Case Digest (G.R. No. 153310) Core Legal Reasoning Model
Facts:
The case revolves around Megaworld Globus Asia, Inc. as the petitioner and DSM Construction and Development Corporation along with Prudential Guarantee and Assurance, Inc. as respondents. This legal matter originates from the construction of a condominium project titled "The Salcedo Park," located in Salcedo Village, Makati City, where Megaworld entered into three contracts with DSM Construction: for Architectural Finishing Works, Interior Finishing Works, and for Supply and Installation of Kitchen Cabinets and Closets. Initially, the total contract price was set at P300 million, later reduced to P240 million after the exclusion of certain items.
A key clause in their contracts included Retention Money, calculated at 10% of all billings, withheld for guaranteed performance during a defect-liability period of twelve months after the project completion. The project had a designated completion timeline from August 1, 1997, to July 31, 1998. An Interim Agreement was execu
...
Case Digest (G.R. No. 153310) Expanded Legal Reasoning Model
Facts:
- Project and Contract Formation
- Megaworld Globus Asia, Inc. (petitioner) undertook the construction of a condominium project known as “The Salcedo Park” in Makati City.
- Three separate contracts were entered into with DSM Construction:
- Contract for Architectural Finishing Works
- Contract for Interior Finishing Works
- Contract for the Supply and Installation of Kitchen Cabinets and Closets
- The original contract price of P300 million was later reduced to P240 million after certain items were deleted.
- Interim Agreement and Payment Adjustments
- On February 21, 2000, DSM Construction and Megaworld signed an Interim Agreement modifying the schedule for the turnover of units (from the 26th to the 40th floor).
- Under the Interim Agreement:
- A new payment arrangement was established, including an immediate release of a portion of the amount and subsequent installment payments tied to the turnover of units.
- A portion of the retention money (originally set at 10% of the contract price) was addressed, with half of it considered within the new arrangement.
- Disputes and Claims
- DSM Construction filed a complaint for compulsory arbitration, claiming a payment of approximately P97,743,808.33 for:
- Outstanding balances of the three contracts
- Variation works, labor escalation, and preliminaries/loss and expense
- Earned retention money, interests, and attorney’s fees
- Megaworld, in its Answer, raised defenses including:
- Allegations of delays primarily caused by DSM Construction, although DSM contended that delays partly arose from uncoordinated efforts of other contractors
- The poor quality of work by DSM Construction
- Megaworld also counterclaimed for:
- Loss of profits
- Liquidated damages
- Costs for take-over and rectification, among other expenses
- Prudential Guarantee and Assurance, Inc.—the guarantor through a performance bond—was impleaded as a third-party respondent.
- Arbitration and Appellate Proceedings
- The Construction Industry Arbitration Commission (CIAC) conducted the arbitration based on the terms agreed upon in signed Terms of Reference, which summarized claimed facts, documentary evidence, and issues for resolution.
- The Arbitral Tribunal rendered its Decision on September 28, 2001, awarding:
- P62,760,558.49 to DSM Construction
- A lesser award to Megaworld on its counterclaims
- Megaworld sought a review under Rule 43 of the Rules of Civil Procedure before the Court of Appeals, contesting:
- The computation of DSM Construction’s work accomplishment
- Findings on delays, liquidated damages, and the evaluation of claims for variation works, preliminaries, and the retention money
- The Court of Appeals affirmed the CIAC award on February 14, 2002, emphasizing that only questions of law may ordinarily be raised on appeal from a CIAC award, while also noting that the tribunal’s findings were amply supported by evidence.
- Grounds for Petition to the Supreme Court
- Megaworld asserted that:
- The Court of Appeals erred by limiting its review solely to questions of law, despite the presence of grave questions involving both fact and law.
- The findings of the appellate court were based on an uncritical adoption of the CIAC’s decision, which was allegedly unsupported by competent and admissible evidence.
- There was a denial of its right to administrative due process.
- Ultimately, the Court had to decide whether these arguments would merit a reversal of the established findings based on the CIAC and appellate decisions.
Issues:
- Accomplishment Level of Work
- Whether DSM Construction’s stated accomplishment level of 95.56% (as determined by the independent surveyor Davis Langdon & Seah) accurately reflected the progress of the works.
- The credibility of conflicting computations compared to Megaworld’s assertion that the actual completion was significantly lower.
- Delay and Liquidated Damages
- Whether the delays in the project should be attributed solely to DSM Construction or also to the actions (or inactions) of other trade contractors and Megaworld’s failure to turn over preceding works.
- Whether DSM Construction was entitled to recover losses based on extension of time provided by the contractual provisions and the Interim Agreement, thereby negating Megaworld’s claim for liquidated damages.
- Contract Price Balance and Retention Money
- Whether DSM Construction was entitled to claim the outstanding balance of the contract price and the remaining retention money after accounting for payments already made under the Interim Agreement.
- Whether Megaworld’s contention that additional payments should be negated due to its own subsequent expenditures was sustainable.
- Valuation of Variation Works
- Whether the award for variation works should be based on DSM Construction’s full claim or be limited as per the evaluation by DLS.
- How the lack of proper documentation or failure by Megaworld’s project manager in forwarding variation orders influenced the final award.
- Claim for Preliminaries/Loss and Expense
- Whether DSM Construction’s claim for preliminaries and loss and expense was valid, considering alleged non-compliance with the stipulated two-month submission requirement.
- Whether Megaworld’s waiver of the submission requirement (as evidenced by subsequent evaluations) justified DSM Construction’s claim.
- Scope of Judicial Review and Due Process Allegations
- Whether the appellate court erred in reviewing factual findings of an arbitration award (especially given the principle that only questions of law may be raised).
- Whether Megaworld’s due process rights were violated in the arbitration proceedings due to alleged bias and inadequate consideration of evidence.
Ruling:
- (Subscriber-Only)
Ratio:
- (Subscriber-Only)
Doctrine:
- (Subscriber-Only)