Title
Tanguilig vs. Court of Appeals
Case
G.R. No. 117190
Decision Date
Jan 2, 1997
Contract dispute over windmill construction; deep well excluded, collapse due to defects; petitioner liable for reconstruction under guaranty, respondent to pay balance.

Case Summary (G.R. No. 211724)

Contract Formation and Express Terms

The parties negotiated two written proposals from petitioner: one dated 19 May 1987 quoting P87,000 (rejected) and another dated 22 May 1987 quoting P60,000 (accepted). The accepted proposal described a windmill assembly “suitable for 2 inches or 3 inches deep-well pump” and listed items relating to the windmill assembly, tower, standard appurtenances, and concreting materials; it did not include an itemized description or any express commitment to construct a deep well. The one-year guaranty from completion and acceptance is an express contractual term.

Payment History and Respondent’s Claim

Respondent paid petitioner a P30,000 down payment and a P15,000 installment, leaving an asserted balance of P15,000. Respondent contended in defense that he paid P15,000 directly to San Pedro General Merchandising, Inc. (SPGMI), which installed the deep well to be connected to the windmill, and that payment to SPGMI should be credited against his balance with petitioner because the deep well formed part of the windmill project.

Trial Court Findings

The trial court held that construction of the deep well was not part of the windmill project, relying primarily on the letter-proposals which did not expressly include deep-well construction. It also found insufficient proof that defects in construction caused the windmill’s collapse and thus did not hold petitioner liable for reconstruction under the guaranty. On the payment issue, the trial court accepted that the deep well was not included in petitioner’s contract price.

Court of Appeals Ruling

The Court of Appeals reversed the trial court: it found that “deep well” was mentioned in both proposals and, considering testimony from SPGMI’s proprietor (Guillermo Pili) that petitioner told him the cost would be deducted from the P60,000 contract price, concluded the deep well was included in the parties’ agreement. The appellate court applied respondent’s P15,000 payment to extinguish his balance with petitioner, rejected petitioner’s force majeure defense, and ordered petitioner to reconstruct the windmill under the one-year guaranty.

Issues on Review and Standard of Appellate Review

The Supreme Court framed the issues as (1) whether the contract included the installation of the deep well, and (2) whether petitioner was obliged to reconstruct the windmill after collapse. The Court applied principles of contractual interpretation: clear and unambiguous terms control, the intention of the parties is paramount, and contemporaneous and subsequent acts may be considered where doubt exists (citing Art. 1371, New Civil Code, and pertinent authorities).

Interpretation of “deep well” in the Proposals

The Supreme Court concluded that the accepted 22 May 1987 proposal did not include construction of a deep well. Though the documents mentioned “deep well” or “deep-well pump,” the phrasing (e.g., “suitable for … deep-well pump”) described the type of pump the windmill would operate rather than promising to construct a well. The Court stressed that had the parties intended to include deep-well construction, conjunctive language such as “and” or “with” would have been used and the proposal would have itemized materials and workmanship for the well.

Contemporaneous and Subsequent Acts and Credibility of Evidence

Examining contemporaneous acts and the parties’ conduct, the Court found respondent’s version unpersuasive. The alleged letter from respondent to Pili was not produced; Pili’s testimony that petitioner told him the deep well cost would be deducted was not corroborated and was improbable absent written commitments. That respondent himself paid Pili P15,000 suggested the well installation was a separate agreement between respondent and SPGMI. The Court held there was no evidence that Pili or SPGMI was authorized to receive payment on petitioner’s behalf; hence legal doctrines regarding payments to a creditor or by a third person (Arts. 1236–1240, New Civil Code) did not operate to extinguish respondent’s obligation to petitioner.

Payment by Third Party and Legal Effect

The Court emphasized the principle that payment must be made to the person in whose favor the obligation subsists, or to an authorized representative (Art. 1240). Since no creditor-debtor relationship or authorization between petitioner and SPGMI was established, respondent’s direct payment to Pili could not be imputed to extinguish the debt to petitioner. The contemporaneous circumstances supported the conclusion that the deep well contract was between respondent and SPGMI, not part of the windmill contract with petitioner.

Fortuitous Event (Force Majeure) Analysis

On the issue of reconstruction and petitioner's force majeure defense, the Court applied its established requisites for exemption under Article 1174 (as elaborated in Nakpil): (a) independence from the debtor’s will; (b) unforeseeable or unavoidable character; (c) impossibility to fulfill the obligation normally; and (d) absence of debtor participation or aggravation. The Court found petitioner failed to prove the collapse was caused solely by a fortuitous event. The record did not show a typhoon occurred; petitioner referred only to a “strong wind.” The Court reasoned that strong wind is not unforeseeable where windmills are installed (indeed, such conditions are the anticipated operating env

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.