Title
Supreme Court
Transcept Construction and Management Professionals, Inc. vs. Aguilar
Case
G.R. No. 177556
Decision Date
Dec 8, 2010
Aguilar contracted Transcept for a vacation house construction. Disputes arose over billing, work quality, and delays. Courts ruled on refunds, liquidated damages, and consultancy fees, adjusting awards based on substantial completion and substandard work corrections.

Case Summary (G.R. No. 177556)

Antecedent Facts

On August 18, 2004, Aguilar and Transcept entered into an Owner-General Contractor Agreement for the construction of a two-storey vacation house, establishing a project cost of approximately P3.49 million, with a completion date projected for June 7, 2005. Aguilar made an initial downpayment of P1 million. As the project progressed, disputes arose over billing practices and the adequacy of the work performed by Transcept. Following substantial compliance issues identified by a testing laboratory, Aguilar alleged substandard work and further withheld payments, leading to Transcept's cessation of work on the project.

Decision of the Construction Industry Arbitration Commission (CIAC)

The CIAC assessed the value of the work completed and determined that Aguilar had overpaid Transcept. Ultimately, the CIAC found that the value of completed work equated to P1,602,359.97, indicating a substantial compliance with the initial contract. The CIAC ruled that Aguilar was entitled to refunds of P30,076.72 for unaccomplished works and P75,000 for consultancy expenses while denying liquidated damages due to the finding of substantial completion.

Decision of the Court of Appeals

Aguilar appealed the CIAC's ruling, leading the Court of Appeals to conduct a reassessment. On January 24, 2007, the Court of Appeals recalculated cost estimations, finding Aguilar was owed P198,916.02 for unaccomplished works and awarded liquidated damages, arguing that Transcept had only achieved 87.81% of the contract obligations. The Court further determined that Transcept was not entitled to costs for additional works as these were deemed rectifications of prior inadequacies.

Key Issues

The central legal issues deliberated included whether the Court of Appeals made errors in: (1) determining the amount due to Aguilar for unaccomplished works; (2) awarding liquidated damages; (3) denying Transcept's claims for additional works; and (4) awarding consultancy service fees to Aguilar.

Ruling of the Supreme Court

The Supreme Court partially granted the petition, emphasizing that the CIAC's assessment of unaccomplished works was accurate based on the total project obligations. The Court struck down the liquidated damages award by referring to provisions under the Construction Industry Authority of the Philippines (CIAP) documents, affirming that the degree of completion met t

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.