Title
Federal Builders, Inc. vs. Daiichi Properties and Development, Inc.
Case
G.R. No. 142525
Decision Date
Feb 13, 2009
Dispute over deductive costs in construction contract; Arbitral Tribunal denied independent surveyor, deemed grave abuse of discretion; Court of Appeals reversed, affirmed by Supreme Court.

Case Summary (G.R. No. 142525)

Factual Background: The Construction Agreement and the Deductive-Cost Dispute

Under the Construction Agreement, Daiichi possessed the right to revise construction plans. During construction, Daiichi reduced the concrete strength from 8,000 to 6,000 pounds per square inch. The reduction decreased the required quantities of cement, steel bars, other materials, and also diminished labor costs. Daiichi then issued revised construction plans.

Daiichi and Federal agreed to reduce the contract price and to submit a separate evaluation of the deductive costs arising from the plan revisions. They diverged, however, on the proper method for computing deductive cost. Daiichi proposed a formula based on the difference between the quantities (and peso value) of steel bars, cement, labor, and materials required under the original plan and those required under the revised plan. Using that approach, Daiichi computed deductive cost at P64,602,110.59.

Federal insisted on a different formula: it compared the quantities (and peso value) required under the construction agreement (specifically the guaranteed maximum or fixed quantity) with the quantities required under the revised plan. Applying this approach, Federal computed deductive cost at P31,326,810.15.

Because of these competing computations, Daiichi engaged an independent quantity surveyor, Davis Langdo and Seah Philippines, Inc. (DLS), to survey the deductive costs. DLS produced an estimate of P68,441,415.58, which was closer to Daiichi’s method. Daiichi also made deductions from the amounts it paid Federal, using Daiichi’s former computation. Federal, feeling aggrieved, initiated arbitration.

CIAC Arbitration Petition and the Central Issue Submitted to the Arbitral Tribunal

Federal filed a petition for arbitration with CIAC on 9 November 1998. The parties agreed that the dispute would be resolved by the Arbitral Tribunal. The record reflected that the basic issue submitted revolved around determining the correct approach for computing the deductive costs caused by the revisions in the construction project.

At the hearing stage, Daiichi filed a Motion to Commission an Independent Quantity Surveyor on 2 June 1999, intending to determine the actual quantities of materials needed to complete the project under both the original (old) plan and the revised plan. Daiichi took the position that the deductive costs could only be properly ascertained by comparing materials requirements under the old and new plans.

Federal opposed the motion. Federal argued that Daiichi already submitted estimates from DLS and that there was no need to commission an estimate of the old plans because the original plans were never implemented. Federal further insisted that the quantity of materials required for the project was reflected in the construction agreement.

Arbitral Tribunal’s Orders Denying the Motion

On 29 June 1999, the Arbitral Tribunal denied Daiichi’s motion. It reasoned that commissioning an independent surveyor was not absolutely necessary and that such engagement would only be useful if both parties agreed.

Daiichi moved for reconsideration. The Arbitral Tribunal denied the motion in an order dated 13 July 1999.

Court of Appeals Proceedings and Ruling Under Rule 65

Dissatisfied, Daiichi challenged the Arbitral Tribunal’s orders before the Court of Appeals. In a Decision dated 9 November 1999, the Court of Appeals set aside the Arbitral Tribunal’s orders and ordered the tribunal to commission an independent quantity surveyor, subject to the relevant time prescription under Section 5, Chapter XV of the Rules of Procedure Governing Construction Arbitration. The Court of Appeals directed the independent surveyor to determine the actual quantities of materials required to complete the “Orient Plaza” project under the original/bid plan and the revised plans.

Federal filed a motion for reconsideration, which the Court of Appeals denied in a Resolution dated 23 February 2000. Federal then filed the present petition to assail the Court of Appeals ruling.

Parties’ Contentions Before the Supreme Court

Federal argued that the petition before the Court of Appeals should have been dismissed outright because Federal believed Daiichi resorted to the wrong remedy: Federal maintained that Daiichi should have filed a Rule 45 petition for review instead of a Rule 65 certiorari petition. Federal emphasized that a special civil action under Rule 65 cannot replace an ordinary appeal.

Federal also contended that, even if procedural defects were ignored, the petition should still be dismissed because the Court of Appeals allegedly committed no grave abuse of discretion amounting to want or excess of jurisdiction. Federal further relied on the limited inquiry in certiorari under Rule 65: whether the tribunal acted without or in excess of jurisdiction, or with grave abuse of discretion.

The Court treated these issues in light of the Court of Appeals’ ground for reversal, namely, that the Arbitral Tribunal’s refusal to commission an independent quantity surveyor disregarded the arbitral rules’ mandate to ascertain facts speedily and objectively and to employ reasonable means to resolve technical disputes.

Legal Basis and Reasoning: Rule 65 Review and the Grave Abuse Finding

The Supreme Court addressed the nature of certiorari under Rule 65 by recalling doctrinal distinctions. A tribunal acts without jurisdiction when it lacks legal power to determine the case. Excess of jurisdiction exists when, although clothed with power, it oversteps its authority as determined by law. Grave abuse of discretion exists when action is capricious, whimsical, arbitrary, or despotic, amounting to lack of jurisdiction.

Applying these standards, the Court held that the Court of Appeals was not far from correctness in finding grave abuse. The Supreme Court agreed with the Court of Appeals that the Arbitral Tribunal’s refusal to allow the independent survey effectively prevented Daiichi from presenting what the Arbitral Tribunal deemed necessary but which the appellate court considered “vital” information for the judicious resolution of the dispute.

The Court explained that the central controversy concerned the computation formula for deductive cost. Daiichi maintained that deductive cost required comparing materials requirements under the original plan and the revised plan, which in turn required determining “old quantity” and “new quantity” through a quantitative survey. Without such survey, Daiichi argued, deductive cost could not be accurately determined. Federal’s approach allegedly relied on the guaranteed maximum quantities under the agreement and the revised plan, but the unresolved components remained the quantities related to the revised and old plan items, which Daiichi sought to establish through expert technical investigation.

The Supreme Court also emphasized that the case involved highly technical matters within the construction industry. Fair-minded and specialized persons were described as valuable sources of needed information for resolving confusing and contradicting claims.

In approving the Court of Appeals reasoning, the Supreme Court pointed out that Article 1, Section 3 of the Rules of Procedure Governing Construction Arbitration exhorts arbitrators to use every and all reasonable means to ascertain facts speedily and objectively, without regard to technicalities of law or procedure. The Court of Appeals concluded that refusal to consider the independent survey deprived the tribunal of a “vital and unimpeachable” piece of information and amounted to disregard of the spirit, if not the letter, of the arbitral rules. The Supreme Court viewed the tribunal’s approach as falling into speculation, conjecture, and guesswork if it relied on the parties’ conflicting submissions without commissioning an independent survey to determine the factual quantities relevant to the competing formulas.

The Supreme Court further addressed the Arbitral Tribunal’s stated justification that an independent survey would only be useful if both parties agreed. The Court of Appeals rejected this rationale as specious because Section 5, Chapter XV of the Rules of Procedure Governing Construction Arbitration permitted the use of technical or legal experts if requested by one of the parties. Thus, refusal to grant Daiichi’s motion conflicted with the rules’ express permission for one-party request of expert assistance.

The Supreme Court likewise found Federal’s argument—that there was no need for a survey because Daiichi already submitted DLS estimates—insufficient. It held that the survey initiated by Daiichi could not be equated with an independent survey sanctioned by the Arbitral Tribunal, which, according to the Court of Appeals and affirmed by the Supreme Court, was suitable for resolving technical disputes by providing the tribunal with objective detailed information.

On the Alleged Encroachment by the Court of Appeals

Federal also contended that the Court of Appeals encroached on CIAC’s jurisdiction by finding Daiichi’s formula more acceptable and thus pre-empting the tribunal’s decision on the merits. The Supreme Court rejected this claim. It held that the Court of Appeals resolved primarily the pro

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.