Case Summary (G.R. No. 149610)
Key Dates
Invitation to Bid: January 27, 1992.
Notice to Proceed: September 25, 1992.
Final inspection and acceptance: October 29, 1992.
Contract Agreement executed: November 4, 1992.
DPWH Legal opinions: September 1, 1993 and July 20, 1994.
Complaint filed (RTC): July 3, 1995.
RTC decision: February 19, 1997.
Court of Appeals decision: April 28, 2003.
Supreme Court decision: March 2, 2007.
Applicable Law and Constitutional Basis
Constitutional basis applied: 1987 Philippine Constitution (Article IX, Section 2(1)) — as the decision date is after 1990.
Statutes and rules invoked: Republic Act No. 4566 (Contractor’s License Law), specifically Section 35 (penalties); Presidential Decree No. 1445 (Government Auditing Code), specifically Section 48 (appeal from auditor decision) and Section 26 (general jurisdiction of COA); Civil Code Article 22 (unjust enrichment). Doctrines considered: exhaustion of administrative remedies, doctrine of primary jurisdiction, estoppel against the government, plain meaning rule in statutory construction, and equitable principle against unjust enrichment.
Factual Background
Carwin Construction was pre-qualified and submitted the lowest bid for the concreting of Sitio 5, Bahay Pare. After award, a Contract Agreement was executed and a Notice to Proceed issued. Respondent performed the work, advanced funds for materials and labor, and the DPWH conducted final inspection on October 29, 1992, finding the project 100% complete, issuing Certificates of Final Inspection and Final Acceptance. The DPWH prepared a disbursement voucher but payment was withheld after the District Auditor of COA disapproved final release on the ground that respondent’s contractor’s license had been expired at the time of contract execution.
Administrative Opinions and Pre-Action Events
The DPWH Legal Department issued written opinions (September 1, 1993 and July 20, 1994) advising that RA No. 4566 does not expressly void contracts entered into after a license has expired and therefore the contract was enforceable and payment could be made, subject to possible administrative liability or fines. Despite these legal opinions and respondent’s demands, payment remained withheld and the District Auditor’s disapproval was not reversed administratively prior to respondent’s filing suit.
Procedural History
Respondent filed a complaint for specific performance and damages in the Regional Trial Court (RTC) on July 3, 1995. Petitioner moved to dismiss on grounds of lack of cause of action and lack of jurisdiction because respondent did not first appeal the District Auditor’s disapproval to the Commission on Audit under Section 48 of P.D. No. 1445. The RTC denied the motion to dismiss, and after trial entered judgment in favor of respondent ordering payment of P457,000 plus interest at 12% from demand and costs. The petitioner appealed to the Court of Appeals (CA). The CA affirmed the RTC’s decision with modification reducing interest to 6% per annum computed from June 21, 1995. Petitioner sought review by the Supreme Court.
Issues Presented
The petition raised primarily: (a) whether respondent’s complaint was prematurely filed for failure to exhaust administrative remedies, since an appeal to the COA was available under P.D. No. 1445, Section 48; and (b) whether the COA has primary jurisdiction to resolve respondent’s money claim against the government such that judicial action was improper prior to exhausting administrative avenues.
Court of Appeals’ Rationale (as adopted in lower proceedings)
The CA held that the case involved application of estoppel against the government, a legal question rendering the doctrine of exhaustion of administrative remedies inapplicable. The CA concluded the government, by its actions, was estopped from questioning the validity and binding effect of the Contract Agreement; refusing payment on technical grounds after acceptance of the completed project was inequitable.
Supreme Court’s Analysis — Exhaustion and Primary Jurisdiction Doctrines
The Supreme Court reaffirmed the general rule favoring exhaustion of administrative remedies and the primary jurisdiction doctrine, which requires administrative agencies to decide matters within their specialized competence. It also acknowledged well-established exceptions to these doctrines, permitting judicial intervention in certain circumstances. Of the enumerated exceptions, the Court found two applicable here: (c) unreasonable delay or official inaction causing irreparable prejudice to the complainant, and (e) the question presented being a pure question of law that ultimately must be resolved by the courts. The Court emphasized that where no administrative determination of law can finally dispose of the issue, exhaustion of administrative remedies is not required.
Supreme Court’s Application of Exceptions to the Present Facts
The Court found that despite DPWH legal opinions recommending payment, respondent suffered unreasonable delay and official inaction—repeated demands were unmet and the disapproval by the District Auditor had not produced timely resolution. The core question — whether a contractor whose license had expired at the time of contract execution is nevertheless entitled to payment for completed projects — was treated as a pure question of law. This legal issue did not call for technical administrative fact-finding; the final resolution rested with the judiciary. Accordingly, the Court concluded the complaint was not prematurely filed and the RTC had jurisdiction to decide the matter.
Statutory Construction of R.A. No. 4566, Section 35
Applying the plain meaning rule (verba legis), the Court examined Section 35 of R.A. No. 4566, which prescribes misdemeanor penalties and fines for contractors who submit bids, contract, or undertake construction without first securing a license, or who use an expired certificate or license. The Court found the statute did not expressly declare contracts entered into by an unlicensed or expired-license contractor to be void. Under the plain meaning of the statute, the legislative text penalizes misconduct but does not automatically void the contract or deprive the contractor of a claim for payment for work actually performed and accepted.
...continue readingCase Syllabus (G.R. No. 149610)
Case Citation and Forum
- Supreme Court of the Philippines decision reported at 546 Phil. 87; G.R. No. 158253; decided March 02, 2007.
- Petition for Review on Certiorari under Rule 45 challenging the Court of Appeals (CA) Decision dated April 28, 2003 in CA-G.R. CV No. 56345.
- Lower courts: Regional Trial Court (RTC), Branch 41, San Fernando, Pampanga, Civil Case No. 10538 (judgment rendered February 19, 1997); Court of Appeals affirmed with modification (April 28, 2003).
- Supreme Court ponente: Justice Austria-Martinez. Concurrence by Ynares-Santiago (Chairperson), Chico-Nazario, and Nachura, JJ.; Callejo, Sr., J. on leave.
Parties and Counsel/Representation
- Petitioner: Republic of the Philippines, represented by the Department of Public Works and Highways (DPWH), Commission on Audit (COA) and the National Treasurer; represented before trial court and appellate courts by the Office of the Solicitor General (OSG).
- Respondent: Carlito Lacap, doing business under the name and style Carwin Construction and Construction Supply (referred to as "Carwin Construction" or "respondent").
- CA decision authored by Associate Justice Rosmari D. Carandang; concurred in by Associate Justices Conrado M. Vasquez, Jr. and Mercedes Gozo-Dadole (as stated in the record).
Procedural History
- Invitation to Bid issued January 27, 1992; respondent pre-qualified and awarded lowest bid for concreting of Sitio 5 Bahay Pare.
- Contract Agreement executed November 4, 1992 between respondent and DPWH (petitioner).
- Notice to Proceed issued September 25, 1992 by District Engineer Rafael S. Ponio.
- Final inspection on October 29, 1992 found project 100% complete; Certificates of Final Inspection and Final Acceptance issued.
- DPWH prepared a Disbursement Voucher in favor of petitioner, but payment was withheld after the District Auditor of COA disapproved final release of funds due to respondent’s expired contractor’s license at time of contract execution.
- DPWH Legal Department issued Letter-Reply (September 1, 1993) and later indorsement (July 20, 1994) by Cesar D. Mejia, Director III, advising payment was proper notwithstanding expired license, subject to possible administrative liability/fines.
- Despite legal opinion recommending payment, respondent was not paid and filed complaint for Specific Performance and Damages on July 3, 1995 before the RTC.
- Petitioner moved to dismiss (September 14, 1995) asserting lack of cause of action and failure to exhaust administrative remedies (no appeal to COA); RTC denied the motion (Order March 11, 1996), and denied reconsideration (Order May 23, 1996).
- OSG filed Answer (August 5, 1996) invoking non-exhaustion and non-suability of the State defenses.
- RTC rendered judgment for respondent on February 19, 1997 ordering payment of P457,000.00 plus interest at 12% from demand until fully paid, and costs of suit.
- Petitioner appealed to the Court of Appeals; CA affirmed with modification on April 28, 2003, reducing interest to 6% per annum computed from June 21, 1995.
- Petitioner elevated case to the Supreme Court via Rule 45 petition which is the subject of this decision.
Factual Chronology (Key Dates and Events)
- January 27, 1992: DPWH District Engineer issues Invitation to Bid.
- Respondent pre-qualified and submitted lowest bid; awarded the concreting contract for Sitio 5 Bahay Pare.
- September 25, 1992: Notice to Proceed issued by District Engineer Rafael S. Ponio.
- November 4, 1992: Contract Agreement executed between respondent and petitioner.
- October 29, 1992: Final inspection by DPWH personnel finds project 100% complete; Certificates of Final Inspection and Final Acceptance issued.
- September 1, 1993: DPWH Legal Department Letter-Reply (Cesar D. Mejia) opines contract enforceable despite expired contractor’s license.
- July 4, 1994 / July 20, 1994: Further request and indorsement reiterating legal opinion that payment should be made.
- July 3, 1995: Respondent files complaint for Specific Performance and Damages.
- March 11, 1996 and May 23, 1996: RTC denies Motion to Dismiss and reconsideration respectively.
- February 19, 1997: RTC decision in favor of respondent ordering payment.
- April 28, 2003: CA decision affirms lower court, modifies interest to 6% from June 21, 1995.
- March 02, 2007: Supreme Court decision denying petition for review.
Claims, Causes of Action and Relief Sought
- Respondent’s claim: Complaint for Specific Performance and Damages to compel payment for completed concreting project and recover contract price plus interests and costs.
- RTC relief awarded: Payment of P457,000.00 (contract price) plus interest at 12% from demand until paid; costs of suit.
- CA modification: Affirmed RTC's decision with modification—interest set at 6% per annum computed from June 21, 1995.
- Supreme Court disposition: Petition denied; CA decision affirmed; no pronouncement as to costs.
Administrative Actions, Opinions, and Audit Disapproval
- District Auditor of COA disapproved final release of funds on ground that respondent’s contractor’s license had expired at the time of contract execution; DPWH consequently withheld payment.
- DPWH Legal Department (Cesar D. Mejia, Director III) rendered opinion (Sept. 1, 1993) that R.A. No. 4566 does not expressly render contracts void merely because license expired; contract enforceable and payment may be made, subject to possible administrative liability or fines against contractor and responsible government personnel.
- July 20, 1994 indorsement reiterated recommendation that payment be made to Carwin Construction.
- Despite DPWH Legal Department opinions recommending payment, payment was not made.
Parties’ Contentions on Appeal to the Supreme Court
- Petitioner’s ground for review: CA erred in finding respondent had a cause of action; respondent failed to exhaust administrative remedies and COA has primary jurisdiction to