Title
Federal Builders, Inc. vs. Foundation Specialists, Inc.
Case
G.R. No. 194507
Decision Date
Sep 8, 2014
FBI and FSI disputed payment for construction work; SC ruled FBI liable for P1,024,600, reduced interest to 6%, and denied FBI's counterclaim due to lack of evidence.

Case Digest (G.R. No. 194507)
Expanded Legal Reasoning Model

Facts:

  • Contractual Agreement and Scope of Work
    • On August 20, 1990, Federal Builders, Inc. (FBI) engaged Foundation Specialists, Inc. (FSI) as sub-contractor for the construction of the diaphragm walls, capping beam, and guide walls of Trafalgar Plaza in Makati City, at a total contract price of ₱7,400,000.00; FBI was to pay 20% downpayment and the balance via progress billings every 15 days, payable one week after presentation.
    • FSI completed approximately 97% of the work by March 8, 1991, but encountered delays in the capping beam and steel props installation due to FBI’s alleged failure to deliver the agreed cement; minor misalignments and rebar dowel placement issues were anticipated in the contract with alternative remedy plans.
  • Trial Proceedings
    • On January 9, 1992, FSI filed a complaint before the Makati RTC seeking ₱1,635,278.91 for unpaid Billings 3 and 4, plus interest from August 1, 1991, moral and exemplary damages, and attorney’s fees, alleging FBI’s refusal to pay despite demand.
    • FBI counterclaimed, asserting FSI completed only 85% of the work, delivered defective and non-specification works, abandoned the jobsite, and sought reimbursement of approximately ₱8,582,756.29 for remedial works.
  • Decisions of the Lower Courts
    • On May 3, 2001, the RTC ruled in favor of FSI, ordering FBI to pay:
(a) ₱1,024,600.00 representing Billings 3 and 4 less ₱33,354.40, plus 12% legal interest from August 30, 1991; (b) ₱279,585.00 for undelivered cement; (c) ₱200,000.00 as attorney’s fees; and costs of suit; counterclaim denied.
  • On July 15, 2010, the Court of Appeals (CA) affirmed with modification: deleted the ₱279,585.00 cement cost and reduced attorney’s fees to ₱50,000.00; upheld the 12% interest; both parties’ motions for reconsideration were denied.
  • Supreme Court Petitions
    • FSI’s petition (G.R. No. 194621) was dismissed as filed late.
    • FBI’s petition (G.R. No. 194507) challenged:
(a) Liability despite alleged defective work and FBI’s own re-work expenses; (b) Imposition of 12% interest absent a loan or forbearance stipulation; (c) Denial of FBI’s counterclaim for actual damages.

Issues:

  • Did the CA err in affirming FBI’s liability to pay Billings 3 and 4 despite alleged defects and FBI’s re-work expenses?
  • Did the CA err in imposing 12% legal interest on the award absent a stipulation of loan or forbearance?
  • Did the CA err in dismissing FBI’s counterclaim for remedial costs amounting to ₱8,582,756.29?

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.