Title
Supreme Court
Sargasso Construction and Development Corp. vs. Philippine Ports Authority
Case
G.R. No. 170530
Decision Date
Jul 5, 2010
A construction joint venture sought to enforce a reclamation project contract with PPA, but the Supreme Court ruled no contract was perfected due to lack of Board approval and authority.

Case Summary (G.R. No. 170530)

Key Dates

  • August 14, 1990: Commencement of original Pier 2 and rock causeway contract
  • October 1, 1992: Consortium’s letter offering to undertake reclamation for ₱36,294,857.03
  • December 18, 1992: PPA’s counteroffer to reduce price to ₱30,794,230.89
  • August 26, 1993: Notice of Award issued to petitioner for ₱30,794,230.89, subject to conditions
  • 1994: Completion of fendering requirement
  • September 9, 1994: PPA Board denies approval of supplemental reclamation contract
  • June 30, 1997: Petition for specific performance filed in the Regional Trial Court (RTC)
  • June 8, 1998: RTC grants specific performance and orders execution of contract
  • 2000–2004: Appeals and procedural motions before the Court of Appeals (CA) and this Court
  • August 22, 2005: CA reverses RTC’s decision and dismisses petition
  • July 5, 2010: Supreme Court issues final decision

Applicable Law

  • 1987 Philippine Constitution (post-1990 decision)
  • Presidential Decree (P.D.) No. 1594 and its IRR (Government infrastructure contracts)
  • P.D. No. 857 (Revising PPA Charter)
  • Executive Order No. 380 (Revised levels of authority for GOCC contracts)
  • Revised Administrative Code, Book I, Sec. 51 (Contract execution authority)

Facts

The joint venture secured a public bid for Pier 2 and rock causeway construction at San Fernando, La Union, in 1990. In October 1992 it offered to undertake an additional 4,280 sqm reclamation adjacent to Pier 2. After price negotiations, PPA’s general manager issued a Notice of Award on August 26, 1993 at ₱30,794,230.89, conditioning contract execution on fendering completion (accomplished in 1994), provision of security documents, and acceptance of stipulated cost terms. Thereafter PPA’s Board of Directors refused to approve the supplemental agreement in September 1994, citing lack of legal basis for negotiated award and the distinct nature of the reclamation work. No formal notice of disapproval was sent; petitioner requested reconsideration but received no reply.

Procedural History

Petitioner filed for specific performance and damages in June 1997 before RTC Manila, alleging PPA’s unjustified refusal to execute the awarded contract caused delays and financial losses. PPA countered that the Notice of Award was revoked by Board’s non-approval, and that petitioner lacked required registration and equipment for subsequent bidding. The RTC granted specific performance in June 1998; PPA’s appeal was initially dismissed by CA for lateness but later reinstated by this Court en banc. On August 22, 2005, the CA reversed the RTC and dismissed the petition. Petitioner sought certiorari under Rule 45, challenging CA’s ruling.

Issue

Whether a binding, perfected contract for the reclamation project existed between the joint venture and PPA, which hinges on whether PPA’s general manager had authority to bind PPA absent express Board approval.

Ruling of the Supreme Court

The petition is denied. No perfected contract existed because the Notice of Award lacked the required approval of PPA’s Board or other competent authority as mandated by law.

Legal Analysis

  1. Essential Elements of Contract
    • Consent, object certain, and cause must concur. Negotiation ends in perfection only when these elements are agreed.
  2. Government Contracts
    • Subject to Civil Code requisites plus statutory requirements for approval by competent authority. Absent such approval, no contract is perfected.
  3. Authority to Bind PPA
    • P.D. 857 vests in the Board the power to “make or enter into contracts” and permits the general manager only “to sign contracts” and perform duties assigned by the Board.
    • Executive Order No. 380 and IRR of P.D. 1594 require Board approval for negotiated infrastructure contracts not exceeding ₱50 million.
    • Revised Administrative Code Sec. 51 mandates that contracts by corporate agencies b

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.