Title
MIAA vs. Powergen, Inc.
Case
G.R. No. 164299
Decision Date
Feb 12, 2008
MIAA contracted Powergen for a power plant under a BOO scheme. Dispute arose over energy rates; Powergen sought injunction for minimum consumption payments. SC ruled injunction improper, preserving status quo pending trial.

Case Digest (G.R. No. 223366)

Facts:

  • Background and Context
    • In the early 1990s, Metro Manila—including the airport area—experienced frequent power outages, voltage fluctuations, and power surges that disrupted the operations of airport facilities and essential public services.
    • The Manila International Airport Authority (MIAA), then entirely dependent on MERALCO for its power needs, resolved to construct its own baseload power plant to ensure continuous and adequate power supply.
  • Project Initiation and Procurement Process
    • Due to its lack of technical expertise and capability, MIAA solicited contractors on a Build-Operate-Own scheme.
    • MIAA prepared the terms of reference and conducted a public bidding process for constructing the power plant.
    • Respondent Powergen, Inc. submitted a bid and was awarded the contract on April 4, 1994, when MIAA issued a notice of award.
  • Formation and Terms of the Power Generation Agreement (PGA)
    • MIAA and Powergen, Inc. entered into a Power Generation Agreement which included key provisions:
      • Article 7.3 designated MIAA’s obligation to purchase and pay for a minimum guaranteed energy of 4,000,000 KWH per month at a privilege discount rate, in addition to energy consumed above that minimum.
      • The Sixth Schedule of the contract provided that energy fees would be calculated based on the MERALCO Billing System with a 40% discount, ensuring the discounted rate payment for all energy supplied.
    • The PGA stipulated that MIAA must answer for any additional charges if MERALCO’s standby power supply was used.
  • Notice to Proceed and Subsequent Contractual Developments
    • On December 18, 1995, MIAA issued a notice to proceed to Powergen, Inc., which reiterated the project's parameters but introduced a significant modification:
      • The initial 7.250 MW power station was to be constructed as part of the original bid proposal.
      • The guaranteed minimum energy consumption clause (4,000,000 KWH per month) was to be ignored temporarily, making the energy fee computation based solely on actual consumption until full capacity was reached.
    • Powergen, Inc. acknowledged receipt and acceptance of this notice through a certified acknowledgment signed by its president, Luisito C. Magpayo.
  • Operational Phase and Emergence of the Dispute
    • The power station was subsequently constructed and became operational. MIAA made payments in accordance with the billings provided by Powergen, Inc.
    • In June 2000, MIAA discovered that MERALCO was charging a lower rate (P2.03 per KWH) than the rate collected by Powergen, Inc. (P2.22 per KWH).
    • As a result, MIAA adjusted its payments to reflect the lower MERALCO rate, leading Powergen, Inc. to claim non-compliance with the contractual obligation under Article 7.3.
  • Litigation History
    • On January 4, 2001, Powergen, Inc. filed a complaint for the reformation of the contract in the Regional Trial Court of Pasig City, Branch 168, seeking:
      • Determination of the proper rate for energy fees.
      • Enforcement of MIAA’s obligation to purchase the guaranteed minimum energy consumption as per Article 7.3 of the PGA.
    • On July 24, 2001, Powergen, Inc. amended its complaint to include a request for a temporary restraining order or preliminary injunction to prevent MIAA from deducting alleged overpayments from future billings.
    • On November 12, 2002, an urgent motion for a preliminary injunction was filed, resulting in:
      • A January 21, 2003, trial court order granting a preliminary injunction.
      • A January 23, 2003, issuance of a writ of preliminary mandatory injunction.
      • A subsequent March 24, 2003, order denying a motion for reconsideration.
    • MIAA sought reconsideration and appealed the trial court’s decision, with the Court of Appeals upholding the trial court’s ruling. Ultimately, MIAA filed a petition for review on certiorari challenging these decisions.
  • Central Dispute and Controversial Issues
    • The core issue revolves around whether Powergen, Inc. is entitled to a preliminary mandatory injunction that compels MIAA to adhere to the guaranteed minimum energy consumption provision of the PGA.
    • MIAA contends that:
      • There is no irreparable injury justifying such an injunction.
      • The notice to proceed effectively altered the PGA, thereby negating the obligation to purchase the guaranteed minimum energy.
    • Powergen, Inc. argues that:
      • The notice to proceed did not amend the PGA.
      • The extreme urgency and potential financial ruin it faces (especially in light of possible operational changes at Terminal 3) justify the issuance of the injunctive writ.

Issues:

  • Whether the preliminary mandatory injunction granted by the trial court was proper.
    • Does the situation warrant the immediate issuance of an injunction given the disputed contractual obligations?
  • Whether the notice to proceed issued by MIAA constituted a valid amendment to the PGA.
    • To what extent did the notice to proceed modify the contractual requirement for MIAA to purchase the guaranteed minimum energy consumption?
  • Whether the trial court acted with grave abuse of discretion by issuing a mandatory injunction that effectively disposes of most of the issues reserved for trial.
    • Has the trial court’s decision preempted the necessity of a full trial to determine the merits of the contractual dispute?
  • Whether the alleged extreme urgency and irreparable injury claimed by Powergen, Inc. are sufficiently proven to justify the preliminary injunction.
    • Does the mere assertion of potential financial ruin and loss of viability meet the threshold for issuing a mandatory injunction without a full trial?

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.