Question & AnswerQ&A (DPWH DEPARTMENT ORDER NO. 114)
The main purpose is to ensure that funds are available to meet escalation of construction costs due to inflation.
The built-in provision for price escalation contingencies must not exceed 12% per annum, based on price indices and projected inflation rates.
A 5% contingency portion is also required in addition to the 12% price escalation contingency.
The amount allocated for price escalation shall be obligated with the support of a separate Request for Obligation Authority (ROA).
Yes, a separate CAF shall be prepared for the price escalation funds.
Unused obligation for price escalation may be used to pay other unpaid claims of the contractor for the same project; otherwise, it shall revert to the unappropriated surplus.
Unobligated allotments of a completed project shall be used to cover any deficiency for price escalation of the same project not covered in the original contract through additional obligation or CAF.
It may be sourced from savings of other projects in accordance with the provisions of the General Appropriations Act.
No, it is an addition to the provisions of Department Order No. 36 series of 1989.
It was adopted on 8 May 1991.