Scope and Application
- These guidelines govern procurement and implementation of design and build contracts for infrastructure projects.
- Supplement existing provisions of RA 9184 and its Implementing Rules and Regulations Part A, especially Section 17.6 and Annex E.
Purpose of Guidelines
- To establish conditions under which the design and build scheme may be used.
- To set procedures for procurement and contract implementation under this scheme.
Guiding Principles
- Advantages: a) Single contractor responsible for both design and construction, including risks. b) Reduced design and construction periods and final project costs. c) Quality assured through involvement of expert contractors.
- Disadvantages: a) Difficulty in final cost prediction until actual construction starts. b) Contractor discretion may lead to differences from procuring entity's original requirements.
Definitions
- Approved Budget for the Contract (ABC): Lump sum covering design and construction costs based on conceptual design.
- Bidding Documents: Include performance specifications and risk allocation methods.
- Conceptual Design: General idea and scope of project facilities and construction methods.
- Design and Build Projects: Single contracts that cover both design and construction awarded to one entity.
- Performance Specifications and Parameters: Functional standards based on outputs, not favoring any design solution.
- Preliminary Investigations and Survey: Data gathering on technical and environmental conditions necessary for design criteria and cost estimates.
- Project Description and Utility Locations: Define project objectives, risk allocation, and existing utilities relevant to the site.
Conditions for Using Design and Build Scheme
- Suitable for: a) Flagship, priority and fast track projects listed in public investment plans. b) Projects requiring advanced technologies or proprietary intellectual property. c) Projects reliant on exclusive equipment, plant, or manufacturer know-how. d) Small projects with standardized designs where innovation can reduce costs and improve quality.
- All such projects must be listed in the procuring entity's Annual Procurement Plan (APP) and prior approved by the head of the entity.
Creation of Design and Build Committee
- Entities may form a committee of technical experts in architecture, engineering, and construction.
- The committee assists in design preparation, technical evaluations, and project supervision.
Preliminary Design and Construction Studies
- Pre-bid studies must be complete and approved, including conceptual design, specifications, surveys, utility data, budget estimates, and safety program requirements.
- Data accuracy is the contractor's responsibility.
- Procuring entity is responsible for right-of-way acquisition and eminent domain processes.
Detailed Engineering Requirements
- The winning bidder prepares and submits all detailed engineering plans and investigations, excluding bid documents and ABC.
- A schedule for submission and approval of detailed designs is included in contracts.
- Procuring entity reviews and approves or disapproves designs, with documented reasons for corrections.
- Contractor bears full responsibility for design integrity and structural performance.
Eligibility Requirements
- Must comply with legal, technical, and financial eligibility under Sections 23-24 of IRR-A.
- Bidders submit combined eligibility documents for infrastructure and consulting services.
- Experience requirements mandate at least one similar project comprising 50% of ABC.
- Joint ventures or consortia allowed with majority Filipino ownership (at least 75%), exceptions allowed down to 25% for projects needing foreign expertise.
- Professionals performing design services must be Filipino and properly licensed, with required authorization for foreign designers.
Bid Submission and Requirements
- First envelope (Technical Proposal) includes technical eligibility documents, preliminary conceptual design, methods, personnel qualifications, and value engineering analysis.
- Second envelope (Financial Proposal) includes lump sum bid price, detailed cost estimates, and payment schedule.
Bid Evaluation Process
- Two-step evaluation:
- Technical compliance pass/fail assessment based on design adherence, proposed methodology, and personnel qualifications.
- Opening and ranking of financial proposals for bidders who pass the technical evaluation.
- Oral presentations may be required for complex projects.
Post-Qualification and Award
- Lowest Calculated Bid (LCB) undergoes post-qualification to confirm responsiveness.
- Contract awarded to Lowest Calculated and Responsive Bid (LCRB).
- Approval or disapproval of BAC recommendations must be done within 7 days.
Contract Implementation
- Compliance with existing Annex E guidelines for infrastructure contract implementation.
- Work commencement requires written approval following receipt of all required contractor documents.
- Contractor responsible for obtaining risk and regulatory approvals.
- Submission and approval of detailed work program including design, construction methods, personnel, equipment, and quality control.
- Contractor costs for rectifications or changes due to their errors.
- Changes generally limited to unforeseen conditions.
- Change orders resulting from contractor errors implemented at no extra cost.
- Contractors compensated only if delays or costs arise from procuring entity changes, subject to limits.
- Payment schedules, advance payments, quality control, and inspection procedures clearly outlined.
- Minimum one-year Defects Liability Period for all projects.
- Contractor liable for design and structural defects.
Amendments and Forms
- GPPB authorized to issue further guidelines, amend provisions, and provide standard bidding and evaluation documents as needed.
Effectivity
- Guidelines take effect 15 days after publication and filing of certified copies with the University of the Philippines Law Center.