Title
Werr Corp. International vs. Highlands Prime, Inc.
Case
G.R. No. 187543
Decision Date
Feb 8, 2017
Property developer HPI and contractor Werr disputed retention money, liquidated damages, and arbitration costs over delayed "Horizon-Westridge Project" completion.
A

Case Summary (G.R. No. 106063)

Factual Background

The parties contracted for the construction of 54 residential units in the Horizon‑Westridge Project in Tagaytay Midlands Complex, Talisay, Batangas. Highlands Prime, Inc. engaged Werr Corporation International as contractor under a lump sum contract price of P271,797,900.00. Werr received a 20% downpayment of P54,359,580.00 and the Agreement provided for ten percent retention in the form of a retention bond, a right of HPI to set off costs for rectification, and liquidated damages at 1/10 of 1% of the contract price per day of delay. Work commenced after the downpayment, but the project missed its initial and extended completion dates. HPI approved a Direct Payment Scheme in May 2006 for supplier obligations, partially funded against retention, and as of the last billing on October 25, 2006 HPI had paid P232,940,265.85 and retained P25,738,258.01 as retention. No progress billings were produced for the period from October 28, 2006 to termination. HPI terminated the contract on November 28, 2006; Werr accepted the termination on November 30, 2006.

Initiation of Arbitration and Claims

Werr demanded payment of outstanding amounts and filed a Complaint for arbitration before the CIAC seeking the balance of its retention money as reflected in its financial status report. HPI answered and set off amounts it had paid to suppliers and incurred for rectification and other costs, asserting that the retention had been applied under the Direct Payment Scheme and other deductions, and counterclaimed for liquidated damages, actual damages, attorney’s fees, and litigation expenses.

CIAC Proceedings and Findings

The CIAC adjudicated the parties’ claims and allowed Werr the balance of retention money in the amount of P10,955,899.79 and awarded liquidated damages to HPI in the amount of P2,535,059.01 based on its computation that Werr incurred 9.327 days of delay to reach substantial completion from the last admitted accomplishment of 93.18% on October 27, 2006. The CIAC disallowed several of HPI’s claims against the retention for being incurred after termination, for lack of documentary proof, or for failure to show prior notice as required by the Agreement, and it denied Werr’s claim for actual damages, attorney’s fees, and litigation expenses. The CIAC ordered respondent to reimburse arbitration costs to claimant.

Court of Appeals’ Ruling

HPI petitioned the Court of Appeals under Rule 43, and the CA modified the CIAC Decision. The CA affirmed the CIAC’s findings on allowable charges against the retention but disagreed on the computation of liquidated damages and arbitration costs. The CA held that delay should be computed from October 27, 2006 until the termination of the contract on November 28, 2006, or 33 days, because the contract governed and the Agreement did not incorporate an industry practice limiting liquidated damages to the date of substantial completion. The CA thus increased liquidated damages to P8,969,330.70 and apportioned arbitration costs equally between the parties.

Parties’ Contentions on Review

Werr contended before the Supreme Court that the CA erred by refusing to apply the prevailing construction industry practice, as reflected in CIAP Document No. 102, that liquidated damages do not accrue after substantial completion, and by substituting its own factual findings for those of the CIAC. Werr argued that the CIAC’s expertise and factual findings should prevail. HPI urged affirmance of the CA’s computation, argued that the direct payments and other expenses charged against the retention were proper and that Werr was not entitled to additional relief, and maintained that arbitration costs should not be borne by HPI alone.

Issues Presented

The Court framed the issues as: whether payments made to suppliers and contractors after termination are chargeable against the retention money; whether the industry practice of computing liquidated damages only up to substantial completion applies and thus whether delay should be computed to termination or to substantial completion; whether arbitration costs should be shared; and whether HPI is entitled to attorney’s fees and litigation expenses.

Standard of Review and Finality of CIAC Awards

The Court emphasized that the petitions were filed under Rule 45, thereby limiting review to questions of law. The Court reiterated the finality of CIAC arbitral awards under Executive Order No. 1008, and explained that factual findings by the CIAC are binding when supported by substantial evidence. The Court summarized recognized exceptions permitting review of factual findings, including awards procured by fraud, evident partiality, refusal to hear material evidence, disqualifications not disclosed, excess of powers, grave abuse of discretion affecting jurisdiction, contradictory findings between the CA and CIAC, and deprivation of administrative due process.

Charges Against the Retention Money — Conclusion

Applying the foregoing standard, the Court found that the issues whether the post‑termination payments were prior obligations and whether HPI incurred expenses warranting actual damages were factual matters beyond review under Rule 45. The Court held that HPI failed to demonstrate any of the exceptions to finality and that the CIAC’s findings, as affirmed by the CA, were supported by the record. The Court therefore affirmed the CIAC and CA conclusions that the direct payments made in 2007 and 2008 were for materials supplied after termination, that certain post‑termination works were for the account of the new contractor, and that HPI failed to prove payment for rectification works and prior notice of defects; accordingly, the balance of the retention money remained P10,955,899.79.

Computation of Liquidated Damages — Legal Reasoning and Ruling

The Supreme Court treated the computation of liquidated damages as a question of law and reviewed whether the construction industry practice should supplement the parties’ Agreement. The Court recognized that parties may stipulate contract terms under Art. 1306 and that general provisions of the Civil Code, notably Art. 1234 and Art. 1376, and customary industry practice may supplement contractual omissions. The Court held that CIAP Document No. 102 has suppletory effect for private construction contracts and that the industry practice that substantial completion (95% performance per Article 20.11) excuses the contractor from liquidated damages may supplement an agreement silent on the period during which liquidated damages run. Nevertheless, the Court ruled that the equitable effect of substantial completion applies only where the contractor proves by substantial evidence that it actually achieved 95% completion before or at termination. The Court found that Werr failed to prove accomplishment of 95% at termination and failed to show that it was industry practice to project the date of substantial completion and compute delay based on prior billing rates. The Court further held that the CIAC erred in assuming continued p

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.