Case Summary (G.R. No. 238671)
Factual Background
Taisei Shimizu Joint Venture contracted with the Department of Transportation on March 15, 2004 for the construction of the New Iloilo Airport. After project completion, TSJV alleged unpaid billings and filed with the Construction Industry Arbitration Commission (CIAC) a Request for Arbitration and Complaint seeking multiple monetary claims arising from variation orders, currency conversion losses, interest on delayed payments, price adjustments, extension-of-time related costs, additional embankment works, damages for delayed payment of aggregates, and litigation costs; the aggregate original claim exceeded Php2,316,687,603.03.
Arbitral Proceedings and Award
The CIAC conducted arbitration and, by its Final Award dated December 11, 2014, granted several claims in favor of TSJV totaling Php223,401,870.83 and directed the DOTr to pay six percent per annum interest from the finality of the award until full payment. On DOTr’s motion for correction, the CIAC issued an Order dated February 20, 2015 reducing one component of the award and amending the total to Php216,073,986.89.
Attempts at Execution and COA Petition
TSJV sought execution of the CIAC award. The CIAC, by resolution dated April 22, 2015, directed implementation of a writ of execution. The DOTr opposed garnishment on grounds that the funds were public and later informed TSJV that COA approval was a condition precedent to payment. Several banks reported no funds in DOTr’s name; the Land Bank advised that COA approval was required. TSJV then filed a petition with the Commission on Audit for enforcement and payment of the arbitral award. The DOTr, through the Office of the Solicitor General, acknowledged the CIAC award and its amended amount and stated it had no further comments on the arbitral determination.
COA Proceedings and Rulings
By Decision No. 2016-395 dated December 21, 2016, the Commission on Audit approved payment only to the extent of Php104,661,421.35 corresponding to Claim No. 4 and partially disapproved payment of the remaining awarded amounts. The COA grounded its disallowances on statutory and regulatory provisions, principally asserting that Claim No. 1 involved price adjustments subject to Section 61 of Republic Act No. 9184 and its IRR and that no prior approvals (including from NEDA and the head of the procuring agency) were shown; that interest and extension-of-time costs lacked statutory authorization; and that attorney’s fees were barred by Section 1, Rule 142 of the Rules of Court. TSJV moved for partial reconsideration, which the COA denied by Resolution No. 2018-047 dated January 22, 2018. COA Chairperson Michael G. Aguinaldo dissented, distinguishing between original money claims filed with COA and money claims arising from final and executory judgments.
Procedural History and Petition
TSJV filed a petition for certiorari under Rule 65 in relation to Rule 64 of the Rules of Court, alleging that the COA committed grave abuse of discretion by modifying and disallowing portions of a final and executory arbitral award. The COA defended its action as within its primary jurisdiction over money claims against the government and as an exercise of quasi-judicial audit authority to approve or disapprove payments even when based on a final judgment or award.
Issues Presented
The Supreme Court articulated the principal issues as: (i) whether the COA has exclusive jurisdiction over money claims due from or owing to the government; and (ii) whether, in the exercise of its audit power, the COA may disturb the final and executory decisions of courts, tribunals, or other adjudicative bodies.
Supreme Court's Ruling
The Court granted the petition. It held that while the Commission on Audit possessed primary jurisdiction over money claims against the government, that jurisdiction was not exclusive and did not empower COA to modify or set aside a final and executory award rendered by a tribunal that validly exercised jurisdiction. The Court ruled that the CIAC had exclusive jurisdiction over disputes arising from construction contracts voluntarily submitted to arbitration under Executive Order No. 1008, that the CIAC’s modified final award had become final and binding, and that the COA gravely abused its discretion by reweighing evidence and disallowing substantial portions of that award. The Court reversed and set aside COA Decision No. 2016-395 and Resolution No. 2018-047 insofar as they disapproved payment of Claim Nos. 1, 3, 5, and 8, and remanded the case to COA for expeditious payment of the balance of the arbitral award in the amount of Php111,412,565.54.
Legal Basis and Reasoning
The Court began from Article IX-D, Section 2(1), 1987 Constitution and statutory provisions such as P.D. No. 1445 and the COA Rules, recognizing COA’s broad audit mandate to examine, audit, and settle accounts and money claims. The Court nevertheless emphasized that nothing in the Constitution, statutes, or COA rules conferred original and exclusive jurisdiction over money claims to COA to the exclusion of courts or other tribunals. It relied on prior jurisprudence establishing that COA’s competence is circumscribed, that COA’s original jurisdiction is properly limited to liquidated claims and accounting matters, and that other specialized tribunals or courts may exercise concurrent or exclusive jurisdiction when statutes so provide. The Court construed E.O. No. 1008 as a specific law granting CIAC original and exclusive jurisdiction over construction disputes voluntarily submitted to arbitration; this specific grant prevailed over PD 1445’s general audit jurisdiction. The Court distinguished between two types of money claims confronting COA: (a) original claims filed with COA, typically liquidated and accounting in nature; and (b) claims that have been reduced to final and executory judgments or awards. For the latter, the Court reiterated the doctrines of res judicata and the immutability of final judgments, observing that COA lacked appellate power to reexamine factual and legal determinations made by a competent tribunal and could not override the finality of the CIAC award except under recognized exceptions (clerical errors, nunc pro tunc entries, void judgments, or other narrow circumstances). The Court held that COA’s proper role regarding final money judgments was aki
...continue reading
Case Syllabus (G.R. No. 238671)
Parties and Posture
- Taisei Shimizu Joint Venture was the petitioner in a certiorari action under Rule 65 attacking COA Decision No. 2016-395 and Resolution No. 2018-047 in COA C.P. Case No. 2015-622.
- Commission on Audit and the Department of Transportation were the respondents in the petition for certiorari.
- The CIAC rendered a final arbitral award in favor of the petitioner which the petitioner sought to execute and enforce.
- The petition was resolved by the Court en banc and the dispositive ruling was authored by LAZARO-JAVIER, J.
Key Facts
- Taisei Shimizu Joint Venture entered into a construction contract with the Department of Transportation for the New Iloilo Airport and completed the project but allegedly suffered unpaid billings.
- TSJV filed a Request for Arbitration before the CIAC seeking multiple monetary claims totaling Php2,316,687,603.03 as pleaded in its Terms of Reference.
- The CIAC issued a Final Award dated December 11, 2014 granting certain claims in the aggregate amount of Php223,401,870.83 and ordered six percent interest per annum from finality until full payment.
- The CIAC corrected its award by Order dated February 20, 2015 to reduce the amount to Php216,073,986.89 after deleting a VAT component.
- The CIAC ordered execution and the sheriff attempted garnishment but banks and the LBP advised that COA approval was necessary for payment from government funds.
- TSJV filed a petition for enforcement with the Commission on Audit, to which the DOTr, through the OSG, admitted the award and its reduced amount and expressed no further objection.
- By Decision No. 2016-395, the Commission on Audit approved payment only to the extent of Php104,661,421.35 and disapproved the remainder of the award for reasons including alleged noncompliance with procurement and audit rules.
- TSJV moved for reconsideration and relied on the immutability of final and executory awards under E.O. No. 1008 and on other authorities, but the COA denied the motion by Resolution No. 2018-047 with Chairperson Michael G. Aguinaldo dissenting.
Statutory Framework
- Article IX-D, Sections 1 and 2, 1987 Constitution defines the composition and the power, authority, and duty of the Commission on Audit to examine, audit, and settle accounts pertaining to government funds.
- P.D. No. 1445 (Government Auditing Code of the Philippines), Section 26, grants the COA authority to audit and settle accounts and to examine debts and claims due from or owing to the Government.
- The 2009 Revised Rules of Procedure of the Commission on Audit, Section 1, Rule II and Section 1, Rule VIII, enumerate the COA's general and original jurisdiction including money claims against the Government.
- Republic Act No. 9184, Section 61 and its IRR provide that bid prices are fixed and are not subject to price escalation except under extraordinary circumstances and upon prior approval, with NEDA and GPPB roles specified.
- E.O. No. 1008 (Construction Industry Arbitration Law), Section 4, vests the CIAC with original and exclusive jurisdiction over construction contract disputes when parties agree to arbitration, and Section 19 declares arbitral awards final and inappealable except on questions of law.
- Batas Pambansa Blg. 129 (as amended) prescribes the jurisdictional allocation to trial courts for civil cases against the State.
- P.D. No. 1594, E.O. No. 40, Rule 142, Sec. 1 of the Rules of Court, Article 2208(5) of the Civil Code, and CIAC Rule Section 16.5 were invoked in the proceedings as relevant legal touchstones.
Issues
- Whether the Commission on Audit has exclusive jurisdiction over money claims due from or owing to the Government.
- Whether the Commission on Audit, in the exercise of its audit power, may disturb final and executory decisions of courts, tribunals, or other adjudicative bodies.