Title
Spouses Lam vs. Kodak Philippines, Limited
Case
G.R. No. 167615
Decision Date
Jan 11, 2016
Spouses Lam and Kodak disputed a contract for minilab equipment; Kodak failed to deliver two units, Lam Spouses stopped payments. Courts ruled mutual breach, awarded damages, ordered return of delivered unit.

Case Summary (G.R. No. 132988)

Letter Agreement — essential terms

The parties executed a single written Letter Agreement (January 8, 1992) for a “package” sale of three Kodak Minilab System 22XL units. Material terms included: total unit price stated at P1,796,000.00 per unit; a 19% multiple-order discount applied to the package and delivered in merchandise/start-up packages; “NO DOWNPAYMENT”; payment in 48 monthly installments at P35,000.00 inclusive of interest for the first 12 months, re-amortization thereafter; price subject to change; secured by post-dated checks (PDCs); first monthly amortization due 45 days after installation. The Letter Agreement was addressed to Colorkwik and written by Kodak representatives.

Factual chronology

Delivery, payments, and breakdown in performance

One Minilab unit was delivered (Tagum) on January 15, 1992 and installed March 9, 1992. The Lams issued postdated checks intended as installment payments; two early checks (March 31 and April 30, 1992) were negotiated and honored, but the Lams thereafter instructed their bank to stop payment on the remaining ten checks, which were dishonored. Kodak demanded return of the delivered unit and later filed a replevin/action for recovery on November 25, 1992. Kodak executed a writ of seizure (December 1992) and took possession of the delivered unit, accessories, and a generator set. The Lams later rescinded the contract (Nov. 18, 1992) for Kodak’s alleged failure to deliver the two remaining units.

Procedural history

Trial and appellate trajectory

Regional Trial Court (Branch 65, Makati) rendered a February 26, 1999 decision finding Kodak in default for failure to deliver two units within a reasonable time, ordered dismissal of Kodak’s claim, and awarded the Lams P130,000 (generator set) plus 12% interest and P1,300,000 for renovation expenses. The Court of Appeals set aside earlier procedural defaults, remanded for pre-trial, and on March 30, 2005 (amended September 9, 2005) modified the RTC outcome: it ordered Kodak to return P270,000 (partial payments), P130,000 for the generator set with interest, and awarded the Lams P440,000 actual damages, P25,000 moral damages, and P50,000 exemplary damages; it also ordered the Lams to return the Minilab unit and accessories. The Supreme Court docketed the petition for review, consolidated matters as appropriate, and ultimately affirmed with modification.

Central legal issues

Issues presented to the Court

(1) Whether the Letter Agreement created divisible/“separable” obligations such that Kodak’s partial delivery (one unit) justified recovery of the contract price for that unit; and (2) upon rescission of the contract, what restitution and damages are proper under Articles 1191 and 1522 of the New Civil Code.

Divisibility analysis and contract character

Court’s analysis on divisibility vs indivisibility

The Court closely examined Article 1225 and the parties’ expressed intent. Although the Minilab units are physically severable and the Court of Appeals emphasized indicators of separability (separate unit prices, separate deliveries, and separate payment arrangements), the Supreme Court found the Letter Agreement manifested a single package transaction: one agreement covering three units, a shared 19% multiple-order discount applied to the package, a single “no downpayment” term, and express reference to a “Minilab Equipment Package.” Under Article 1225 and controlling jurisprudence, an obligation is indivisible if so intended by the parties despite the physical divisibility of the object. The Supreme Court concluded the parties meant a single, indivisible obligation covering the three-unit package.

Rescission, mutual restitution, and legal effects

Rescission under Article 1191 and consequences

Both parties exercised the power to rescind under Article 1191 (reciprocal obligations). The Court reiterated that rescission abrogates the contract from inception and requires mutual restitution “as far as practicable.” Because both parties invoked rescission, Kodak must restore what it received (return of the Lams’ partial payments) and the Lams must restore what they received (relinquish the delivered Minilab unit and accessories). The Court emphasized that an off-set of the two monthly installments against Kodak’s award is improper because rescission aims to revert parties to pre-contract positions; therefore Kodak should return the P270,000 in partial payments and the Lams must return the unit.

Seller’s default and buyer’s liability for accepted goods

Application of Article 1522 to accepted partial deliveries

The Court analyzed Article 1522 to qualify the Lams’ liability for the delivered unit. Even where a seller fails to deliver fully, a buyer who accepts and uses delivered goods before knowing further nonperformance may be liable only for the fair value of what was received. The Supreme Court affirmed that the Lams accepted and used the unit prior to knowledge of non-delivery and thus had obligations limited by rescission and restitution principles; Kodak’s recovery of the unit by replevin was supportable but subject to mutual restitution.

Damages: proofs and limits of review

Standard of appellate review on damages and findings of fact

The Supreme Court emphasized Rule 45’s confines: a petition for review on certiorari is principally a vehicle for questions of law and does not allow re-evaluation of factual findings. Absent grave abuse of discretion, trial and appellate factual findings on damages are binding. The Court found that the Court of Appeals’ awards for actual damages (P440,000) were supported by documentary evidence (incentive fee, lease rider advance, compromise payment for lease pre-termination) and that the Lams failed to substantiate other claimed actual damages. The Court also noted that petitioners’ own breach (stopping payment) warranted tempering Kodak’s liability for its failure to deliver remaining units under Article 1192 (equitable tempering when both parties breach reciprocal obligations).

Moral, exemplary damages, and attorney’s fees

Rationale for moral, exemplary damages, and attorney’s fees award

The Court affirmed the Court of Appeals’ finding that Kodak did not act in bad faith in seeking recovery of the Minilab unit but did misrepresent ownership/right over the separately procured generator set, thereby acting in bad faith for that item. Accordingly, the award of exemplary damages (P50,000) was justified to sanction wrongful misrepresentation and discourage abuse of judicial processes; moral damages (P25,000) were adequate compensation for the Lams’ moral suffering. Because exemplary damages were appropriate, the Court applied Article 2208 to award reasonable attorney’s fees (P20,000), citing precedents that attorney’s fees may be awarded in tandem with exemplary damages and as reasonable compensation in such circumstances.

Equitable adjustment pursuant

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.