Title
Supreme Court
Megaworld Globus Asia Inc. vs. DSM Construction and Development Corp.
Case
G.R. No. 153310
Decision Date
Mar 2, 2004
Construction dispute over condominium project; CIAC awarded DSM Construction P62.76M, upheld by courts, citing delays not solely its fault.

Case Summary (G.R. No. 224626)

Contracts and Agreements

Megaworld entered into three separate contracts with DSM Construction for various works, including architectural finishing, interior finishing, and the supply and installation of kitchen cabinets and closets. A significant clause in these contracts outlined "Retention Money," a portion of the total contract price (10% in this case) retained by the project owner to ensure the contractor's performance during the defect liability period.

Interim Agreement and Payment Issues

On February 21, 2000, an Interim Agreement was signed, establishing a new payment schedule totaling PHP 53 million, with releases contingent upon the turnover of units. Disputes later arose regarding varying amounts payable, leading DSM Construction to file a complaint for compulsory arbitration before the Construction Industry Arbitration Commission (CIAC) for an outstanding balance of approximately PHP 97 million, citing various causes for this amount.

Megaworld's Defenses and Counterclaims

Megaworld primarily posited defenses based on alleged delays in unit turnover and questioned the quality of work delivered by DSM Construction. This led to a counterclaim for loss of profits and liquidated damages amounting to approximately PHP 85 million. Prudential Guarantee and Assurance acted as a third-party respondent due to a performance bond issued to Megaworld.

CIAC Proceedings and Decision

Following an evidentiary hearing, the CIAC issued a decision on September 28, 2001, awarding PHP 62,760,558.49 to DSM Construction and PHP 9,473,799.46 to Megaworld. Megaworld subsequently sought review from the Court of Appeals, raising substantial questions about the findings of the CIAC, including the level of accomplished work and the basis for awarding liquidated damages.

Court of Appeals Rulings

On February 14, 2002, the Court of Appeals affirmed the CIAC decision, emphasizing that the review of CIAC awards typically pertains to questions of law. It noted that the CIAC findings were substantiated by substantial evidence. Megaworld's motion for reconsideration was denied, prompting the case's elevation to the Supreme Court.

Supreme Court's Analysis

The Supreme Court analyzed Megaworld’s claims, emphasizing that the issues mainly involved facts rather than legal questions. Under Section 19 of Executive Order No. 1008, CIAC awards are generally deemed final and appealable only on legal grounds; consequently, Megaworld's disputes around factual determinations were found to not substantiate sufficient grounds to overturn the CIAC and Court of Appeals' findings.

Findings on Key Issues

The Court upheld the CIAC's finding that DSM Construction achieved a 95.

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.