Title
Uy vs. Public Estates Authority
Case
G.R. No. 147925-26
Decision Date
Jun 8, 2009
Contractor Uy sought compensation for delays and additional costs in a landscaping project with PEA, leading to arbitration and court rulings on claims, attorney fees, and procedural issues.

Case Summary (G.R. No. 147925-26)

Applicable Law and Administrative Context

The Construction Industry Arbitration Commission (CIAC) and the applicable provisions of the 1987 Philippine Constitution govern the proceedings and the adjudication of disputes arising from the agreement. The case involves claims related to delays in contract performance and demands for additional costs incurred by Uy due to actions attributed to PEA.

Background of the Agreement and Performance Issues

On November 20, 1996, Uy entered into a Landscaping and Construction Agreement with PEA for a total price of P355,080,141.15, requiring completion within 450 days. The application of this timeline was hindered due to delays in the turnover of work areas by PEA, primarily because horizontal works by a different contractor, Makati Development Corporation (MDC), were ongoing. Consequently, Uy commenced work on January 7, 1997, and experienced further delays, leading to an extension of the contract period to 693 days.

Claims for Additional Costs

Due to the delays, Uy sought additional compensation amounting to P181,338,056.30, representing costs for idle equipment, labor, and additional topsoil procurement. The PEA Project Management Office (PEA-PMO) evaluated the claims and arrived at a lesser amount of P146,484,910, which led to disputes regarding obligations and liabilities.

CIAC Decision and Subsequent Appeals

The CIAC eventually ruled in favor of Uy, awarding him amounts for idle equipment and labor and for constructing a nursery shade net area. PEA contested the decision but failed to adhere to procedural rules, while Uy filed a motion for correction of computation that went unresolved, leading to further appeals to the Court of Appeals. The Court found PEA’s challenges lacked merit, maintaining that the CIAC's award was justified based on the presented evidence.

Grounds for Dismissal by the Court of Appeals

The Court of Appeals dismissed Uy’s petition on the grounds of being belatedly filed and upheld the CIAC's decision. Additionally, the court found insufficient justification to reverse the CIAC ruling based on contract provisions, available evidence, and relevant legal principles.

Injunctive Relief and Concurrent Claims

PEA’s plea for injunction against Uy’s new claims in CIAC Case No. 03-2001 was granted by the Court of Appeals, emphasizing the principle of litis pendentia given the overlap of issues between the cases. This was deemed necessary to prevent the inefficiencies associated with concurrent proceedings addressing the same contractual disputes.

Findings on Procedural Issues and Claim Validity

Examining procedural matters, the Supreme Court acknowledged that Uy’s appeal had been timely filed as the running of the appeal period was interrupted by his motion for correction. On substantive grounds, the Court rejected Uy’s claims for costs related to topsoil and water truck mobilization, citing the lack of required prior written approvals as stipulated in the contract. The Court concluded that Uy acted inappropriately by accruing additional costs without ensuri

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.