Title
Smart Communications, Inc. vs. Aldecoa
Case
G.R. No. 166330
Decision Date
Sep 11, 2013
Residents sued Smart Communications over a cellular tower and generator, alleging health and safety risks. Courts debated permits, nuisance claims, and procedural errors, remanding for trial.

Case Summary (G.R. No. 109941)

Petitioner

Smart Communications, Inc., through its contractor, Allarilla Construction, constructed and operates a 150-foot cellular base station with antennas, transmitters, and a 25KVA diesel generator.

Respondents

Nearby homeowners and occupants who allege that the tower’s structural design, radiofrequency emissions, generator noise and fumes, and lack of proper permits pose dangers to health, safety, and property.

Key Dates

• March 9, 2000 – Lease executed for lot in Barangay Vira.
• May 23, 2000 – Respondents filed Complaint for abatement of nuisance and injunction in the RTC.
• January 16, 2001 – RTC grants SCI’s motion for summary judgment, dismissing the Complaint.
• July 16, 2004 – Court of Appeals reverses and declares the base station a nuisance, ordering cessation of operations.
• December 9, 2004 – CA denies SCI’s motion for reconsideration.
• September 11, 2013 – Supreme Court decision on Rule 45 petition.

Applicable Law

• 1987 Philippine Constitution (site decision post-1990).
• Republic Act No. 7925 (Telecommunications Act of 1995), promoting expansion of service.
• HLURB Resolution No. R-626, series of 1998 (locational guidelines for base stations).
• 1996 HLURB Rules of Procedure, as amended by R-655 (administrative opposition, primary jurisdiction, exhaustion of remedies).
• Civil Code, Article 694 (definition of nuisance).
• Rules of Court, Rule 35 (summary judgment).

Factual Background

SCI secured a building permit from the municipal engineer and applied (pending) for an Environmental Compliance Certificate from DENR-EMB. Respondents allege lack of barangay and municipal permits, absence of public hearing, forgery of barangay certifications, structural instability (citing a prior tower collapse), hazardous radiofrequency emission, noxious generator fumes and noise, and violation of NTC requirements. SCI counters with engineering and health-physics certifications, a list of consenting residents (including the barangay captain), and reliance on RA 7925’s mandate.

Trial Court Proceedings

• Respondents sought temporary restraining order and preliminary mandatory injunction, injunctive relief, abatement of nuisance, demolition of the tower, and damages.
• SCI filed an answer with special and affirmative defenses and a compulsory counterclaim for damages.
• Pretrial and summary-judgment proceedings were held; key disputed facts included structural integrity, radiation levels, generator noise test results, and validity of local approvals.

Summary Judgment and RTC Decision

On January 16, 2001, the RTC granted summary judgment for SCI, dismissing the Complaint as “highly speculative.” The court held that:

  1. DOH findings showed radiation levels lower than broadcast standards.
  2. Alleged hazards were unsupported by facts.
  3. Other urban base stations operate without challenge.
  4. No DENR action had been taken to halt operations.
    Reconsideration was denied on February 27, 2001.

Court of Appeals Ruling

The Court of Appeals reversed on two main grounds:

  1. SCI’s locational clearance was void for lack of majority-resident consent and no barangay council resolution.
  2. The generator’s noise emissions exceeded DENR standards.
    It declared the entire base station a nuisance and ordered SCI to cease operations. A motion for reconsideration was denied.

Issues on Review

  1. Whether the CA improperly adjudicated the validity of SCI’s HLURB locational clearance.
  2. Whether the CA correctly declared the whole base station a nuisance when only the generator produced objectionable noise.
  3. Whether the complaint became moot after the generator’s removal.

Supreme Court Analysis

Validity of Locational Clearance
• By the doctrines of exhaustion of administrative remedies and primary jurisdiction, HLURB has the exclusive authority to issue, review, or revoke locational clearances for base stations.
• Respondents made no prior HLURB opposition or petition for review. It was premature for courts to rule on the clearance’s validity.

Nuisance Determination
• Article 694, Civil Code, defines nuisance broadly as acts or conditions injurious to hea



...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.