Title
Supreme Court
Uniwide Sales Realty and Resources Corp. vs. Titan-Ikeda Construction and Development Corporation
Case
G.R. No. 126619
Decision Date
Dec 20, 2006
Construction disputes between Titan and Uniwide over three projects: overpayments, VAT liability, delays, and defects. CIAC ruled for Titan; SC affirmed with modifications, denying Uniwide's claims.

Case Summary (G.R. No. 126619)

Agreements for Projects 1–3

Project 1 (May 1991): Written contract for a Warehouse Club and Administration Building in Libis, Quezon City; contract price ₱120,936,591.50; completion stipulated by November 30, 1991; actual turnover February 15, 1992.
Project 2 (July 1992): Oral agreement to add a floor and renovate a warehouse at EDSA Central Market, Mandaluyong; based on cost estimate ₱21,301,075.77 (including 20% mark-up); ₱15,000,000 received; turnover October 1992.
Project 3 (May 1992): Written contract for Sales Department Store in Kalookan City; contract price ₱118,000,000; completion by February 28, 1993; actual turnover June 1993.

Arbitral Proceedings

• CIAC Reference (1994): Titan re-filed its claim under Executive Order No. 1008 after RTC suspension.
• Uniwide’s defenses and counterclaims: overpayment refunds, VAT non-liability, liquidated damages, defective construction.
• Tribunal process: Terms of Reference signed, ocular inspection, affidavits, hearings, memoranda.
• CIAC Decision (April 17, 1995):
– Project 1: Uniwide absolved of liability.
– Project 2: Uniwide pays unpaid balance ₱6,301,075.77 with 12% p.a. interest; absolved of defective construction and VAT liability.
– Project 3: Uniwide pays unpaid balance ₱5,158,364.63 with 12% p.a. interest; Uniwide liable for VAT.

Court of Appeals Modification (February 21, 1996)

• VAT on Project 3 may be passed to Titan.
• Liquidated-damages denial without prejudice.
• Interest rate on unpaid balances reduced from 12% to 6% p.a.
• Other CIAC findings affirmed.

Standard of Review and Applicable Law

• Arbitration awards are final on facts, subject to narrow exceptions (fraud, partiality, misconduct, excess of powers, grave abuse of discretion, conflicting findings).
• Factual issues may be reviewed where CIAC and CA findings diverge.
• Governing laws: New Civil Code (Arts. 1423, 1723, 1724, 2154, 2156), National Internal Revenue Code (Secs. 99, 102), CIAC Rules, Rules of Court (Rule 45, Civil Code provisions), National Building Code (PD 1096).

Issue 1: Reimbursement for Unauthorized Additional Works (Project 1)

Uniwide contended payments (₱5,823,481.75) were made by mistake for works not authorized in writing. CIAC and CA: absence of proof of mistake; Section 3(f), Rule 131 presumes paid sums were due; Art. 1724 does not itself grant reimbursement right once payment is made; solutio indebiti (Arts. 2154, 2156) requires proof of debtor’s mistake or doubt. Neither tribunal found evidence Uniwide paid under mistake.

Issue 2: VAT Liability (Project 1)

Contract silent on VAT; Uniwide argued VAT included in contract price. CIAC and CA relied on Titan’s October 7, 1992 Order of Payment billing ₱2,400,000 as 4% VAT on ₱60,000,000, approved by Uniwide president and identifying Project 1. CIAC held parties agreed to pass VAT on but limited to ₱60 million base; balance VAT remains Titan’s obligation.

Issue 3: Liquidated Damages (Projects 1 and 3)

Uniwide claimed liquidated damages for delays. CIAC refused to resolve because claim was not raised in CIAC’s Terms of Reference or amended therein; Rule 10, Sec. 5 of Rules of Court not applicable to CIAC’s voluntary arbitration process. CA agreed claim was too belated and unformulated for Titan or tribunal to address. Evidence on completion dates did not alo




...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.