Title
Sta. Lucia Realty and Development, Inc. vs. Uyecio
Case
G.R. No. 176217
Decision Date
Aug 13, 2008
Sta. Lucia Realty failed to complete amenities in "The Royale Tagaytay Estates," breaching contracts with Uyecio buyers. HLURB ruled for contract cancellation, refunds with 6% interest, and damages. SC affirmed with modifications.
A

Case Summary (G.R. No. 171980)

Contracts to Sell and Promised Amenities

The petitioner marketed the Phase II lots with a schedule of amenities that included, among others, a church; clubhouse; basketball court; adult pool and kiddie swimming pool; multipurpose hall and function room; billiards; a grand entrance; perimeter fence; cemented roads, curbs and gutters; cemented sidewalks; storm drainage system; electrical facilities; mercury street lamps; centralized interrelated water system with deepwell and overhead water tank; concrete electrical posts; and a tennis court.

Under the contracts to sell dated May 21, 1999, the respondents actually paid the required downpayments and then remitted monthly amortizations until April 2001. They then suspended further payments because the project was not delivered within the promised period and because the improvements and amenities shown in the sales brochures had not yet been introduced or completed.

Parties’ Conduct After Alleged Non-Completion

The respondents sent petitioner a letter demanding completion of the entire project and expressly stated that they were suspending installment payments due to “contractual breach.” Petitioner, for its part, sent letters advising the respondents of alleged default in the payment of monthly amortizations from March 2001 through the third quarter of 2002. Thus, both sides treated the other as breaching the respective contractual obligations: respondents by withholding amortizations, and petitioner by asserting the respondents’ default.

Petitioner also attempted to distance itself from advertising representations by disclaiming participation in the preparation of the project advertising materials distributed by Asian Pacific Realty Brokerage, Inc. It also insisted that it was not barred from seeking time extension to complete the project, citing License to Sell No. R4-98-12-0203, which allowed application for an extension of time to complete development when the project could not be completed within the prescribed period before expiration.

Administrative Complaint Before the HLURB and the Ocular Inspection

On August 22, 2002, respondents filed a complaint before the HLURB Regional Field Office No. IV, seeking (i) completion of the project within six months, or, alternatively, (ii) refund of their total payments bearing interest at 21% per annum computed from February 1999 until full payment, as well as (iii) moral and exemplary damages and attorney’s fees.

Following an ocular inspection of the subdivision on December 3, 2002, the HLURB Regional Office found that the project remained unfinished. Engineer Rey E. Musa’s report reflected that multiple brochure-indicated features and amenities for Phase II were yet to be provided or constructed, including the church, electrical facilities (including concrete posts and mercury street lamps), clubhouse and specific recreational courts and facilities, property perimeter wall for security and privacy, and landscaped garden promenade. The report also stated that while existing water tanks were present in Phase II, they were not yet operational, and that the project lacked a sewerage water treatment plant within the whole project.

Petitioner did not entirely deny lack of completion, but claimed that the basic components were almost 100% complete and submitted a report from its project engineer, Gregorio Evangelio, which indicated substantial completion of earthworks, concrete works, drainage, and that water distribution was 98% finished. Petitioner nevertheless conceded in its own engineer’s report that electrical distribution works remained at 5% and that the perimeter fence remained at 50% as of September 2002.

HLURB Rulings, Appeal, and Affirmance by Higher Tribunals

By Decision dated June 23, 2003, the HLURB ruled in favor of respondents and ordered rescission of the contracts to sell, refunding the paid amounts with 12% interest per annum from the filing of the complaint until full payment. It also awarded moral damages, exemplary damages, attorney’s fees, and imposed an administrative fine for violation of Sections 19 and 20 in relation to Section 38 of P.D. 957. Petitioner appealed to the HLURB Board of Commissioners, First Division, but its petition for review was denied by Decision dated December 5, 2003 and Resolution dated March 31, 2004.

The Office of the President affirmed the HLURB decision. The Court of Appeals likewise affirmed. Petitioner then sought further review, arguing that the Court of Appeals erred in upholding rescission, in awarding refund with allegedly exorbitant interest, and in sustaining the awards of moral and exemplary damages and attorney’s fees.

The Supreme Court’s Treatment of Factual Findings

The Supreme Court held that petitioner’s issues were largely a rehash of matters already passed upon by the HLURB, the Office of the President, and the Court of Appeals. It reiterated that absent substantial showing that the factual findings of administrative agencies within their expertise were based on erroneous estimation of evidence, those findings were considered conclusive. The Court found no ground to disturb the HLURB’s factual determinations.

The Court also noted that petitioner’s own project accomplishment report and an HLURB letter dated November 5, 2003 granting petitioner an extension until September 2004 to complete Phase II-B tended to corroborate that petitioner had not finished the project within the announced time frame. It further ruled that petitioner’s counterclaim that respondents were in default was immaterial to the issue of petitioner’s failure to complete the project as promised.

Respondents’ Suspension of Payments and Section 23 of P.D. 957

The Court addressed petitioner’s reliance on the respondents’ alleged default. It stated that even assuming arguendo that respondents defaulted, such alleged default did not prevent petitioner from exercising its option to cancel the contracts to sell. However, petitioner did not cancel; it merely demanded payment of overdue amortizations in May 2002, which was after the lapse of 14 months of alleged default.

The Court deemed respondents’ suspension justified under **Section 23 of P.D. 957, which provided that installment payments made by a buyer would not be forfeited when the buyer, after due notice, desists from further payment due to the owner or developer’s failure to develop according to approved plans and within the time limit. Under that provision, the buyer could opt for reimbursement of the total amount paid, including amortization interest but excluding delinquency interest, with interest at the legal rate.

Remedy for Contracts to Sell: Cancellation, Not Rescission

The Supreme Court then clarified the proper characterization of the remedy. It distinguished between rescission under Article 1191 of the Civil Code and cancellation in the context of contracts to sell on installment. The Court explained that a contract to sell on installments operates on a positive suspensive condition—the full payment of the purchase price—so that until full payment occurs, the obligation of the vendor to convey title does not acquire obligatory force.

Because the obligation whose breach is contemplated by Article 1191 presupposes an existing reciprocal obligation, the Court held that Article 1191 did not apply to a contract to sell since the suspensive condition had not occurred. Thus, rather than rescission, cancellation of the contracts to sell was the correct remedy in the premises.

In this regard, while the HLURB and lower courts used the term rescission, the Supreme Court treated the dispositive result as requiring cancellation consistent with the doctrinal distinction.

Damages and Attorney’s Fees

On damages, the Supreme Court sustained the awards of moral and exemplary damages, citing testimonial evidence presented by respondents. It also sustained the award of attorney’s fees in the amount of P50,000, reasoning that respondents were compelled to litigate and incur

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.