Title
Datem, Inc. vs. Alphaland Makati Place, Inc.
Case
G.R. No. 242904-05
Decision Date
Feb 10, 2021
Construction dispute over unpaid claims and retention money; CIAC's jurisdiction upheld despite non-compliance with amicable settlement precondition.

Case Summary (G.R. No. 242904-05)

Factual Background

In May 2014, Alphaland entered into a construction agreement with DATEM worth Php1.26 billion, for civil, structural, and architectural works on the condominium project. DATEM submitted progress billings which Alphaland partially paid, leaving an unpaid balance of Php34,076,747.09. The construction experienced delays not attributable to DATEM, prompting multiple claims for time extensions, some of which were granted. Alphaland accepted and certified the completion of Towers 1 and 2 but refused to pay for works related to Tower 3, deducting Php72,396,659.29 from DATEM’s contract. DATEM also claimed retention funds amounting to Php121,930,996.35 were withheld unjustly. Following Alphaland’s alleged delay and refusal to resolve issues, DATEM terminated the remaining works on Tower 3 and demanded payment, which Alphaland refused, leading to arbitration under the contract’s arbitration clause.

Applicable Law and Procedural History

The parties’ dispute was brought before the CIAC pursuant to the arbitration clause in their construction agreement, with DATEM filing a complaint for unpaid claims. Alphaland challenged the CIAC’s jurisdiction on grounds of non-compliance with a stipulated condition precedent requiring amicable settlement meetings before arbitration. The CIAC denied the motion to dismiss and proceeded with arbitration. Alphaland filed a petition for certiorari with the Court of Appeals (CA) to nullify the CIAC's jurisdiction, resulting in the CA annulling the CIAC’s Final Award dated April 5, 2018, for lack of jurisdiction based on the unmet precondition. DATEM subsequently filed a petition for review with the Supreme Court.

Issue Before the Court

The central issue is whether the CA erred in ruling that the CIAC lacked jurisdiction over the arbitration case due to the non-fulfillment of the amicable settlement meeting precondition embedded in the arbitration clause.

Jurisdiction of the CIAC Under EO 1008

The Supreme Court affirmed that under Section 4 of Executive Order (EO) No. 1008, the CIAC has original and exclusive jurisdiction over construction contract disputes when the parties have agreed to submit their controversies to arbitration. This jurisdiction is vested automatically by law upon the presence of an arbitration clause in the contract, irrespective of compliance with any procedural conditions stipulated within that clause. The Court emphasized that jurisdiction conferred by law cannot be waived, diminished, or conditioned upon by the parties’ stipulations, acts, or omissions. The existence of an arbitration clause alone is sufficient to establish CIAC's jurisdiction.

Arbitration Clause Analysis

The contract’s Article 13 on Dispute Settlement specifies that parties should attempt amicable resolution within specified timeframes before submitting disputes to arbitration. However, the Court interpreted these provisions as procedural guidelines rather than jurisdictional conditions precedent. The CA’s reliance on the failure to meet the amicable settlement meeting requirement as a ground to deny jurisdiction was held to be erroneous.

Treatment of Non-Compliance with Preconditions

The CIAC Revised Rules of Procedure provide that while claimants must show compliance with preconditions, non-compliance does not divest CIAC of jurisdiction. Instead, the CIAC may suspend proceedings temporarily to allow compliance within a reasonable period. The records show that the CIAC granted several extensions to allow amicable negotiations, but Alphaland eventually insisted on dismissal instead of continuing participation, which was within the CIAC’s authority to reject.

Substantial Compliance with Verification Requirements

The Court addressed Alphaland’s contention regarding defective verification of the petition, ruling that the discrepancy in dates did not render the petition fatally defective. Verification is a formal requirement to assure good faith; substantial compliance is sufficient when the verifying party has actual knowledge of the facts. Here, DATEM substantially complied with the requirement.

Policy Considerations and Legislative Intent

The Court highlighted the


...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.