Case Summary (G.R. No. 188794)
Factual Background
The dispute arose from a construction agreement by which DATEM Incorporated undertook civil, structural, and architectural works for three towers constructed atop a podium at the Alphaland Makati Place condominium project. The total contract price was PHP 1,260,000,000.00. During performance, DATEM submitted progress billings for Main Works and Change Orders, of which Alphaland approved and paid substantial sums but left an unpaid balance of PHP 34,076,747.09. Work completion experienced delays attributed by DATEM to causes beyond its control, leading DATEM to seek nine claims for time extensions, six of which were granted by Alphaland’s construction manager until 30 September 2015. Towers 1 and 2 were completed and accepted on 06 September 2015, but unresolved design issues affected Tower 3 and Alphaland deducted from DATEM’s contract the balance of Tower 3 works in the amount of PHP 72,396,659.29.
Claims and Alleged Damages
DATEM asserted that upon completion it remained entitled to release of retention money totaling PHP 121,930,996.35 and payment of unpaid billings and claims including extended preliminaries in the aggregate amounts it itemized. After Alphaland allegedly refused to settle these demands, DATEM invoked the arbitration clause in the construction agreement and filed a complaint with the Construction Industry Arbitration Commission (CIAC).
Arbitration Clause and Preconditions
The parties’ construction agreement contained Article 13 providing for dispute settlement by amicable meetings within prescribed timeframes and, failing settlement within thirty calendar days, submission to arbitration in accordance with the arbitration rules of the Construction Industry Authority of the Philippines. The clause further provided that unresolved issues submitted for arbitration would not, save limited exceptions, justify suspension of work or extension of time except as authorized in writing by the owner.
Proceedings Before the CIAC
Alphaland moved to dismiss before the CIAC, contending that the parties had not complied with the arbitration clause’s precondition of meeting to attempt amicable settlement. The CIAC denied the motion in an Omnibus Order dated 25 August 2017 and denied reconsideration. During CIAC proceedings, the tribunal followed the CIAC Rules by giving the parties reasonable periods to negotiate and to file their answers, and counsel for Alphaland acknowledged on record that negotiations were ongoing and requested additional time to pursue settlement.
Arbitral Final Award
Pending resolution of a certiorari petition filed by Alphaland, the CIAC arbitral tribunal rendered a Final Award dated 05 April 2018 in favor of DATEM Incorporated, awarding a total of PHP 235,901,940.49 composed of awards for release of retention, progress billings, return of unjustified deductions, an award on extended preliminaries and related items, partial interest, attorney’s fees, and costs, with additional interest at 6% per annum upon finality.
Proceedings Before the Court of Appeals
Alphaland filed a petition for certiorari with the Court of Appeals in CA-G.R. SP No. 152827 challenging the CIAC’s jurisdiction on the ground that DATEM failed to satisfy the arbitration clause’s precondition requiring meetings for amicable settlement. The CA consolidated that petition with a subsequent petition attacking the Final Award and, on 25 October 2018, annulled the CIAC Omnibus Order and set aside the Final Award for lack of jurisdiction, ordering dismissal of CIAC Case No. 21-2017.
Issue on Review
The central issue before the Supreme Court was whether the Court of Appeals erred in finding that the CIAC lacked jurisdiction over the dispute because the parties allegedly failed to comply with a contractual precondition to arbitration.
Petitioner's Contentions
DATEM Incorporated argued that jurisdiction of the CIAC is conferred by law under Executive Order No. 1008 and vests automatically when a construction contract contains an arbitration clause; therefore, non-compliance with any stipulated precondition cannot oust or diminish CIAC jurisdiction.
Respondents' Contentions
Alphaland maintained that the arbitration clause imposed a condition precedent—mandatory meetings to attempt amicable settlement—which DATEM did not fulfill before initiating arbitration; on that basis, Alphaland contended the CIAC lacked jurisdiction and the arbitral proceedings should have been dismissed.
The Court’s Analysis on Verification and Procedural Formalities
The Court first addressed Alphaland’s contention that DATEM’s petition to the Supreme Court was fatally defective because the verification bore a date earlier than the petition’s filing date. The Court held that verification is a formal and not jurisdictional requirement, and that noncompliance or a variance in dates does not necessarily render a pleading fatally defective. The Court applied established guidelines that allow correction or acceptance of a defective verification where the petitioner has substantial compliance and the circumstances justify dispensing with strict formality. DATEM satisfactorily explained the variance and substantially complied with the purpose of the verification rule.
The Court’s Analysis on CIAC Jurisdiction
The Court reaffirmed that under Section 4 of Executive Order No. 1008, the CIAC has original and exclusive jurisdiction over disputes arising from or connected with construction contracts and that the Board acquires jurisdiction when the parties agree to submit the dispute to voluntary arbitration. The Court emphasized that the mere existence of an arbitration clause in a construction contract is sufficient, by law, to vest the CIAC with jurisdiction and that such jurisdiction is conferred by statute and cannot be subjected to conditions, waived, or diminished by stipulation, act, or omission of the parties.
CIAC Rules on Contractual Preconditions
The Court noted that the CIAC Revised Rules of Procedure expressly contemplate situations of non-compliance with contractual preconditions. Those Rules require a claimant in private construction contracts to show good faith compliance with preconditions or exemptions and direct that, in case of non-compliance without justifiable reasons, the tribunal shall suspend proceedings pending compliance within a reasonable period. The Court found that the CIAC applied these procedures by allowing reasonable time for negotiation and settlement and by repeatedly granting extensions to the parties.
The Court’s Conclusion on the CA’s Error
The Court concluded that the Court of Appeals erred in declaring that the CIAC lacked jurisdiction due to alleged noncompliance with the arbitration clause’s precondition. The CA’s invocation of a condit
...continue reading
Case Syllabus (G.R. No. 188794)
Parties and Posture
- DATEM Incorporated was the petitioner below and sought review on certiorari of the Court of Appeals' decision annulling an arbitral award.
- Alphaland Makati Place, Inc. and Alphaland Southgate Tower, Inc. were the respondents below and the adverse parties in the CIAC arbitration.
- The petition assailed the Court of Appeals Decision dated 25 October 2018 in CA-G.R. SP. Nos. 152827 and 155448 which set aside the Final Award of the Construction Industry Arbitration Commission.
- The arbitral tribunal of the CIAC that rendered the Final Award was composed of Engr. Rodolfo R. Penalosa, Atty.-Engr. Jesusito G. Morallos, and Atty. Teodoro C. Baroque, Jr.
Key Facts
- The dispute arose from a construction agreement for Towers one, two, and three of Alphaland Makati Place, a mixed residential and commercial project built over a six-level podium with a five-level basement and three tower buildings.
- The total contract price for the works delegated to DATEM was PHP 1,260,000,000.00.
- DATEM submitted separate progress billings for Main Contract Works and Change Orders, of which Alphaland approved payments totaling Php1,167,442,794.02 for Main Works and Php230,201,525.49 for Change Orders.
- Unpaid billings asserted by DATEM amounted to Php34,076,747.09 and included specific progress billings, change orders, and labor escalation claims.
- DATEM claimed withheld retention money totaling Php121,930,996.35 and additional claims for extended preliminaries totaling Php153,109,616.92.
- Completion of Towers one and two occurred on 06 September 2015 and were accepted by Alphaland, while design issues delayed Tower three and Alphaland deducted Php72,396,659.29 for the balance of Tower three works.
- DATEM terminated the remaining works on Tower three by letter dated 27 January 2017 and thereafter filed a complaint before the CIAC invoking an arbitration clause in the construction agreement.
Procedural History
- Alphaland filed a motion to dismiss before the CIAC challenging jurisdiction on the ground of non-compliance with a contractual precondition to arbitration.
- The CIAC denied the motion to dismiss in an Omnibus Order dated 25 August 2017 and denied Alphaland's motion for reconsideration.
- Alphaland filed a petition for certiorari before the Court of Appeals docketed as CA-G.R. SP No. 152827 while CIAC proceedings were pending.
- While the CA petition was pending, the CIAC rendered a Final Award dated 05 April 2018 in favor of DATEM, and Alphaland promptly filed a second petition before the CA docketed as CA-G.R. SP No. 155448 which were subsequently consolidated.
- The Court of Appeals rendered the decision dated 25 October 2018 annulling the CIAC Final Award for lack of jurisdiction and dismissing CIAC Case No. 21-2017.
- DATEM filed the instant petition for review on certiorari in the Supreme Court to challenge the CA ruling.
Arbitral Award
- The CIAC Final Award dated 05 April 2018 adjudged in favor of DATEM and granted a net award totaling Php235,901,940.49.
- The Award included the release of retention money in the amount of Php121,930,996.35 and recovery for progress billings, return of unjustified deductions, and partial recovery for extended preliminaries.
- The Award adjusted claimed amounts by accounting for undesignated payments and apportioned interest and fees as reflected in the dispositive portion.
- The Final Award provided that upon its finality interest at six percent per annum shall accrue on the outstanding amount until full payment.