Title
National Grid Corporation of the Philippines vs. Manila Electric Company
Case
G.R. No. 239829
Decision Date
May 29, 2024
National Grid Corporation challenged the Court of Appeals' reversal of a decision involving the sale of subtransmission assets to Meralco, asserting that essential consortium requirements under the EPIRA were ignored.

Case Summary (G.R. No. 239829)

Factual Background

On December 12, 2011, TRANSCO and Meralco executed a Contract to Sell covering four subtransmission lines/assets (STAs): the Dasmarinas-Abubot-Rosario 115 kV Line, Rosario substation equipment, Tayabas 115 kV switchyard, and Ternate substation equipment. TRANSCO and Meralco filed a Joint Application with the ERC on April 17, 2012 seeking approval of the sale. NGCP later filed a Petition for Intervention on June 29, 2015 asserting it had not been informed of the sale and that it had incurred improvement and upgrade costs in operating the subject STAs which merited consideration in the disposition.

Proceedings before the ERC

The ERC conducted hearings on the Joint Application and on April 22, 2013 rendered a Decision approving the sale with modification. It approved the sale of the Tayabas Switchyard and Ternate equipment in the aggregate amount of PHP 109,186,604.30, but disapproved the sale of the Dasmarinas-Abubot-Rosario 115 kV Line and Rosario substation equipment (the DAR Assets). The ERC reasoned that the DAR Assets served more than one distribution utility, including the Cavite Economic Zone (CEZ) managed by the Philippine Economic Zone Authority (PEZA), and that Section 8 of the EPIRA required formation of a consortium or juridical entity among connected distribution utilities as a prerequisite to acquisition.

ERC orders and subsequent motions

Both Meralco and TRANSCO moved for partial reconsideration and the ERC denied those motions in orders of May 5, 2014 and June 16, 2014. Meralco subsequently sought to reopen proceedings after PEZA communicated a legal impediment to forming a consortium; the ERC gave due course to that motion but ultimately denied it in its March 4, 2015 Order, adhering to the position that the consortium requirement under Section 8 of the EPIRA applied regardless of PEZA’s waiver or claimed legal constraints.

ERC technical determination and reclassification

During the administrative proceedings the ERC considered technical evidence that the DAR 115 kV Line would be connected to a 40 MW generator and concluded that the connection transformed the line’s function from subtransmission to transmission. The ERC invoked Article III, Section 2 of ERC Resolution No. 15, Series of 2011, which classifies as transmission assets those lines that allow transmission from one or more directly connected generators, and ruled that the DAR Assets should be reclassified as transmission assets and thus could no longer be subject of sale to a distribution utility.

Court of Appeals original ruling

Meralco filed a petition for review under Rule 43 with the Court of Appeals. On August 12, 2016 the CA dismissed the petition. The CA held, on procedural grounds, that the reglementary time to appeal ran from receipt of the ERC’s Third Order because the ERC had given due course to the Motion to Re-open. On the merits the CA affirmed the ERC’s interpretation that Section 8 of the EPIRA required, as a mandatory prerequisite, formation of a consortium where two or more distribution utilities were connected to an STA.

Court of Appeals amended decision

Meralco moved for reconsideration before the CA. On September 15, 2017 the CA issued an Amended Decision granting reconsideration, reversing the ERC and approving the sale of the DAR Assets to Meralco. The CA reasoned that PEZA’s waiver of its right to acquire the DAR Assets was valid because the waiver concerned a right or privilege rather than an obligation, and that the waiver effectively dispensed with the consortium requirement. The CA further held that Meralco’s acquisition would serve public interest and that the ERC’s reclassification and its rate impact findings were not persuasive grounds to deny the sale.

Issues raised to the Supreme Court

NGCP sought review by Rule 45 and presented issues whether the CA had jurisdiction to entertain the petition; whether the CA erred in concluding that the consortium and franchise requirements under Section 8 of the EPIRA could be waived by a distribution utility; whether the CA effectively engaged in judicial legislation; whether the CA improperly overturned consistent ERC practice; and whether the DAR Assets were transmission assets that could no longer be divested.

Supreme Court on jurisdiction

The Court affirmed that the CA possessed jurisdiction to entertain Meralco’s petition. It held that the fifteen-day reglementary period to appeal to the CA began to run from receipt of the ERC’s Third Order because the ERC had given due course to Meralco’s Motion to Re-open, entertained comments from TRANSCO, NGCP, and PEZA, and thus only upon issuance of the Third Order did the ERC finally dispose of the case.

Supreme Court’s interpretation of Section 8, paragraph 6 of the EPIRA

The Court construed Section 8 of the EPIRA as clear and unambiguous. It applied the plain-meaning rule and verba legis principles, observing that the use of the word “shall” demonstrated a mandatory requirement. The Court held that where two or more distribution utilities are connected to a subtransmission asset, those utilities must form a consortium or juridical entity and that such consortium must obtain a franchise from the ERC before a transfer can be approved. The Court rejected the CA’s view that PEZA’s waiver could dispense with the consortium requirement, reasoning that allowing circumvention by waiver would defeat the statutory scheme. The Court noted that the EPIRA itself contemplates flexibility in the consortium’s subscription rights—paragraph 7 permits proportional subscription rights “unless otherwise agreed by the parties”—and that a distribution utility could limit its participation within the consortium rather than avoid consortium formation entirely. The Court also observed that Rule 6, Section 8(e) of the EPIRA IRR provides that where a distribution utility refuses to acquire assets, TRANSCO is deemed in compliance with its obligation to sell, but that provision pertains to TRANSCO’s obligation and does not render the consortium requirement optional for distribution utilities.

Deference to ERC factual and technical findings

The Court gave substantial weight to the ERC’s factual and technical determinations. It reiterated the principle that administrative agencies with technical expertise are entitled to deference in matters within their competence. Applying ERC Resolution No. 15, Series of 2011, Article III, Section 2, the Court affirmed the ERC’s conclusion that the DAR Assets, by reason of connection to a generator, had the technical and functional character of transmission assets and therefore were not suitable for sale to a distribution utility. The Court held that reliance on formal classification alone would strip the ERC of its authority to apply technical criteria in approving div

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.