Title
Republic, represented by the Department of Public Works and Highways vs. A.D. Gonzales, Jr. Construction and Trading Company, Inc.
Case
G.R. No. 250296
Decision Date
Feb 12, 2024
Gonzales Construction sought payment for completed public works projects. The SCT affirmed the lower court's decision, requiring DPWH to pay PHP 5,364,086.35 with interest.

Case Summary (G.R. No. 250296)

Factual Background

The case stemmed from a money claim filed by Gonzales Construction against DPWH for unpaid balances allegedly due for two projects. Gonzales Construction alleged that it entered into two contracts with DPWH: (1) Rehabilitation of Gumain-Porac Division Channel, Sta. 5+800 to Sta. 6+100, in the amount of PHP 2,695,980.00 (the Gumain Project); and (2) Abacan River Control Cut-Off Channel along Manggahan Sto. Rosario, Mexico, Pampanga, Sta. 17+500 to Sta. 18+033, in the amount of PHP 8,174,294.32 (the Abacan Project).

As to the Abacan Project, Gonzales Construction asserted that Gonzales, for the company, signed the contract and submitted it to the Regional Director of DPWH for signature. As to the Gumain Project, it was signed by Gonzales for the company and by District Engineer Angelita M. Twano of DPWH for the government side, and it was submitted to the regional director for signature. Gonzales Construction further claimed that it fully performed its undertakings and submitted completion documents. It stated that the works were inspected and verified as complying with the plans, specifications, and special provisions.

According to Gonzales Construction, despite project completion, only PHP 1,178,252.42 was paid as partial payment for the Abacan Project, leaving an unpaid amount of PHP 9,692,021.92 for both projects. It asserted that its last demand for payment was made on March 26, 1999.

Litigation in the RTC

In support of its complaint, Gonzales Construction presented witnesses including Remedios P. Soto of the Commission on Audit, Aurelio Gonzales, Jr., and Engineer Jesus O. Obordo, then assistant chief of the Construction Division, DPWH. It also offered documentary evidence. DPWH raised special and affirmative defenses: first, that DPWH, as an unincorporated government agency, could not be sued without the State’s consent; second, that the contracts were void for lack of the certification required by Presidential Decree No. 1445 on the availability or appropriation of funds; third, that the contracts were not signed by the Regional Director nor the DPWH Secretary; and fourth, that the complaint was premature due to failure to exhaust administrative remedies. Notably, DPWH did not present evidence.

The RTC, by Decision dated July 17, 2014, ruled in favor of Gonzales Construction and ordered DPWH to pay: PHP 5,364,086.35 representing the unpaid accomplished work on the Abacan Project, PHP 50,000.00 as attorney’s fees, and costs of suit. The RTC found that a perfected contract existed between DPWH and Gonzales Construction when DPWH informed Gonzales Construction of the award of the Abacan Project and Gonzales signed it as conformity. It also reasoned that implied consent to suit attached because the State had entered the contract through its officers or agents in furtherance of a legitimate aim and purpose.

The RTC also ruled that DPWH was estopped from invoking non-compliance with Presidential Decree No. 1445, given that higher authorities had ordered the construction of the projects as an emergency measure due to Mt. Pinatubo, even without full compliance with paperwork requirements. On quantum meruit, the RTC found that the Abacan Project was 90.61% accomplished and valued completed works at PHP 7,332,292.45. Since partial payment of PHP 1,968,206.10 had already been made for the Abacan Project, the RTC computed the unpaid balance at PHP 5,364,086.35. Regarding the Gumain Project, the RTC found no substantial evidence supporting the claim for PHP 2,695,980.00, and it denied payment on that project. It further found that exceptions to exhaustion of administrative remedies applied because of long delay and because the issue on the effect of Presidential Decree No. 1445 non-compliance was purely legal.

DPWH sought reconsideration, but it was denied in an Order.

Appellate Review in the CA

The CA affirmed the RTC with modification in a Decision dated January 31, 2019. It deleted the RTC’s award of attorney’s fees and costs of suit, but it maintained the principal award of PHP 5,364,086.35. It also added interest at six percent (6%) per annum from the finality of its Decision until full payment.

The CA emphasized that it could only consider errors assigned by DPWH. Since DPWH did not properly raise issues, the CA limited its review primarily to whether the RTC erred in awarding PHP 5,364,086.35 on quantum meruit and on related matters of attorney’s fees and costs. The CA held that while certification as to availability of funds is ordinarily a condition sine qua non for government contracts, its absence does not automatically bar recovery for services rendered. Relying on DPWH v. Quiwa and R.G. Cabrera Construction v. DPWH and COA, the CA applied the principle that the government should not unjustly deny what it owes after it benefited from the contractor’s performance.

The CA also sustained the RTC’s factual findings that 90.61% of the Abacan Project was accomplished. It cited evidentiary support, including the testimony of Engr. Obordo, inspection certificates and time-and-work accomplishment documents, and a statement showing accomplishment and approved payment valuation. Since DPWH did not controvert the evidence, the CA ruled that DPWH could not deny the actual work accomplished for which payment was due.

DPWH’s motion for reconsideration was denied in a Resolution dated November 5, 2019, prompting the petition under Rule 45.

The Court’s Issues and the Parties’ Arguments

The principal issue before the Court was whether the CA correctly affirmed the award of PHP 5,364,086.35 in favor of Gonzales Construction based on quantum meruit. DPWH argued, first, that the RTC had no jurisdiction over money claims because, under Presidential Decree No. 1445, the Commission on Audit (COA) had primary jurisdiction over money claims against government agencies. Second, DPWH contended that quantum meruit was inapplicable because Gonzales Construction did not present convincing evidence of the asserted 90.61% accomplishment of the Abacan Project.

Gonzales Construction countered that its suit fell within recognized exceptions to the doctrine of exhaustion of administrative remedies, citing long delay and the fact that the question on the effect of Presidential Decree No. 1445 non-compliance was purely legal. It also asserted that DPWH was barred by estoppel by laches from raising jurisdiction only on appeal, considering the long lapse of time and DPWH’s participation in prior proceedings. On the merits, Gonzales Construction argued that the emergency and urgency surrounding the Abacan Project warranted relaxation of the certification requirement. It further contended that DPWH was aware of and supervised the project, thereby estopping DPWH from denying or questioning the project’s performance. On the evidentiary issue, it maintained that the Court should not re-examine facts, and it invoked the principles of unjust enrichment and quantum meruit.

Jurisdiction Over Money Claims and the Court’s Disposition

The Court held that, under Commonwealth Act No. 327, as amended by Section 26 of Presidential Decree No. 1445, the COA had primary jurisdiction over money claims against government agencies and instrumentalities. It quoted Section 26 on COA’s general jurisdiction over auditing procedures, government accounts, and the examination, audit, and settlement of “debts and claims of any sort due from or owing to the Government.” In support, it cited Metropolitan Manila Development Authority v. D.M. Consunji, Inc., which explained that COA has jurisdiction over money claims against a government agency even when the basis is quantum meruit.

Nonetheless, the Court proceeded to rule on the merits in the interest of judicial economy. It found it unjust and contrary to the ends of justice to leave the case unresolved after an inordinate amount of time. It relied on R.G. Cabrera Corporation, which involved Mt. Pinatubo-related government rehabilitation projects where the DPWH did not pay rental obligations and where the contractor later sought payment before the COA. In that line of cases, the Court had recognized that certification of availability of funds, and attachment of that certification to the contract, are generally conditions sine qua non for executing government contracts. However, it also held that the absence of such certification does not necessarily preclude payment for services actually rendered where the contracts were not intrinsically illegal but were declared void merely for procedural non-compliance with Presidential Decree No. 1445 requirements.

Applying R.G. Cabrera Corporation and DPWH v. Quiwa, the Court ruled that Gonzales Construction should be paid what was due to it. It reasoned that denying compensation for work that benefited the public, solely on the ground of procedural defects, would amount to unjust enrichment at the expense of the contractor.

Quantum Meruit, Proof of Accomplishment, and Appellate Deference to Facts

On DPWH’s contention that Gonzales Construction failed to present convincing proof of 90.61% accomplishment, the Court reiterated that a petition under Rule 45 is limited to questions of law. It stressed that factual findings of the trial court, when affirmed by the appellate court, attain conclusiveness and receive the Court’s highest respect, absent recognized exceptions.

The Court found none of the exceptions. It noted that the RTC found 90.61% accomplishment and evaluated the completed works at PHP 7,332,292.45. The CA affirmed those findings after evaluating the same pieces of evidence. Since DPWH presented no evidence to the contrary, the Court refused to disturb the uniform factual findings.

Having settled Gonzales Construction’s entitlement, the Court maintained the principal award of PHP 5,364,086.35, computed as the unpaid accomplished work after partial payment of PHP 1,968,206.10.

Interest: Modification of the Accrual Point and Rate

While the Court denied the peti

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.