Title
Rizal Light and Ice Co., Inc. vs. Municipality of Morong, Rizal
Case
G.R. No. L-20993
Decision Date
Sep 28, 1968
Rizal Light & Ice Co.'s certificate revoked for non-compliance; PSC upheld, favoring public interest over private investment. Morong Electric granted franchise, deemed financially capable.
A

Case Summary (G.R. No. L-20246-48)

Petitioner’s status and franchise history

Rizal Light & Ice Co., Inc. was granted a certificate of public convenience and necessity by the PSC on August 15, 1949 to install, operate and maintain electric light, heat and power service in Morong, Rizal. The PSC later issued orders to show cause and, after several proceedings and inspections, cancelled and revoked that certificate and ordered forfeiture of the franchise on the ground that the petitioner failed to comply with directives and did not render adequate service.

Respondents and competing applicant

The PSC is the administrative body charged with supervision, approval and regulation of public utilities and of municipal franchises. The Municipality of Morong initiated proceedings complaining of petitioner’s inadequate service. Morong Electric Co., Inc. sought and subsequently obtained municipal franchise and PSC approval to operate an electric service in Morong; its corporate existence was formalized by SEC issuance of its certificate of incorporation on October 17, 1962.

Key procedural dates and events

Important milestones: PSC certificate to petitioner (Aug. 15, 1949); PSC order to show cause (Dec. 19, 1956) and initial cancellation for failure to appear (Feb. 18, 1957); reinstatement after evidence of illness of petitioner’s manager; petition by Municipality of Morong to revoke (filed June 25, 1958); multiple PSC inspections (notably July 12–13, 1960 and June 21–24, 1961); PSC decision revoking petitioner’s certificate (Aug. 20, 1962); petitioner’s electric plant burned (July 29, 1962); Morong Electric municipal franchise granted (May 6, 1962) and SEC incorporation (Oct. 17, 1962); PSC decision granting Morong Electric certificate (Mar. 13, 1963); Supreme Court petitions by petitioner to review PSC decisions and denials of preliminary injunctions (various resolutions denying injunctions in 1963).

Applicable law and constitutional framework

Applicable statutory law included Commonwealth Act No. 146 (regulating public utilities) as amended (notably provisions authorizing investigations, imposition of conditions, and revocation/cancellation powers), R.A. No. 723 (amending delegation language in Section 32), and municipal franchise statutes (Act No. 667, as amended by Act No. 1022). Because the decision predates the 1987 Constitution, the applicable constitutional framework is that in effect at the time of decision (the 1935 Constitution and prevailing statutory law). Key statutory provisions cited: Section 16(n) (cancellation/revocation power), Section 17(a) (investigatory power), Section 21 (fines and cumulative remedies), and the delegation provision in Section 32 as amended.

Procedural history before the PSC and Supreme Court

The PSC conducted joint proceedings on the order to show cause and the municipality’s petition. The Commission authorized division chief Pedro S. Talavera to conduct hearings for reception of evidence. Multiple postponements and inspections occurred; petitioner repeatedly participated, at times agreeing that a current PSC inspection report would suffice and accepting a procedure that would abbreviate hearings. After petitioner failed to file a written reply to the June 1961 inspection report within the time allowed, the PSC submitted the case for decision and later revoked petitioner’s certificate (Aug. 20, 1962). Morong Electric applied for a certificate; petitioner opposed. The PSC found Morong Electric financially capable and, in view of the PSC’s revocation of petitioner’s certificate, issued a certificate to Morong Electric (Mar. 13, 1963). Petitioner sought review in the Supreme Court of both PSC decisions.

Issues presented to the Supreme Court

Petitioner’s principal assignments of error included: (1) improper delegation of hearing authority to a non-lawyer division chief (Pedro S. Talavera); (2) insufficiency and unreliability of the evidence (inspection reports), denial of opportunity to present or cross-examine evidence; (3) failure of the PSC to protect petitioner’s investment and to apply the “protection-of-investment” rule; (4) excessive penalty in revoking the certificate instead of imposing a fine; and, in the Morong Electric case, (5) Morong Electric’s lack of legal personality at the time of municipal franchise and application; (6) alleged lack of financial capability of Morong Electric; and (7) PSC’s findings being unsupported by the record.

Delegation of hearing authority and waiver

The Court found that Mr. Pedro S. Talavera was not a lawyer and thus, under the second paragraph of Section 32 (as amended by R.A. No. 723), authorization to a division chief to receive evidence is limited to division chiefs who are lawyers. Nevertheless, the Supreme Court treated the point as procedural, not jurisdictional. Because petitioner never objected before the PSC, participated in hearings conducted by Talavera, submitted evidence, and entered into procedural agreements with him as hearing officer, the Court held petitioner waived the defect in delegation. Precedent established that failure to timely object to delegation of hearing authority before the PSC constitutes waiver of the procedural defect.

Standard of review and adequacy of evidence (inspection reports)

The Court reiterated the limited scope of judicial review of PSC factual determinations: the Supreme Court’s role is not to retry facts de novo but to determine whether there is evidence before the PSC upon which its decision may reasonably be based. The PSC relied principally upon its engineers’ inspection reports detailing deficiencies in petitioner’s plant and service. Those reports were the PSC’s own observations and investigations; they were admissible in the administrative fact-finding process. The Court held the reports provided sufficient evidentiary basis for the PSC’s decision, particularly because petitioner had failed to present counter-evidence or to cross‑examine report authors after expressly agreeing through counsel to rely on the engineer’s report and accept abbreviated proceedings.

Waiver of opportunity to present evidence and admissions in the record

The Court emphasized transcript passages showing petitioner’s counsel expressly agreed to rely on the PSC inspection report, requested a current inspection by Engineer Martinez and manifested willingness not to cross-examine, and accepted submission of the case for decision upon filing a written reply. Petitioner failed to file the reply within the granted period. Because petitioner waived its right to cross‑examine and present further evidence, it could not later complain that the PSC’s decision rested on untested inspection reports.

Judicial notice and post‑hearing testimony (Bernardino)

Petitioner argued the PSC should have credited testimony by Harry B. Bernardino that petitioner’s service had improved before the fire. The Court found the PSC could not properly take judicial notice of that testimony for three reasons: (1) the fact was not of the character appropriate for judicial notice (not a universally known, indisputable fact); (2) Bernardino’s testimony was given in a subsequent and separate proceeding after petitioner’s motion for reconsideration had been heard and submitted; and (3) the testimony had not been presented to the PSC in the subject case by an appropriate pleading. Consequently, the PSC’s preference for its own inspection reports over Bernardino’s later testimony was legally permissible.

Allegation that PSC acted as prosecutor and judge

Petitioner alleged the PSC improperly combined prosecutorial/investigatory and adjudicatory roles. The Court noted that the PSC’s investigatory and enforcement roles are expressly authorized by statute (Section 17(a) of Commonwealth Act No. 146 as amended) and that the Commission may initiate investigations and enforcement actions. The Court held that so long as the certificate holder is given a day in court and due process protections, the PSC’s exercise of investigatory and adjudicatory functions does not violate due process. The record showed the municipality was permitted to present its evidence and the petitioner received opportunities to be heard.

Protection of investment rule and its limits

Petitioner invoked the “protection‑of‑investment” principle (Batangas Transportation Co. v. Orlanes) to contend that a prior operator should be protected from issuance of a second certificate. The Court recognized the rule but explained it is not absolute: protection applies only to operators in good standing who comply with their licenses and regulations. Where ample evidence shows that a prior operator persistently failed to render adequate service, violated conditions of its certificate, and ignored PSC directives, protecting that operator’s investment would contravene public interest. The paramount consideration is public convenience and safety; therefore the protection rule does not bar issuance of a new certificate where the prior operator is at fault.

Discretion to revoke versus impose fine

Petitioner argued that a fine would have sufficed in lieu of revocation. The Court observed that Section 16(n) confers broad discretion on the PSC to cancel and revoke certificates when an operator willfully or contumaciously refuses to comply with orders, rules, or regulations. Section 21’s provision for fines is cumulative and not exclusive. Given the record of repeated noncompliance and inadequate service extending back to 1954, the Court concluded revocation was within the PSC’s discretion and was warranted to protect public interest.

Requisites for grant of a certificate to a public service operator

The Court summarized the statutory requisites for granting a certificate of public convenience and necessity: (1) appropriate nationality/corporate form and required

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.