Case Digest (G.R. No. 213229) Core Legal Reasoning Model
Facts:
The legal case involves Filinvest Alabang, Inc. as the petitioner and Century Iron Works, Inc. as the respondent. The events leading to the case occurred between 1997 and 1998 when Filinvest, the petitioner, awarded multiple contracts to Century Iron, including a substantial contract for the completion of metal works for the Filinvest Festival Supermall, valued at P29,000,000.00. This arrangement was formalized through an Agreement for Construction and went along with General Conditions of Contract that supplemented the agreement. After Century Iron completed the project, they sought payment for the total amount owed, which included withheld sums like a balance of a retention fee amounting to P40,880.00, a disputed deduction of P227,500.00 due to alleged substandard workmanship, and P1,123,708.68 for an additional scenic elevator enclosure, which Filinvest had not authorized upfront. In response to non-payment, Century Iron filed a case for money and damages against Filinvest,
...
Case Digest (G.R. No. 213229) Expanded Legal Reasoning Model
Facts:
- Contract Award and Subject Matter
- Sometime in 1997 and 1998, petitioner Filinvest Alabang, Inc. awarded various contracts to respondent Century Iron Works, Inc.
- One such contract was for the completion of the metal works requirement of Filinvest Festival Supermall, with a fixed lump sum contract price of P29,000,000.00.
- The contractual documents included an Agreement for Construction (the subject contract) and the General Conditions of Contract, which outlined procedures for variations and extra works.
- Dispute Over Payment and Withheld Amounts
- Upon project completion, respondent sought full settlement for its services.
- Petitioner allegedly withheld a total amount of P1,392,088.68, itemized as:
- A balance of the retention fee amounting to P40,880.00.
- An additional deduction of P227,500.00, purportedly due to respondent’s substandard workmanship.
- The cost for an additional scenic elevator enclosure amounting to P1,123,708.68.
- Respondent subsequently filed a case for sum of money with damages before the Regional Trial Court (RTC) in Civil Case No. 68850.
- Proceedings in the Regional Trial Court (RTC)
- In its Decision dated August 3, 2010, the RTC:
- Granted respondent’s claim for P227,500.00 plus legal interest.
- Denied respondent’s claim for the retention fee and the additional scenic elevator enclosure, holding that:
- Petitioner was estopped from claiming damages due to its earlier issuance of a Certificate of Completion and Acceptance, which signified acceptance of the work.
- The case was subsequently appealed by respondent to the Court of Appeals (CA).
- Proceedings in the Court of Appeals (CA)
- In its Decision dated December 27, 2013, the CA:
- Affirmed the RTC ruling regarding the deduction of P227,500.00 but with modifications.
- Ordered petitioner to also pay:
- The balance of the retention fee amounting to P40,880.00.
- Held that despite the subject contract being fixed lump sum in nature, the contract allowed for additional works when stipulated by written instructions.
- Petitioner later moved for reconsideration, which was denied by the CA in a Resolution dated June 25, 2014.
- Petitioner then elevated the matter to the Supreme Court through a petition for review on certiorari.
- Relevant Contract Provisions and Written Instructions
- Key provisions of the subject contract:
- ARTICLE I confirmed the scope, where respondent was to furnish all materials, labor, equipment, and other necessities for the project.
- ARTICLE II fixed the contract price at P29,000,000.00.
- The General Conditions included provisions for variation orders:
- Stipulated that extra work beyond the original scope required an official Site Instruction.
- Provided for the valuation of such variations using agreed-upon rates or schedules.
- In this case, petitioner issued two Site Instructions (dated August 1, 1997, and January 23, 1998) authorizing the construction of the additional scenic elevator enclosure.
- Supporting documents such as the Cost Breakdown for Claim of Change Orders and the Material Quantity Breakdown for Scenic Elevator Enclosure evidenced the extra work and its valuation.
Issues:
- Whether the Court of Appeals correctly ordered petitioner to pay respondent:
- The balance of the retention fee amounting to P40,880.00.
- An additional deduction of P227,500.00 due to respondent's purported substandard workmanship.
- The cost of an additional scenic elevator enclosure amounting to P1,123,708.68.
- Whether the subject contract’s nature as a fixed lump sum precluded additional liability for extra works beyond the lump sum price.
- Whether the issuance of a Certificate of Completion and Acceptance by petitioner estopped it from withholding payments on claims of defective workmanship.
Ruling:
- (Subscriber-Only)
Ratio:
- (Subscriber-Only)
Doctrine:
- (Subscriber-Only)