Case Digest (G.R. No. 129824)
Facts:
On January 27, 1999, PETROLEUM DISTRIBUTORS & SERVICES CORPORATION (PDSC) engaged N.C. Francia Construction Corporation (FCC) to build the Park N Fly building in Pasay City for P45,522,197.72 with completion by October 15, 1999 and a contractual liquidated damages clause (Art. 2.3). FCC procured Performance Bond No. 31915 for P6,828,329.66 from PHILIPPINE CHARTER INSURANCE CORPORATION (PCIC) as surety; delays ensued, PDSC terminated the contract on December 3, 1999, sued FCC and later impleaded PCIC, and the RTC awarded PDSC damages; the CA modified the award and held FCC and PCIC solidarily liable with deductions for assigned receivables and auction proceeds, and PCIC appealed to the Supreme Court.Issues:
- Is PCIC liable for liquidated damages under Performance Bond No. 31915?
- Did the September 10, 1999 Memorandum of Agreement (MOA) between PDSC and FCC extinguish or novate PCIC’s liability under the bond?
- Should the sums of P2,793,000.00 and P662,836.50 be deducted from
Case Digest (G.R. No. 129824)
Facts:
- Background and parties
- Petroleum Distributors & Services Corporation (PDSC), owner/obligee of the Project.
- N.C. Francia Construction Corporation (FCC), contractor/principal, represented by Emmanuel T. Francia.
- FCC officers who signed an Undertaking of Surety: Natividad Francia, Emmanuel C. Francia, Jr., Anna Sheila C. Francia, San Diego Felipe G. Bermudez, Emmanuel T. Francia, Charlemagne C. Francia, and Ruben G. Caperina.
- Philippine Charter Insurance Corporation (PCIC), surety, issuer of Performance Bond No. 31915.
- The Building Contract and bond
- Building Contract dated January 27, 1999 for construction of a four‑storey commercial/parking complex known as Park N Fly, located at MIA Road cor. Domestic Road, Pasay City.
- Contract price stated as PHP 45,522,197.72; work to commence February 1, 1999; completion by October 15, 1999 or within 259 calendar days.
- Project schedule under PERT‑CPM: Phase 1 completion May 17, 1999; Phase 2 May 18 to October 20, 1999; project turnover October 21, 1999.
- Contract provision (Art. 2.3) for liquidated damages: one‑tenth (1/10) of one percent (1%) of the contract price for every day of delay, characterized as liquidated damages and not penalty.
- Performance Bond No. 31915 issued by PCIC in the face amount of PHP 6,828,329.66 to secure full and faithful performance; bond stated liability of surety shall not exceed face value.
- Course of performance and initial problems
- Construction commenced February 1, 1999.
- PDSC sourced materials and subcontracted various phases to obtain lowest cost and expedite work, which FCC later said reduced the contract price substantially to PHP 19,809,822.12.
- During Phase 1, FCC fell behind schedule: 16 days, then 30 days, then 60 days delay despite PDSC letter of March 25, 1999 warning of liquidated damages.
- On September 10, 1999 FCC executed a Deed of Assignment (portion of receivables from Caltex) and a chattel mortgage (conveying construction equipment) in favor of PDSC as additional security.
- September 10, 1999 Memorandum of Agreement and bond extension
- On September 10, 1999 PDSC and FCC executed a Memorandum of Agreement (MOA) revising the work schedule; MOA stated other terms of the Building Contract not inconsistent remain in full force and effect.
- Performance Bond No. 31915 was extended to March 2, 2000 per Exhibit N‑1.
- Termination, demands and proceedings
- PDSC, by letter dated December 3, 1999, terminated the Building Contract under Article 12, Paragraph 12.1 for failure to accomplish the project within the agreed period.
- PDSC demanded liquidated damages of PHP 9,149,962.02 from FCC and its officers, and sought remuneration from PCIC under the performance bond.
- PDSC filed a complaint before the RTC for damages, recovery/foreclosure and sought writs of replevin and attachment; later filed a supplemental complaint impleading PCIC claiming coverage under Performance Bond No. 31915 for PHP 6,828,329.66.
- Defenses of FCC and PCIC
- FCC admitted the contract but alleged: (a) PDSC's subcontracting and sourcing reduced the contract price to PHP 19,809,822.12; (b) the September 10, 1999 MOA modified obligations and caused PDSC to assume costs; (c) delay was attributable to both parties; (d) a progress billing dispute where PDSC agreed to shoulder subsequent expenses and use FCC equipment.
- PCIC asserted: (a) as surety it was not a principal obligor; liability under the bond was conditional, subsidiary, and limited to terms of the bond; (b) bond expired October 15, 1999 and extension to March 2, 2000 was without its knowledge/consent; (c) the September 10, 1999 MOA discharge...(Subscriber-Only)
Issues:
- Primary legal questions presented by PCIC's petition
- Whether PCIC is liable under Performance Bond No. 31915 for liquidated damages where the bond ostensibly answers only for actual and compensatory damages.
- Whether, assuming liability for liquidated damages, such award is iniquitous or unconscionable and whether Article 2227, Civil Code and *Palmares v. Court of Appeals, 288 SCRA 422* require reduction or denial.
- Whether the September 10, 1999 MOA between PDSC and FCC, entered without PCIC's knowledge or consent, discharged PCIC from liability under the bond pursuant to Article 2079, Civil Code.
- Secondary and accounting issues
- Whether the sums of PHP 2,793,000.00 (receivable assigned from Caltex...(Subscriber-Only)
Ruling:
- (Subscriber-Only)
Ratio:
- (Subscriber-Only)