Title
Reliance Commodities, Inc. vs. Daewoo Industrial Co., Ltd.
Case
G.R. No. 100831
Decision Date
Dec 17, 1993
Reliance and Daewoo entered a pig iron sale contract; Reliance failed to open a letter of credit, breaching the agreement. Daewoo sold goods at a loss, sued for damages. Courts ruled Reliance liable, affirming breach and awarding damages to Daewoo.

Case Summary (G.R. No. 100831)

Contractual Agreement and Shipment Details

On January 9, 1980, Reliance Commodities, Inc. (Reliance) entered into a contract with Daewoo Industrial Co., Ltd. (Daewoo) for the sale of 2,000 metric tons of foundry pig iron at a price of US$404,000.00. Daewoo shipped the agreed quantity from Pohang, South Korea, but upon receipt in Manila, the actual delivery was short by 135.655 metric tons. In acknowledgment of this shortfall, Daewoo subsequently entered another contract with Reliance on May 2, 1980, including a commitment to reduce the price per ton for future orders; however, this contract was later superseded by a new contract dated July 31, 1980.

July 31, 1980 Contract and Letter of Credit

The July 31, 1980 contract confirmed an order for another 2,000 metric tons of foundry pig iron at a reduced price of US$190.30 per metric ton, to be paid for by an irrevocable letter of credit (L/C). Reliance applied for the L/C on August 1, 1980; however, the application was denied by the China Banking Corporation due to the need for additional purchase orders to substantiate the request. Reliance managed to present orders for only 900 metric tons, leading Daewoo to reject the proposed L/C for failing to meet the contractual requirements.

Reliance's Non-Compliance and Legal Action

Reliance withdrew its L/C application on August 14, 1980, following Daewoo's rejection. Subsequently, Daewoo responded by selling the pig iron to another buyer at a lower price, incurring losses due to Reliance's non-compliance. On September 3, 1980, Reliance demanded payment for the short delivery under the January 9 contract, but Daewoo's refusal led Reliance to file for damages.

Trial Court Ruling

The trial court ruled that while Daewoo was responsible for the short delivery and thus required to pay Reliance, Reliance concurrently was found liable for breach of contract for failing to open the L/C as stipulated in the July 31 agreement. The court ordered Reliance to pay damages to Daewoo.

Court of Appeals Decision

Upon appeal, the Court of Appeals upheld the trial court's findings and conclusions, stating that the L/C was a requisite for payment and the opening of it did not constitute a suspensive condition preventing a contract's existence. The failure to secure the L/C was directly attributable to Reliance's prior exhaustion of foreign exchange allocated to it.

Legal Interpretation of Letter of Credit

The nature of a letter of credit was elaborated upon, illustrating it as a commercial instrument designed to facilitate international trade by securing payment once certain conditions, predominantly documentation, are met. The courts recognized an L/C as a standard mechanism under commercial agreements, reinforcing that the obligations of Reliance to establish the L/C were binding and crucial for executing the contract's intended transactions.

Responsibility and Compliance

The courts concluded that Reliance's inability to open the L/C resulted from its own prior limitations in compliance with foreign exchange regulations, leading to its liability for damages incurred by Daewoo. This liability held firm even considering Reliance's arguments

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.