Title
Saura Import and Export Co., Inc. vs. Development Bank of the Philippines
Case
G.R. No. L-24968
Decision Date
Apr 27, 1972
Saura, Inc. sued DBP for loan non-release; SC ruled contract extinguished by mutual desistance due to unmet conditions and delay in filing.

Case Summary (G.R. No. L-24968)

Parties

Plaintiff-appellee: Saura Import & Export Co., Inc., borrower-applicant for an RFC loan to finance construction, machinery payment, and working capital for a jute mill.
Defendant-appellant: Rehabilitation Finance Corporation (later Development Bank of the Philippines), lender which approved but later conditioned, revised, and ultimately cancelled the loan/mortgage at the borrower’s request.

Key Dates

Loan application and arrival of machinery: July 1953.
RFC initial approval (Resolution No. 145): January 7, 1954; plaintiff notified January 9, 1954.
RFC re-examination order (Resolution No. 736): February 4, 1954.
Loan documents executed and mortgage registered: April 13–17, 1954.
RFC reduced loan (Resolution No. 3989): June 10, 1954.
China Engineers withdraws as co-signer: June–July 1954.
RFC restored loan to P500,000 with conditions (Resolution No. 9083): December 17, 1954; communicated December 22, 1954.
Correspondence re: availability of local raw materials and release requests: January 1955.
Mortgage cancellation at Saura’s request: June 17, 1955.
Plaintiff’s suit for damages filed: January 9, 1964.
Trial court judgment in favor of plaintiff: June 28, 1965.
Supreme Court decision (appeal): April 27, 1972.

Applicable Law

  • Civil Code provisions on consensual contracts and perfection/extinguishment of obligations (as cited by the court). The court expressly referenced the Civil Code provision quoted in the decision.
  • Doctrine of mutual desistance (mutuo disenso) as a mode of extinguishing obligations (cited authorities: Manresa, Castan).
  • Contract law principles on offer, acceptance, conditions precedent and conditions subsequent, and the binding effect of agreed uses of loan proceeds.

Factual Background

Saura, Inc. applied in July 1953 to RFC for an industrial loan of P500,000, allocated as P250,000 for factory construction, P240,900 for machinery balance, and P9,100 working capital. The jute mill machinery had already arrived based on a letter of credit from Prudential Bank and Trust Co., and Saura had executed a trust receipt in favor of that bank. RFC approved the loan by Resolution No. 145 (Jan. 7, 1954), with specified allocations and co-makers required on promissory notes, and releases to be made as construction progressed. Subsequent internal re-examination was ordered by RFC (Resolution No. 736), committees were appointed to study the project, and loan documents were formally executed and the mortgage registered in April 1954.

RFC Resolutions and Loan Terms

RFC initially approved the P500,000 loan with express terms that proceeds be used exclusively for the enumerated purposes and that releases be contingent on construction progress and RFC certification. After re-examination, RFC’s Board reduced the loan to P300,000 (Resolution No. 3989) but later (Resolution No. 9083) restored the P500,000 approval conditioned upon certification by the Department of Agriculture and Natural Resources that the required raw materials (locally grown kenaf/jute) were available in the immediate vicinity and that production prospects would be adequate to supply the factory. The record demonstrates that RFC’s original approval was premised on the objective of developing sack manufacture using 100% locally grown raw materials.

Subsequent Negotiations and Correspondence

Saura, Inc. recognized that local kenaf availability was uncertain (citing a Bureau of Forestry study). Saura requested specific releases and asked for assurances that jute could be imported if needed; in particular, it sought P67,586.09 for raw materials and labor and proposed staged releases tied to opening letters of credit and arrival of raw jute. RFC replied (Jan. 25, 1955) reiterating its position that the loan’s basis was local raw material supply and declining to accede to a plan premised on imported jute, and indicating that releases would be subject to reappraisal and to the certification requirement. Negotiations then reached a standstill.

Cancellation of Mortgage and Subsequent Events

Saura, Inc. requested cancellation of the RFC mortgage; RFC cancelled and delivered the deed of cancellation on June 17, 1955. The cancellation appears linked to Saura’s registration of a mortgage in favor of Prudential Bank and Trust Co., and subsequently Prudential sued Saura for failure to pay an obligation on the trust receipt. Saura did not immediately contest RFC’s position or assert breach; it sought no reservation of rights at the time. In 1962 Saura applied to DBP for another loan (disapproved). The present suit for damages against RFC/DBP was filed only on January 9, 1964 — roughly nine years after mortgage cancellation.

Trial Court Judgment and Issues on Appeal

The trial court found a perfected contract between the parties and ruled that RFC/DBP breached its obligation to release loan proceeds, awarding Saura actual and consequential damages totaling P383,343.68, plus interest and attorney’s fees. On appeal, DBP argued (1) prescription/waiver/abandonment of cause of action by plaintiff, (2) absence of a perfected contract, and (3) plaintiff’s own noncompliance with contractual terms. The Supreme Court addressed primarily the question of whether the contract remained in force or had been extinguished.

Supreme Court Analysis — Existence of Contract and Conditionality

The Court acknowledged that there had been offer and acceptance: the loan application was approved and the mortgage executed and registered, thus evidencing a consensual contract under the Civil Code. The Court then examined the conditions attached to implementation. It emphasized that RFC’s insistence on certification of local raw material availability (Resolution No. 9083) was consistent with the stated basis of the original approval and constituted a step in the loan’s implementation rather than an alteration of substantive loan terms. Saura’s January 21, 1955 letter, requesting releases for imported raw jute and differing allocations, amounted to a proposed deviation from the original agreed uses of loan proceeds embodied in Resolution No. 145 and the mortgage. RFC’s refusal to permit diversion of proceeds was therefore within its rights under the existing terms and the implementation conditions it had imposed.

Supreme Court Analysis — Mutual Desistance (Mutuo Disenso) and Extinguishment

The Court found that after RFC declined Saura’s proposed diversion and insisted on certification and reappraisal, further negotiations stalled and Saura asked RFC to cancel t

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.