Title
Federal Builders, Inc. vs. Foundation Specialists, Inc.
Case
G.R. No. 194507
Decision Date
Sep 8, 2014
FBI and FSI disputed payment for construction work; SC ruled FBI liable for P1,024,600, reduced interest to 6%, and denied FBI's counterclaim due to lack of evidence.

Case Summary (G.R. No. 194507)

Petitioners and Respondents

• Petitioner in G.R. No. 194507: Federal Builders, Inc.
• Respondent in G.R. No. 194507: Foundation Specialists, Inc.
• Petitioner in G.R. No. 194621: Foundation Specialists, Inc. (petition later dismissed for lateness)
• Respondent in G.R. No. 194621: Federal Builders, Inc.

Key Dates

• August 20, 1990: Execution of sub-contract for P7,400,000.00.
• January 9, 1992: FSI files complaint for unpaid Billings No. 3 and 4 (P1,635,278.91).
• May 3, 2001: RTC decision awarding FSI P1,504,231.50 (inclusive of various items).
• July 15, 2010 & November 23, 2010: CA Decision and Resolution affirming with modifications.
• September 8, 2014: Supreme Court decision.

Applicable Law

• 1987 Philippine Constitution (post-1990 decision)
• Civil Code Articles on obligations and damages (Arts. 1169, 2209)
• Eastern Shipping Lines v. CA (1994) – guidelines on interest
• Nacar v. Gallery Frames (2013) – updated interest rates

Antecedent Facts

• Under the sub-contract, FBI paid 20% downpayment; balance payable via progress billings every fifteen days.
• FSI completed approximately 97% of its scope but alleged FBI failed to deliver required cement, delaying capping beam work.
• FBI counterclaimed, asserting only 85% completion, defective works, and incurred remedial costs.

Issues

  1. Whether FBI remained liable to pay Billings 3 and 4 despite alleged defects.
  2. Proper interest rate on the overdue amount.
  3. Validity of FBI’s counterclaim for remedial costs.

Ruling on Factual Findings

• RTC and CA found FSI substantially performed its obligations; non-completions and defects were attributable to FBI’s failure to deliver cement and other interferences.
• Federal Builders’ payments of approximately P6 million without objections demonstrated acceptance of FSI’s accomplished works.
• Counterclaim for P8,582,756.29 was dismissed for lack of proof linking remedial costs to FSI’s negligence.
• Supreme Court upheld these factual conclusions, noting no exceptional grounds to overturn them under settled jurisprudence.

Ruling on Interest Rate

• Courts below imposed 12% per annum legal interest from August 30, 1991 (date of extrajudicial demand).
• Supreme Court applied Eastern Shipping Lines and Nacar guidelines: construction contract breach does not

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.