Case Summary (G.R. No. L-18965)
Petitioner
WGCC contracted to perform the extension works (including the granitite wash-out finish) and tendered a one-year guarantee bond to cover defects in materials and workmanship in compliance with the construction contract.
Respondent
PCIB engaged WGCC under a written construction contract and, with concurrence of its consultant TCGI, accepted the completed work. PCIB supervised the project through its team of experts and supplied the materials for the granitite wash-out finish.
Key Dates and Events
Contract executed: October 20, 1989. Final acceptance and turnover: June 1, 1992 (with TCGI’s concurrence). Guarantee bond issued by Malayan Insurance: dated July 1, 1992. Observable failure of the granitite finish (peeling/falling): 1993. PCIB contracted Brains and Brawn to redo the entire finish after WGCC declined to perform full rework: 1994. PCIB’s out-of-pocket expenses for the rework: P11,665,000. WGCC counterclaimed for material cost adjustment: P5,777,157.84. Administrative and judicial proceedings culminated in a Supreme Court decision rendered March 24, 2006.
Applicable Law (including constitutional basis)
Because the decision date is in 2006, the 1987 Philippine Constitution is the governing constitutional backdrop. Governing statutory and civil law provisions cited in the decision include Article 1306 (autonomy of contracts), Article 1159 (obligations arising from contracts), and Article 1719 of the Civil Code (effect of acceptance of work on contractor’s liability). Contractual provisions central to the dispute are Article XI (Guarantee/Defects Liability Period) and Article 62.2 (Unfulfilled Obligations) of the parties’ construction contract.
Factual Background of the Contract and Defect Allegations
WGCC performed the extension works up to the specified floors and applied the granitite wash-out finish to exterior walls. PCIB, through its consultants and project supervision, inspected the works and issued the final certificate of acceptance. As required by the contract, WGCC furnished a one-year guarantee bond to secure its obligation to remedy defects discovered within one year after final acceptance. Thereafter, portions of the granitite finish began peeling off in 1993. WGCC performed minor repairs on request; however, when WGCC indicated it was not in a position to undertake full re-finishing, PCIB engaged another contractor in 1994 to redo the entire finish and sought reimbursement from WGCC.
Procedural History
PCIB filed for arbitration with the Construction Industry Arbitration Commission (CIAC) seeking reimbursement for the repair costs, alleging defective materials and workmanship by WGCC. WGCC counterclaimed. The CIAC found WGCC liable for the defects. WGCC then sought judicial review at the Court of Appeals (CA), which dismissed WGCC’s petition. WGCC’s motion for reconsideration in the CA was denied. WGCC elevated the matter to the Supreme Court by petition for review on certiorari.
Contractual Provision at the Heart of the Dispute (Article XI)
Article XI of the contract provided a one-year guarantee: the contractor guarantees the work and shall make good any defect in materials and workmanship evident within one year after final acceptance. The provision further allowed the owner and engineer to use the guarantee bond to have defects corrected by another contractor if the contractor failed to act promptly, while stating that nothing in the section shall relieve the contractor’s responsibility to the owner. The parties did not specify a different defects period for the granitite wash-out finish.
Legal Issues Presented
The primary legal question was whether WGCC remained liable for defects in the granitite wash-out finish that manifested after the lapse of the one-year defects liability period stipulated in Article XI. Subsidiary questions raised included whether the alleged defects were latent (hidden) defects such that liability survived acceptance under Article 1719 of the Civil Code, and whether PCIB bore the burden of proving such defects and met the substantial evidence standard.
Court’s Analysis — Autonomy of Contracts
The Court emphasized the autonomy of contracts under Article 1306 of the Civil Code: parties are free to stipulate terms so long as they do not contravene law, morals, or public policy. The defects-liability provision establishing a one-year warranty was a valid, customary, and reasonable contractual limitation, commonly used in Philippine private and government construction contracts. Absent evidence that the stipulation was contrary to law or public policy, the Court held that the contractual limitation on liability must be respected; otherwise the contractor would be subject to perpetual liability for workmanship and materials.
Court’s Analysis — Interpretation of Contractual Clauses (Article 62.2)
PCIB relied on Article 62.2, which preserves liability for obligations incurred prior to the issuance of the Defects Liability Certificate that remain unperformed. The Court concluded Article 62.2 did not extend the one-year defects period or apply to defects that manifested after the defects liability certificate was issued. The clause contemplates unperformed obligations existing at the time of issuance, not later-emerging defects.
Court’s Analysis — Article 1719 and the Nature of the Defects
Article 1719 relieves the contractor of liability for defects after acceptance of the work unless the defect is hidden/latent or the employer expressly reserves rights against the contractor. The Court examined the facts and rejected the characterization of the granitite failure as hidden defects. The Court relied on several factual considerations indicating that PCIB was in a position to observe or prevent defects: PCIB’s expert team supervised workmanship throughout the project; WGCC submitted progress reports and photographs; PCIB had access to the site and issued punch lists for compliance prior to acceptance; PCIB supplied the granitite materials; and TCGI gave concurrence to the turnover. Given these circumstances, the Court found no justification to treat the later peeling as latent defects insulated from the contractual one-year guarantee.
Burden of Proof and Evidence Considerations
The Court noted t
...continue readingCase Syllabus (G.R. No. L-18965)
Facts of the Case
- William Golangco Construction Corporation (WGCC) and Philippine Commercial International Bank (PCIB) entered into a contract for the construction of the extension of PCIB Tower II (denominated as PCIB Tower II, Extension Project) on October 20, 1989.
- The extension consisted of the fifth up to and including the twenty-first floor, with a supplement to the contract including construction work up to and including the twenty-third roof deck level.
- The project included, among other things, the application of a granitite wash-out finish on the exterior walls of the building. (The Court of Appeals referred to this as "pebble washout finish," though both parties agreed the subject was the "granitite wash-out finish.")
- PCIB, with the concurrence of its consultant TCGI Engineers (TCGI), accepted WGCC’s turnover of the completed work by letter dated June 1, 1992; PCIB’s Engineer and Project Manager was TCGI, and its architect was Leandro V. Locsin & Partners.
- To answer for any defect arising within a period of one year, WGCC submitted a guarantee bond dated July 1, 1992, issued by Malayan Insurance Company, Inc., in compliance with the construction contract.
- Portions of the granitite wash-out finish began peeling off and falling from the exterior walls in 1993.
- WGCC performed minor repairs after PCIB requested rectification of construction defects.
- In 1994 PCIB contracted Brains and Brawn Construction and Development Corporation to re-do the entire granitite wash-out finish after WGCC stated it was “not in a position to do the new finishing work,” though WGCC was willing to share part of the cost.
- PCIB incurred expenses amounting to P11,665,000 for the repair work.
- WGCC filed a counterclaim before the arbitral tribunal for P5,777,157.84 for material cost adjustment.
Contractual Background and Key Provisions
- The contract contained a defects liability period provision under ARTICLE XI ("a GUARANTEE"), which in relevant part provided:
- “Unless otherwise specified for specific works, and without prejudice to the rights and causes of action of the OWNER under Article 1723 of the Civil Code, the CONTRACTOR hereby guarantees the work stipulated in this Contract, and shall make good any defect in materials and workmanship which [becomes] evident within one (1) year after the final acceptance of the work.”
- “The CONTRACTOR shall leave the work in perfect order upon completion and present the final certificate to the ENGINEER promptly. If in the opinion of the OWNER and ENGINEER, the CONTRACTOR has failed to act promptly in rectifying any defect in the work which appears within the period mentioned above, the OWNER and the ENGINEER may, at their own discretion, using the Guarantee Bond amount for corrections, have the work done by another contractor at the expense of the CONTRACTOR or his bondsmen.”
- “However, nothing in this section shall in any way affect or relieve the CONTRACTOR’S responsibility to the OWNER. On the completion of the [w]orks, the CONTRACTOR shall clear away and remove from the site all constructional plant, surplus materials, rubbish and temporary works of every kind, and leave the whole of the [s]ite and [w]orks clean and in a workmanlike condition to the satisfaction of the ENGINEER and OWNER.” (Emphasis in source.)
- Article 62.2 of the contract provided another relevant clause:
- “62.2 Unfulfilled Obligations Notwithstanding the issue of the Defects Liability Certificate[,] the Contractor and the Owner shall remain liable for the fulfillment of any obligation[,] incurred under the provisions of the Contract prior to the issue of the Defects Liability Certificate[,] which remains unperformed at the time such Defects Liability Certificate is issued [. And] for the purpose of determining the nature and extent of any such obligation, the Contract shall be deemed to remain in force between the parties of the Contract.” (Emphasis in source.)
- Civil Code provisions cited in the decision:
- Article 1306: the autonomy of contracts — parties may establish stipulations provided they are not contrary to law, morals, good customs, public order, or public policy; obligations from contracts have the force of law between the parties and must be complied with in good faith.
- Article 1719: Acceptance of the work by the employer relieves the contractor of liability for any defect in the work, unless (1) the defect is hidden and the employer is not, by his special knowledge, expected to recognize the same; or (2) the employer expressly reserves his rights against the contractor by reason of the defect.
Procedural Timeline
- October 20, 1989: Contract for extension project executed between WGCC and PCIB.
- June 1, 1992: PCIB, with concurrence of TCGI, accepted turnover of completed work by WGCC.
- July 1, 1992: WGCC submitted a guarantee bond issued by Malayan Insurance Company, Inc. covering one-year defects liability.
- 1993: Portions of granitite wash-out finish began peeling and falling.
- 1994: PCIB contracted Brains and Brawn to re-do the entire granitite wash-out finish; PCIB spent P11,665,000.
- CIAC arbitration: PCIB filed for reimbursement of repair expenses; WGCC counterclaimed for material cost adjustment; CIAC declared WGCC liable for the construction defects (Decision in CIAC Case No. 07-95).
- WGCC filed petition for review with the Court of Appeals (C