding the bond’s coverage of “full and faithful performance” encompassed the creditor’s contractual remedies, includ

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.