Title
National Grid Corporation of the Philippines vs. Manila Electric Company
Case
G.R. No. 239829
Decision Date
May 29, 2024
National Grid Corporation challenged the Court of Appeals' reversal of a decision involving the sale of subtransmission assets to Meralco, asserting that essential consortium requirements under the EPIRA were ignored.
A

Case Digest (G.R. No. 239829)

Facts:

  • Background and Contract to Sell
    • On December 12, 2011, the National Transmission Corporation (TRANSCO) and Manila Electric Company (Meralco) entered into a Contract to Sell involving several subtransmission assets (STAs): Dasmariñas-Abubot-Rosario 115 kV Line, Rosario Substation Equipment, Tayabas 115 kV Switchyard, and Ternate Substation Equipment.
    • On April 17, 2012, TRANSCO and Meralco jointly filed an application with the Energy Regulatory Commission (ERC) seeking approval for the sale of the subject STAs under their contract.
    • ERC found the application sufficient and set a hearing on July 4, 2012.
  • Intervention and Additional Claims
    • On June 29, 2015, National Grid Corporation of the Philippines (NGCP) filed a Petition for Intervention claiming it was not informed about the sale.
    • NGCP cited its authority and responsibility under the EPIRA to operate, maintain, and manage the national transmission system.
    • NGCP alleged it incurred improvement and upgrade costs on the STAs which were not included in the sale contract, claiming Meralco should pay these additional costs.
    • The ERC granted NGCP’s petition for intervention.
  • ERC Decision on Sale of Assets (April 22, 2013)
    • ERC approved with modifications the joint application to sell certain STAs to Meralco for PHP 109,186,604.30.
    • Specifically, the sale of Tayabas 115 kV Switchyard and Ternate Substation Equipment was approved.
    • The sale of Dasmariñas-Abubot-Rosario 115 kV Line and Rosario Substation Equipment (DAR Assets) was disapproved.
    • ERC ruled that DAR Assets served not only Meralco but also Cavite Economic Zone (CEZ), managed by the Philippine Economic Zone Authority (PEZA).
    • Per Section 8 of EPIRA, where two or more distribution utilities are connected, a consortium or juridical entity must be formed by all utilities as a prerequisite for acquisition.
    • ERC mandated that Meralco and TRANSCO must file a new application involving a consortium with CEZ.
  • Motions for Reconsideration and ERC Orders
    • Meralco and TRANSCO filed partial motions for reconsideration contesting the requirement for a consortium and citing PEZA’s waiver of rights in favor of Meralco.
    • On May 5, 2014, ERC denied motions, holding the consortium requirement mandatory with no right to abdication through waiver.
    • ERC ordered the DAR Assets to be reverted to TRANSCO’s Regulatory Asset Base.
    • Meralco’s subsequent motion for reconsideration and clarification was denied on June 16, 2014.
    • Meralco attempted to form a consortium but PEZA cited legal impediments.
    • Meralco filed a Motion to Re-open Proceedings raising the new substantive issue of PEZA’s inability to join consortium; this was denied by ERC on March 4, 2015.
  • Court of Appeals Proceedings
    • Meralco filed a petition for review with the Court of Appeals (CA).
    • CA initially dismissed petition (August 12, 2016), ruling the ERC’s Third Order finally disposed of case, triggering the reckoning of the appeal period.
    • CA affirmed the consortium requirement under Section 8 of EPIRA as mandatory.
    • CA invalidated PEZA’s waiver as it involved a non-waivable function mandated by law.
    • CA agreed that DAR Assets should be reclassified as transmission assets, thus not subject to sale to Meralco.
    • CA denied Meralco’s motion for reconsideration initially but later granted it on September 15, 2017, reversing earlier dismissal and declaring the sale of DAR Assets to Meralco approved.
    • CA reasoned that PEZA’s waiver dispensed with consortium requirement and acquisition by Meralco would benefit consumers.
  • NGCP’s Motion for Reconsideration
    • NGCP filed motions for reconsideration and for inhibition, denied on May 31, 2018.
    • NGCP then filed the present Petition for Review on Certiorari before the Supreme Court.

Issues:

  • Whether the Court of Appeals had jurisdiction to entertain and reverse a final and executory decision of the ERC.
  • Whether the CA erred in ruling the consortium and franchise requirements of Section 8 of EPIRA may be waived by a distribution utility.
  • Whether the CA's interpretation of Section 8 of EPIRA amounted to judicial legislation.
  • Whether the CA erred in overturning the ERC’s rulings, which have been consistently applied since EPIRA’s enactment.
  • Whether the DAR Assets are transmission assets, which may no longer be divested to any other entity.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.