Title
Filinvest Alabang, Inc. vs. Century Iron Works, Inc.
Case
G.R. No. 213229
Decision Date
Dec 9, 2015
Filinvest withheld payment from Century Iron Works for completed construction, citing substandard work and additional costs. Courts ruled Filinvest estopped due to Certificate of Completion, liable for retention fee, deductions, and additional works under lump sum contract terms.

Case Summary (G.R. No. 156851-55)

Factual Background

In 1997 and 1998, the petitioner awarded the respondent contracts including services for the metal works of the Filinvest Festival Supermall, valued at P29,000,000.00. Following project completion, the respondent asserted claims against the petitioner for unpaid amounts totaling P1,392,088.68, including a retention fee, damages for an alleged substandard performance, and costs associated with an additional scenic elevator enclosure. The respondent subsequently initiated legal proceedings to recover these amounts in Civil Case No. 68850 in the Regional Trial Court (RTC) of Pasig City.

RTC Ruling

The RTC, in its decision dated August 3, 2010, partially ruled in favor of the respondent by granting a claim for P227,500.00, while denying the remaining claims. The RTC determined that the petitioner was estopped from claiming damages for substandard workmanship, given its issuance of a Certificate of Completion and Acceptance. However, it found that the nature of the contract was a lump sum, thus ruling that the petitioner was not liable for the costs of the scenic elevator enclosure.

CA Ruling

Upon appeal, the Court of Appeals (CA) issued a modified ruling on December 27, 2013, requiring the petitioner to pay the previously denied amounts of P40,880.00 and P1,123,708.68, along with legal interest. The CA concurred with the RTC's estoppel ruling but disagreed on the contract's nature, determining it was not a fixed lump sum contract, which allowed for additional claims for works that had been authorized.

Legal Issue

The primary issue before the Supreme Court was whether the CA correctly ordered the petitioner to pay the amounts of P40,880.00, P227,500.00 relating to substandard work, and P1,123,708.68 for the additional elevator enclosure.

Court’s Ruling

The Supreme Court upheld the CA's decision. It emphasized that a petition under Rule 45 is generally limited to questions of law and not fact, which respect the findings of lower courts unless very clear abuse or disregard of evidence is shown. The Court confirmed that the petitioner was bound by the Certificate of Completion and Acceptance, thus justifying the payment of P40,880.00 and P227,500.00. The intricate analysis of the contract terms led the Court to align with the CA’s finding that the contract's lump-sum nature permits for subsequently agreed additional works, thus enabling the recovery for the scenic elevator enclosure.

Contract Interpretation

Fixed lump sum contracts, regulated under Article 1724 of the Civil Code, dictate that contractors cannot demand payment increases unless changes are authorized in writing. The Court clarified that althou

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources.