Title
DPWH Policy on Excavation Permits for National Roads
Law
Dpwh Department Order No. 26, S. 2011
Decision Date
May 3, 2011
DPWH Department Order No. 26 mandates strict guidelines for excavation and restoration works by utility agencies on national roads, ensuring proper planning, timely execution, and compliance to minimize public inconvenience and maintain road safety.

Law Summary

Application and Required Documents

  • Excavation Permit applications must be accompanied by:
    • Sketch plan/map showing exact project location, road section, facility type, and related appurtenances.
    • Programs of Work (POWs) with detailed cost estimates for excavation and restoration.
    • Timetable in Bar/Gantt or PERT-CPM chart outlining work duration.
    • Typical section and specifications including pavement type, total area to be excavated, nature and extent of work, and contractor details.
    • Signed terms and conditions by authorized applicant representative.
    • Performance Bond surety callable on demand, covering 100% of restoration costs.
    • Non-refundable Supervision Fee based on restoration cost:
      • Below P50,000: 3% of restoration cost.
      • P50,000 and above: 1.5% of restoration cost.

Processing and Inspection

  • Complete applications lead to scheduling of a joint field inspection with DPWH representatives and contractor.
  • Inspection verifies the extent and precise location of excavation work.

Restoration Requirements

  • Temporary paving with bituminous concrete is required immediately after excavation.
  • Final restoration begins only after utility is operational and passes necessary tests (e.g., hydro testing for pipes).
  • Restoration work is supervised by DPWH representatives.

Coordination with Tree Planting Guidelines

  • Excavations must avoid conflicts with tree planting initiatives along national roads.

Road Improvements Affecting Utilities

  • Utilities affected by road expansion must be relocated or removed at the utility agency's expense.
  • DPWH waives fees related to relocation/removal.

Authority and Monitoring

  • Excavation permit requests handled by District Engineering Office and recommended to Regional Director for approval.
  • Restoration works monitored during a one-year warranty period.
  • Warranty bond of 10% of actual restoration cost held for one year after completion certificate issuance.

Work Schedule and Conditions

  • Excavations and restoration in highly urbanized or traffic congested areas should be conducted in two shifts (day and night) if practicable.

Compliance with DPWH Typical Roadway Sections

  • Excavations allowed only in locations specified by DPWH Typical Roadway Sections corresponding to various road right-of-way widths.
  • Deviations require detailed plans and approval from the Regional Director.

Enforcement and Penalties

  • DPWH notifies applicants of any permit violations.
  • Reasonable time is given to rectify violations.
  • Failure to comply may result in permit revocation or cancellation.

Transitional and Final Provisions

  • This order supersedes all previous guidelines on digging/excavations.
  • Immediate effect and will remain enforced until amended or revoked by future issuances.

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.