Law Summary
Scope and Purpose of the Guidelines
- Applies to National Government Agencies (NGAs), GOCCs, GFIs, SUCs, and Local Government Units (LGUs).
- Separately governed guidelines exist for projects by the AFP Corps of Engineers.
- Establishes procedural standards for negotiatied procurement under Section 54.2(d) of IRR-A and administration of infrastructure projects.
Definitions of Key Terms
- By Administration: Implementation done directly by agency personnel under agency supervision.
- Force Account: Subset of administration where remaining work (≤10% cost and ≤₱2M) contracts out to a qualified contractor with cost-plus markup.
- Implementing Agency: Government or government-controlled entities executing the project.
- Job-Contractor: Entity responsible for a delegated job under its own supervision.
- Job-Order: Short-term employment for piece/lump sum work with duration ≤6 months.
- Labor-Only Contractor: Supplies labor without substantial capital or investment, and labor performs duties relating directly to principal business.
- Pakyaw: System of hiring labor groups with tools/materials provided by agency and lump sum payment.
- Skilled, Semi-skilled, Unskilled Work: Classification based on complexity and required judgment.
Conditions and Requirements for Negotiated Procurement (Section 54.2(d))
- Applicable only when immediate action is necessary to address imminent danger or restore vital services caused by calamity/emergency.
- Monetary limit: ₱2,000,000 unless presidential approval is granted.
- Projects above ₱2,000,000 must use short-listing under Section 54.2(b).
- Head of Agency or Local Chief Executive must certify the existence of conditions and justification for negotiated procurement.
- Negotiations must be with bona fide contractors from agency registry or local vicinity with prior satisfactory similar contracts.
- Transparency ensured via posting on Government Electronic Procurement System (G-EPS) and agency website.
Conditions and Requirements for "By Administration" Implementation
- Agency must have completed similar projects by contract or administration of at least 50% value and possess or have access to required equipment.
- No use of contractors allowed for works by administration.
- Head of agency must certify compliance with conditions before project commencement.
- Documentation must include detailed design, equipment and manpower schedules, and equipment leasing MOAs if applicable.
- Procurement of tools and equipment follows approved Project Procurement Management Plan (PPMP).
- Project approval required from agency head.
- Project cost caps: max ₱5,000,000 per project; NGAs/GOCCs/GFIs/SUCs capped at 25% of budget for infrastructure projects; LGUs capped at 50% of infrastructure fund.
- Force Account application allows contracting out unfinished portion (≤10% cost and ≤₱2,000,000) to qualified contractors under cost-plus markup; otherwise competitive bidding required.
Labor Component in Projects "By Administration"
- Manual labor may be performed in-house by personnel, through job-orders, or pakyaw contracting system.
- Pakyaw labor groups should be sourced locally from Barangays, municipalities, or province depending on skill level.
- Barangay leaders involved in organizing pakyaw labor groups with assistance from a Project Facilitator.
- Pakyaw work contracts require competitive selection where applicable, organized into groups to maximize labor participation.
- Group leader elected to act on behalf of the group; replacements allowed.
- Pakyaw groups must not be regular contractors or linked to labor-only or job-contractors formed for this purpose.
- Maximum contract amount per pakyaw group is ₱500,000.
Repealing and Effectivity Clauses
- These guidelines repeal GPPB Resolution 08-2004 related to administration or force account projects.
- Take effect 15 days after publication in the Official Gazette or a newspaper with nationwide circulation.
- Filing of certified copies required with the University of the Philippines Law Center.