Case Summary (G.R. No. 142985)
Key Dates
First Agreement executed May 21, 2009. Notice of Award/Notice to Proceed issued March 25, 2010. Second Agreement executed April 5, 2010. WAO No. 20 dated August 24, 2010. CIAC Final Award promulgated July 16, 2012. CA Decision promulgated January 31, 2013. Petition for review to the Supreme Court decided September 21, 2022. (Applicable constitutional framework: 1987 Philippine Constitution, as decision date is 1990 or later.)
Applicable Law and Rules
Primary legal sources invoked: Civil Code of the Philippines (Articles 1291, 1292, 1370, 1371) on obligations, novation, and contract interpretation; Rules of Court (Rule 45 and Rule 43 provisions cited in the record, and Rule 133 evidentiary standard); CIAC Revised Rules of Procedure Governing Construction Arbitration (Section 18.2, Rule 13.5, Section 13.5); administrative-law principles on substantial evidence and relaxed technical rules on evidence in administrative proceedings. Doctrines applied: express/objective novation, solutio indebiti (recovery of undue payment), unjust enrichment, compensation between mutual creditors and debtors, and de minimis non curat lex.
Core Factual Background
SECOR was engaged to perform electrical works under a First Owner–Contractor Agreement (fixed lump sum P15,250,000.00). Work was suspended after a few months. BDI later issued a Notice of Award/Notice to Proceed (March 25, 2010) reflecting substantially expanded works and higher amounts, and the parties executed a Second Agreement (April 5, 2010) with a contract price of P51,550,000.00. Numerous Work Authorization Orders (WAOs) followed. The total actual cost alleged by respondent amounted to P80,711,308.05. Respondent paid petitioner amounts apparently covering full contract prices less contested retention sums; the contested unpaid items/consolidated demand amounted to P8,030,000.00 (two retention fees and unpaid WAO No. 20).
Important Contractual Provisions
First Agreement: fixed lump sum P15,250,000.00; Article 2.02 incorporated mutually agreed documents into contract; Article 5.05 addressed adjustments for additional or reduced work. Second Agreement: Article 2.4 declared the contract documents as containing the entire agreement, superseding all prior agreements and deeming prior documents not forming part as waived/abandoned. Second Agreement expanded the scope to include new major structures (vault substation, CCTV, FDAS) and amended contract price and billing scheme (monthly billings based on percent accomplished).
Parties’ Performance, Payments and Claims
Certificates of Final Inspection (September 1 and 7, 2010) issued for completion of certain works under the revised plan. Respondent paid considerable sums to petitioner; retention fees (10% under each contract) and unpaid WAO No. 20 remained disputed. Petitioner demanded payment of P8,030,000.00; respondent requested documentary support for the cost escalation from P15,250,000.00 to P80,711,308.05. Petitioner filed CIAC arbitration (September 13, 2011). Respondent counterclaimed for reimbursement of alleged excess payments under the First Agreement (asserting novation by the Second Agreement).
CIAC Proceedings and Final Award
After hearings, CIAC awarded petitioner the three contested amounts totaling P8,030,000.00 plus 12% legal interest from finality of the award; denied exemplary damages, attorney’s fees, and respondent’s counterclaims. CIAC’s findings emphasized (a) that the Second Agreement did not contain a specific stipulation expressly declaring the First Agreement superseded; (b) that the core issue was petitioner’s proper compensation for services rendered and billed; (c) that no fraud or vitiation of consent justified undoing contractual terms; and (d) that respondent’s professionals’ evaluations did not show irregularities, binding respondent to pay for services rendered.
CA Decision and Modifications
BDI sought judicial review under Rule 43; the CA modified CIAC’s Final Award. The CA concluded insufficient evidentiary basis for CIAC’s monetary awards because petitioner failed to prove completion of work under the First Agreement. The CA found the Second Agreement had superseded the First (relying on an as-built plan matching the revised plan and an unsigned Jarhaus Options & Trends report indicating only 6.774% completion under the original plan). The CA ordered SECOR to reimburse BDI P13,593,273.00, computed by offsetting amounts paid against petitioner’s entitlement (one retention fee for the Second Agreement, 6.774% attributable to the First Agreement, and WAO No. 20), and denied other damages and fees.
Issues Presented to the Supreme Court
- Whether Article 2.4 of the Second Agreement was ambiguous or whether doubt existed as to its interpretation and effect on the First Agreement. 2) Whether the Second Agreement effected an objective (express) novation extinguishing the First Agreement. 3) Whether sufficient evidence established the percentage of accomplished work by petitioner under the First Agreement.
Procedural Consideration on Reconsideration and Reviewability
The Supreme Court noted petitioner failed to file a motion for reconsideration of the CA decision but observed Rule 45 of the 1997 Rules of Court does not strictly require such motion for an appeal by certiorari. Although petitioner should ordinarily have afforded the CA the opportunity to reconsider, the Court proceeded to resolve substantive issues given the case’s importance and protracted duration.
Principles of Contract Interpretation and Novation Applied
The Court applied Civil Code Article 1370 (literal meaning and prevailing intent) and Article 1371 (contemporaneous and subsequent acts as guides). It emphasized that an express novation (objective novation under Articles 1291–1292) requires clear agreement of the parties to extinguish the old obligation or that the new and old be incompatible on every point; novation is not presumed. The Court treated Article 2.4 as an express novation clause put in issue by petitioner, thereby requiring judicial inquiry into the parties’ contemporaneous and subsequent acts and admissions to determine true intent.
Factual and Expert Evidence on Difference Between Original and Revised Plans
The Court found substantial evidence that the revised plan materially changed the project’s subject matter: a substantially higher contract price, inclusion of vault substation and CCTV (not in the original), and technical differences demonstrated by respondent’s project engineer’s affidavits comparing Design 1 (original) and Design 2 (revised) and the as-built plan. Petitioner’s own president conceded significant increases in scope and cost in the revised plan, although he maintained the First Agreement subsisted. Given the disparity in scope and the single as-built output satisfying the revised specifications, the Court concluded the change was essential (principal) rather than merely accidental.
Critique of CIAC’s Evidentiary Approach
The Supreme Court found that CIAC erred by failing to resolve the critical evidentiary question whether the revised plan was substantially different. CIAC’s omission to make c
...continue readingCase Syllabus (G.R. No. 142985)
Procedural Posture
- Petition for Review on Certiorari under Rule 45 filed with the Supreme Court to set aside the Court of Appeals (CA) Decision dated January 31, 2013 in CA-G.R. SP No. 125889 and to reinstate the Construction Industry Arbitration Commission (CIAC) Final Award dated July 16, 2012 (CIAC Case No. 25-2011).
- CIAC proceedings initiated by Systems Energizer Corporation (petitioner/claimant before CIAC) by filing Complaint on September 13, 2011.
- Respondent (Bellville Development, Inc.) filed Answer with Counterclaim before the CIAC.
- CIAC promulgated Final Award on July 16, 2012 granting claimant retention fees and WAO No. 20 value (total Php8,030,000.00) with 12% legal interest; denied exemplary damages and attorneys’ fees for both parties; allocated arbitration costs pro rata.
- Respondent sought review of the CIAC award at the Court of Appeals under Rule 43 in relation to Section 18.2 of the CIAC Revised Rules; CA issued Decision on January 31, 2013 modifying the CIAC Award and ordering reimbursement of Php13,593,273.00 as excess payment.
- Petitioner instituted the present Rule 45 petition to the Supreme Court; Supreme Court denied the petition and affirmed the CA Decision (G.R. No. 205737, September 21, 2022).
Factual Background — Parties, Project, and Initial Agreement
- Parties: Systems Energizer Corporation (SECOR) engaged as Contractor; Bellville Development, Inc. (BDI) as Owner.
- Project: Electrical works for Molito 3 / Puregold Commercial Building inside El Molito Commercial Complex, corner Madrigal Ave. and Alabang–Zapote Road, Barangay Alabang, Muntinlupa City.
- First Agreement: Owner-Contractor Agreement executed May 21, 2009. Contract price: fixed lump sum of Php15,250,000.00.
- Notable provisions of First Agreement:
- Article 2.02: other documents mutually agreed and signed by Owner and Contractor shall form part of Contract Documents.
- Article 5.05: if Owner requires Contractor to perform additional or reduced work, costs shall be added to or deducted from the Contract Price in Article 5.01.
- Work commenced but suspended after a few months allegedly due to issues with structural contractor and the deaths of two vice presidents who were signatories to the First Agreement.
Notice of Award / Revised Scope and Second Agreement Formation
- Notice of Award / Notice to Proceed dated March 25, 2010 issued to petitioner, detailing new scope items and variation/change orders:
- Architectural & Structural Vault Sub-station: Php2,000,000.00; Downpayment Php400,000.00 (20%).
- Vault Sub-station System: Php19,800,000.00; Downpayment Php5,940,000.00 (30%).
- CCTV System: Php1,500,000.00; Downpayment Php450,000.00 (30%).
- Changes/Revisions of Electrical Building Plans dated October 17, 2009: Php28,250,000.00; Downpayment Php8,475,000.00 (30%).
- Total contract amount stated: Php51,550,000.00 inclusive of VAT and taxes; downpayment aggregate Php15,265,000.00; construction period to commence 90 calendar days from March 15, 2010 with completion date indicated June 14, 2010.
- Parties executed Second Agreement dated April 5, 2010 to reflect new specifications indicated in the March 25, 2010 Notice.
- Second Agreement:
- Scope expanded to cover the entirety of electrical works including additional major structures (vault substation, CCTV).
- Contract price: Php51,550,000.00.
- Payment: monthly billings based on percentage of actual accomplishment with summaries of accomplishment prepared by the construction manager and accepted by respondent.
- Article 2.4: expressly declared that the Contract Documents contain the entire agreement and understanding and “supersedes all prior agreements, commitments, representations, writing, and discussions between them,” and that prior documents not forming part of the enumerated Contract Documents are “deemed waived and/or abandoned.”
Work, Certifications, Change Orders, and Final Costs
- Additional Work Authorization Orders (WAOs) were entered during the course of the project for further electrical installations; WAO No. 20 dated August 24, 2010 listed nine additional installations and had a value of Php1,350,000.00.
- Certificates of Final Inspection and Acceptance in the record:
- Certificate dated September 1, 2010: completion of the CCTV system installation.
- Certificate dated September 7, 2010: completion of electrical works, fire protection/fire detection and suppression system (FDAS), and the power substation vault.
- Respondent’s Statement of Actual Cost Accounting & Summary of Expenses showed petitioner’s services cost amounting to Php80,711,308.05 (prepared by respondent’s accountant/finance manager).
- Record indicates respondent paid petitioner amounts for the First and Second Agreements, but retained retention fees of 10% under both contracts (no receipts or billings attached in record).
- Retention fees: Php1,525,000.00 (First Agreement) and Php5,155,000.00 (Second Agreement).
- Together with unpaid WAO No. 20 (Php1,350,000.00), total remaining claimed by petitioner: Php8,030,000.00.
- Petitioner’s counsel sent a demand letter dated July 12, 2011 for the unpaid amounts; respondent’s reply dated July 15, 2011 requested documentation to justify the increase of project cost from Php15,250,000.00 to Php80,711,308.00.
CIAC Proceedings and Final Award (July 16, 2012)
- CIAC conducted preliminary conference and evidentiary hearings; received memoranda from parties.
- CIAC Final Award dispositive (summary):
- Ordered respondent to pay claimant (petitioner) Php1,525,000.00 (10% retention under first contract), Php5,155,000.00 (10% retention under second contract), and Php1,350,000.00 (WAO No. 20) — total Php8,030,000.00 — with 12% legal interest from date of finality of award.
- Denied claimant’s requests for exemplary damages and attorneys’ fees.
- Denied respondent’s counterclaim for reimbursement of Php32,044,090.32 and denied its claims for exemplary damages and attorneys’ fees.
- Each party to bear its own attorney’s fees; arbitration costs to be borne pro rata.
- CIAC’s key findings relevant to the dispute:
- The additional cost of Php28,250,000.00 for revised plan partly covered scope of First Agreement; Second Agreement did not contain a provision specifically stating the First Agreement was abandoned.
- The central issue was whether petitioner was properly compensated for services actually rendered and billed.
- No showing of fraud or vitiation of consent; respondent had evaluations by project manager, quantity surveyor, and accountant and was bound by their actions and evaluations.
- Petitioner entitled to release of retention fees because respondent failed to object timely in its reply to the demand letter and raised objections belatedly before CIAC.
Court of Appeals Decision (January 31, 2013) — Modification of CIAC Award
- CA modified CIAC Final Award and ordered as follows (dispositive as stated in CA Decision):
- “Respondent Systems Energizer Corporation (SECOR) is hereby ORDERED to reimburse petitioner BELLVILLE DEVELOPMENT INCORPORATED (BDI) the amount of Thirteen Million Five Hundred Ninety[-]Three Thousand Two Hundred Seventy[-]Three Pesos (P13,593,273.00), representing the excess amount paid by the petitioner to the respondent;” (emphases in original).
- Denied exemplary damages and attorneys’ fees for both parties.
- Arbitration costs borne pro rata by both parties; all other requests denied.
- CA rationale and findings:
- The monetary awards in the CIAC Final Award lacked evidentiary basis because petitioner did not prove completion of work under the First Agreement; CIAC relied on presumptions and conjectures.
- Petitioner f