Law Summary
Background and Context
- Legal Basis: This memorandum is issued in accordance with Executive Order No. 429, series of 1990, which reorganized administrative regions in Mindanao.
- Purpose: To direct a moratorium on the transfer of regional offices from Zamboanga City to Pagadian City.
- Preceding Actions: Memorandum Circular No. 75, series of 2004, mandated the transfer of regional offices, with exceptions for certain departments.
Moratorium on Office Transfers
- Provision: All departments, bureaus, and government agencies are ordered to suspend transfers of their offices from Zamboanga City to Pagadian City.
- Key Definitions:
- Zamboanga City: Designated as the commercial and industrial center.
- Pagadian City: Designated as the regional center.
- Key Definitions:
- Current Situation:
- Of 121 regional offices, only 32 have fully transferred, 12 have partially transferred, and 6 have established satellite offices.
- Employees face economic and social challenges due to dual residences.
Study and Consultation Requirement
- Procedure: A study and consultations will be conducted by the following agencies:
- Presidential Management Staff (PMS)
- Department of the Interior and Local Government (DILG)
- Civil Service Commission (CSC)
- National Economic Development Authority (NEDA)
- Department of Budget and Management (DBM)
- Deadline: A comprehensive report with findings and recommendations must be submitted to the President within 30 working days of this memorandum's issuance.
Continuation of Operations
- Operating Protocol: Regional offices that have already moved to Pagadian City will continue their operations in that location.
Effective Date
- Implementation: This memorandum circular is effective immediately upon issuance.
Key Takeaways
- A moratorium has been established on the transfer of regional offices from Zamboanga City to Pagadian City pending further study and stakeholder consultation.
- A report is required from designated agencies within 30 working days.
- Existing regional offices in Pagadian City will continue their operations without interruption.
This memorandum aims to address the concerns of affected employees and ensure a thorough evaluation of the transfer process before any further actions are taken.