Title
Saura Import and Export Co., Inc. vs. Development Bank of the Philippines
Case
G.R. No. L-24968
Decision Date
Apr 27, 1972
Saura, Inc. sued DBP for loan non-release; SC ruled contract extinguished by mutual desistance due to unmet conditions and delay in filing.

Case Summary (G.R. No. L-24968)

Factual Background

Saura Import & Export Co., Inc. applied in July 1953 to the Rehabilitation Finance Corporation for an industrial loan of P500,000 to finance construction of a factory (P250,000), payment for jute mill machinery and equipment (P240,900), and working capital (P9,100). The jute mill machinery had already been purchased on the strength of a letter of credit from the Prudential Bank and Trust Co., and Saura executed a trust receipt to secure the release of the machinery. RFC approved the loan by Resolution No. 145 on January 7, 1954, prescribing the specific purposes for the proceeds and requiring certain co‑makers and staged releases as construction progressed. RFC later authorized a re‑examination of the loan under Resolution No. 736, and committees of technical men met to study the project. The loan documents were executed and the mortgage registered in April 1954, but the RFC Board, after re‑examination, reduced the loan to P300,000 by Resolution No. 3989 on June 10, 1954. Shortly thereafter China Engineers, Ltd., which had co‑signed, signified withdrawal. RFC temporarily considered the loan cancelled insofar as the corporation was concerned. RFC restored the loan to P500,000 by Resolution No. 9083 on December 17, 1954, but expressly conditioned revival upon certification by the Department of Agriculture and Natural Resources that the raw materials needed were available locally and that production prospects would supply factory requirements.

Project Purpose and Raw‑Material Condition

The project was expressly described in Saura’s own brochure as a venture to manufacture sacks and other products from “100% local raw materials, principal Kenaf,” and the RFC’s condition requiring certification of local raw‑material availability echoed that premise. Saura later acknowledged, by letter dated January 21, 1955, that kenaf would not be available in sufficient quantity for the current or possibly the ensuing year, and it requested revised releases of loan proceeds that would include funds for imported jute and other items not strictly within the original allocations. RFC replied on January 25, 1955 reiterating that the original approval contemplated reliance on locally available raw materials and refused the proposed deviation.

Procedural History

Saura filed suit for damages against RFC’s successor, Development Bank of the Philippines, on January 9, 1964, alleging failure to release the loan proceeds and consequent injury. The Court of First Instance of Manila rendered judgment for Saura on June 28, 1965, awarding P383,343.68 in actual and consequential damages, legal interest from the filing of the complaint, and attorney’s fees of P5,000. The defendant appealed. The Supreme Court took up the appeal and issued decision on April 27, 1972.

Parties’ Contentions on Appeal

The defendant contended that the plaintiff’s cause of action had prescribed or been waived or abandoned; that there was no perfected contract; and alternatively, that the plaintiff itself failed to comply with the contract terms. The plaintiff maintained that RFC/DBP breached an obligation to release loan proceeds as approved, that a perfected contract existed, and that it was entitled to recover damages.

Court’s Findings on Contract Formation

The Court found that there had been offer and acceptance and that a consensual contract existed in the sense recognized by the Civil Code. The opinion cited Art. 1954, Civil Code, observing that an accepted promise to deliver in a simple loan is binding upon the parties though the loan is perfected upon delivery. The execution and registration of the mortgage and the formal loan documents demonstrated an agreement to finance the jute mill project.

Court’s Ruling on Extinguishment by Mutual Desistance

Notwithstanding recognition of a perfected consensual contract, the Court held that the contract had been extinguished by mutual desistance. The Court emphasized that RFC’s restoration of the loan on December 17, 1954, was explicitly conditioned on the availability and prospect of local raw materials. Saura’s subsequent request in January 1955 for releases to permit reliance on imported jute and for diversion of funds to purposes other than those specified constituted a deviation from the terms embodied in Resolution No. 145 and in the mortgage. RFC’s refusal produced an impasse. Saura then requested cancellation of the mortgage, and RFC executed the deed of cancellation in June 1955 at Saura’s behest. The Court treated these mutual acts as an agreement to desist from the contract — mutuo disenso — which extinguished the obligations. The Court relied on authorities cited in the opinion to show that mutual agreement can both create and extinguish obligations.

Consideration of Plaintiff’s Conduct and Delay

The Court noted that Saura did not protest RFC’s position or reserve rights when requesting cancellation. Saura’s later conduct, including an application for a different loan in 1962 and the filing of the present action only in 1964, reinforced the Court’s conclusion that Saura had abandoned the contract and accepted cancellation. These circumstances led the Court to conclude that Saura had no enforceable claim for damages against RFC/DBP arising from the cancelled loan.

Disposition and Consequences

The Supreme Court

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.