Title
PH Construction Arbitration Law
Law
Executive Order No. 1008
Decision Date
Feb 4, 1985
The Construction Industry Arbitration Law in the Philippines establishes the Construction Industry Arbitration Commission (CIAC) to resolve disputes arising from construction contracts, providing a streamlined and efficient process for both government and private contracts.

Policy and declared intent

  • Section 2 declares the policy of the State to encourage the early and expeditious settlement of disputes in the Philippine construction industry.
  • The Executive Order directs the creation of an arbitration machinery to support this policy (Sections 3 and 4).

Creation and supervisory structure

  • Section 3 establishes in the Construction Industry Authority of the Philippines (CIAP) a body known as the Construction Industry Arbitration Commission (CIAC).
  • Section 3 provides that the CIAC is under the administrative supervision of the Philippine Domestic Construction Board (PDCB).
  • Section 6 assigns to the CIAC the formulation and supervision of the arbitration program and related authority.

Scope, jurisdiction, and exclusions

  • Section 4 grants the CIAC original and exclusive jurisdiction over disputes arising from, or connected with, construction contracts entered into by parties involved in construction in the Philippines.
  • Section 4 covers disputes arising before or after the abandonment or breach of the contract.
  • Section 4 covers disputes involving government or private contracts.
  • Section 4 requires a jurisdictional agreement: for the Board to acquire jurisdiction, the parties must agree to submit the dispute to voluntary arbitration.
  • Section 4 provides that CIAC jurisdiction includes, among others:
    • violation of specifications for materials and workmanship;
    • violation of the terms agreement;
    • interpretation and/or application of contractual provisions;
    • amount of damages and penalties;
    • commencement time and delays;
    • maintenance and defects;
    • payment default of employer or contractor; and
    • changes in contract cost.
  • Section 4 excludes disputes arising from employer-employee relationship, which remain governed by the Labor Code of the Philippines.

Composition, term, and governance

  • Section 5 provides that the CIAC consists of a Chairman and two (2) members.
  • Section 5 states that all members are appointed by the CIAP Board upon recommendation by the members of the PDCB.
  • Section 8 sets the term of office at six (6) years for the members, with staggered terms as follows:
    • one member for six (6) years;
    • another member for four (4) years; and
    • the third member for two (2) years.
  • Section 8 provides that an appointment to fill a vacancy is only for the unexpired portion of the predecessor’s term.
  • Section 9 provides that a majority of the members constitutes quorum.
  • Section 10 provides that the CIAC’s decisions are reached by majority vote.

CIAC functions and personnel

  • Section 6 directs the CIAC to formulate and adopt an arbitration program for the construction industry.
  • Section 6 directs the CIAC to enunciate policies and prescribe rules and procedures for construction arbitration.
  • Section 6 authorizes the CIAC to supervise the arbitration program and exercise authority on the appointment, replacement, or challenging of arbitrators.
  • Section 6 requires the CIAC to direct its officers and employees to perform functions assigned from time to time.
  • Section 12 authorizes the CIAC to appoint the Executive Director, consultants, arbitrators, and other personnel and staff.

Secretariat and its responsibilities

  • Section 11 requires the CIAC to have a Secretariat headed by an Executive Director.
  • Section 11 makes the Executive Director responsible for:
    • receiving requests for arbitration and other pleadings;
    • notifying the parties; and
    • fixing and receiving filing fees, deposits, costs of arbitration, administrative charges, and fees.
  • Section 11 requires the Executive Director to notify the parties of the decisions/awards made by the arbitrators.
  • Section 11 provides that the Secretariat includes a Publication and Training Division.

Fees, deposits, and financial authority

  • Section 7 provides that CIAC members receive per diems and allowances fixed by the CIAP from time to time.
  • Section 13 empowers the CIAC to determine and collect fees, deposits, cost of arbitration, and administrative and other charges needed for its functions.
  • Section 13 authorizes the CIAC to use its receipts and deposits to finance its operations, subject to approval by the President and without prejudice to any law to the contrary.
  • Section 16 provides that arbitration expenses include:
    • filing fee;
    • administrative charges;
    • arbitrator’s fees;
    • expert’s fees and expenses; and
    • other impositions that the CIAC imposes.
  • Section 16 provides that administrative charges and arbitrator’s fees are computed based on a percentage of the sum in dispute, to be fixed under the Table of Administrative Charges and Arbitrator’s Fees.

Arbitrators, tribunal composition, and experts

  • Section 14 allows settlement of a dispute by either a sole arbitrator or three arbitrators.
  • Section 14 allows, by party agreement, the nomination of a sole arbitrator from the CIAC’s list of accredited arbitrators for appointment and confirmation.
  • Section 14 grants the CIAC the option, considering the complexities and intricacies of the dispute, to appoint a single arbitrator if the parties fail to agree.
  • Section 14 provides that if the CIAC decides to form an Arbitral Tribunal, each party may nominate one (1) arbitrator from the accredited list for appointment and confirmation.
  • Section 14 requires the third arbitrator acceptable to both parties, confirmed in writing, to be appointed by the CIAC and to preside over the Tribunal.
  • Section 14 provides that arbitrators must be people in whom both the business sector and the government have confidence.
  • Section 14 provides that arbitrators are not permanently employed with the CIAC and render services only when called to arbitrate, and they receive fees for each dispute they settle.
  • Section 15 authorizes the use of technical or legal experts in dispute settlement if requested by a party or by the Arbitral Tribunal.
  • Section 15 requires that if a party requests an expert, the appointment is confirmed by the Arbitral Tribunal.
  • Section 15 allocates expert costs:
    • if both parties request an expert, they equally shoulder the expert’s fees and expenses; and half must be deposited with the Secretariat before the expert renders service;
    • if only one party requests an expert, that party deposits the whole amount required.

Arbitration deposits and dismissal consequences

  • Section 17 authorizes the CIAC to fix the required deposit amount equivalent to the expected arbitration expenses.
  • Section 17 requires the deposit to be paid to the Secretariat before arbitration proceedings commence.
  • Section 17 provides that the deposit is paid either equally by the parties or by any one of them.
  • Section 17 provides that if one party fails to contribute its share, the other party must pay in full.
  • Section 17 provides that if both parties fail to tender the required deposit, the case is considered dismissed.
  • Section 17 provides that even if the case is dismissed for failure to deposit, the parties remain liable to pay one half (1/2) of the agreed administrative charge.

Awards: finality, appeal, and execution

  • Section 19 states that the arbitral award is binding on the parties.
  • Section 19 provides that the award is final and inappealable, except on questions of law.
  • Section 19 provides that questions of law are appealable to the Supreme Court.
  • Section 20 provides that once a decision, order, or award becomes final and executory, the Arbitral Tribunal or the single arbitrator, with the concurrence of the CIAC, issues a writ of execution.
  • Section 20 authorizes the writ of execution to be issued motu proprio or on motion of any interested party.
  • Section 20 directs the writ to require a sheriff or other proper officer to execute the decision, order, or award.

Reports and rule-making

  • Section 18 requires the Commission to submit an annual report to the CIAP within three (3) months after the end of the fiscal year.
  • Section 18 requires the Commission to submit other periodic reports as required from time to time.
  • Section 21 requires the CIAC to formulate and adopt necessary rules and procedures for construction arbitration.

Separability, repeals, and effectivity

  • Section 22 provides a separability rule: if any provision is held invalid or unconstitutional, the validity of the remaining provisions remains in full force and effect.
  • Section 23 repeals or modifies, accordingly, all provisions of existing laws, proclamations, decrees, letters of instructions, and executive orders that are contrary to or inconsistent with this Executive Order.
  • Section 24 provides immediate effectivity of the Executive Order.

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.