Title
Re: Helen P. Macasaet
Case
A.M. No. 17-12-02-SC
Decision Date
Jul 16, 2019
Supreme Court declared eight consultancy contracts void due to lack of proper authority and procurement law violations, emphasizing transparency and accountability.
A

Case Summary (A.M. No. 17-12-02-SC)

Contracts Challenged and Governing Legal Framework

The challenged arrangements consisted of eight Contracts of Services between the Court and Ms. Macasaet for ICT consultancy work for the EISP and related computerization and ICT projects. The Contracts of Services were entered through negotiated procurement, justified on the basis that the work was allegedly highly technical, primarily confidential, and policy determining, where trust and confidence would be the primary consideration. The procurement strategy cited Section 53.7 of the Revised Implementing Rules and Regulations (IRR) of Republic Act (RA) No. 9184, which allows direct negotiation for Highly Technical Consultants, subject to the maximum term of six months, renewable at the option of the appointing Head of the Procuring Entity but not exceeding the latter’s term. The challenged contracts were also measured against executive and administrative procurement contract controls under Executive Order (EO) No. 423, the Government Procurement Reform Act (RA No. 9184), the Government Auditing Code under Presidential Decree (PD) No. 1445, and relevant provisions of the Administrative Code of 1987 (EO No. 292).

EISP Background and Need for a Consultant

The EISP was designed to structure the Judiciary’s ICT roadmap. After approval of the 2009 EISP, the Court faced a gap because the 2009 Budget did not include funding for judiciary-wide technical infrastructure, nationwide connectivity, and network security, which were prerequisites to the nationwide rollout of the EISP and ongoing ICT programs such as the eCourts. The Court therefore found it necessary to hire an ICT consultant to review the status of EISP implementation and related ICT and computerization projects and to develop policy and technical guidance for implementation.

BAC-CS Action and the Recruitment of Ms. Macasaet

As part of the consultancy procurement, the Bids and Awards Committee for Consultancy Services (BAC-CS) issued a 10 September 2013 Memorandum finding the procurement to be highly technical and requiring trust and confidence because it was a priority program of the Court. The BAC-CS recommended three consultants it believed could be considered, among them Ms. Macasaet, for consideration by the Supreme Court.

A Joint Memorandum dated 12 September 2013 to then Chief Justice Maria Lourdes P. A. Sereno, signed by Atty. Michael B. Ocampo and Mr. Edilberto A. Davis, stated that after evaluating the three proposed consultants, the offices found Ms. Macasaet to be the most qualified. This recommendation was approved by the then Chief Justice. Pursuant thereto, the Supreme Court entered into a six-month Contract of Services with Ms. Macasaet on 1 October 2013. The consultancy fee under this first Contract of Services was P600,000.00, payable in six equal monthly installments.

Approval for Direct Negotiation for the Updated EISP Work Plan

In a 16 April 2014 Memorandum, Atty. Ocampo stated that the Court needed a technical and policy consultant for the implementation of the Updated EISP Work Plan and proposed direct negotiation of a six-month contract at P250,000.00 per month, inclusive of applicable taxes. This proposal was anchored on Section 53.7 of the Revised IRR of RA No. 9184, allowing direct negotiation for consultants whose work is highly technical, proprietary, primarily confidential, or policy determining. A subsequent 15 May 2014 Memorandum reiterated that the procurement could proceed without the BAC-CS’s involvement due to being highly technical and prioritised for the Supreme Court. The BAC-CS nonetheless named the previously considered consultants for consideration.

A Joint Memorandum dated 20 May 2014 concluded that Ms. Macasaet was the most qualified among the three proposed consultants and was approved by Chief Justice Sereno. On 23 May 2014, the Court entered into a second six-month Contract of Services with Ms. Macasaet.

Extensions and Total Number of Contracts

In the En Banc approval process, the Court later issued an En Banc Resolution dated 16 September 2014 in A.M. No. 14-09-06-SC, approving the Updated EISP Work Plan and its budget (2014-2019) as the output of the first Contract of Services. A Joint Memorandum dated 1 December 2014 recommended extension of Ms. Macasaet’s engagement for another six months to assist with first-year implementation of the plan and development of ICT policies. Chief Justice Sereno approved the recommendation, and a Contract of Services was entered on 10 December 2014.

Thereafter, the contracts were extended five more times, resulting in a total of eight Contracts of Services signed between the Court and Ms. Macasaet. The record reflects that each extension covered a period of six months per extension and that the Court entered into the first contract on 1 October 2013, the second on 23 May 2014, and subsequent renewals/ extensions thereafter, culminating in the eighth contract with execution on 24 July 2017 (as discussed in the resolution’s treatment of compensation and the final contract window).

Procedural History of the Administrative Matter

The question of legality began as part of A.M. No. 17-08-05-SC. In a Resolution dated 19 September 2017, the Court referred the legality issue to the Office of the Chief Attorney (OCAt) and directed then former Chief Justice Sereno to comment. The OCAt Report was submitted on 6 November 2017. Former Chief Justice Sereno submitted a Preliminary Comment on 20 November 2017, and the Court then required the BAC-CS and Ms. Macasaet to comment through a Resolution dated 21 November 2017. The BAC-CS and Ms. Macasaet filed their comments on 25 January 2018 and 22 January 2018, respectively. Further, Atty. Candelaria and Atty. Ocampo were required to comment on the OCAt Report, with their submissions filed on 20 February 2018 and 25 April 2018, respectively.

Main Issue

The issue presented was the legality of the eight Contracts of Services entered through negotiated procurement, ostensibly represented by Atty. Eden T. Candelaria as Chief Administrative Officer and Deputy Clerk of Court, with Ms. Macasaet for ICT consultancy related to the Supreme Court’s EISP.

Ruling of the Court

The Court declared that all the eight Contracts of Services should be declared void ab initio. It grounded the declaration of nullity on multiple independent bases, namely: (i) lack of written authority of the government signatory; (ii) lack of qualifications of Ms. Macasaet for a highly technical consultant position under the TOR; (iii) unreasonable and excessive compensation; (iv) procurement without proper appropriation and violation of requirements on fiscal authorization; and (v) absence of the required Certificate of Availability of Funds (CAF) for the later contracts.

The Court directed Ms. Macasaet to reimburse the total amounts received as consultancy fees under the eight Contracts of Services from the Supreme Court amounting to P11,100,000.00, less whatever taxes were withheld, within thirty (30) days from finality of the resolution, with legal interest at six percent (6%) per annum from the expiration of that thirty-day period until fully paid.

Legal Basis and Reasoning: Lack of Written Authority of the Signatory

The Court focused first on the signature process. It held that the signatory in the eight Contracts of Services was Atty. Candelaria, acting as Chief Administrative Officer and Deputy Clerk of Court, but that the records failed to show she was authorized in writing by the Supreme Court En Banc to sign the contracts.

Even Atty. Candelaria admitted that she was not expressly given a written authorization by then Chief Justice to sign these contracts, asserting instead an implied authority because the Chief Justice had already approved the award and the Office of the Chief Justice prepared the contract. The Court rejected this theory and held that implied authority does not satisfy the requirement of EO No. 423, which mandates that government contracts require the approval and signature of the Head of the Procuring Entity or duly authorized officials, with such delegation of authority must be done in writing and must carry full authority to enter into or give final approval for the particular contract.

The Court described the Supreme Court as the Procuring Entity and held that the Supreme Court’s Head of the Procuring Entity is the Supreme Court En Banc. It relied on constitutional and internal rules showing that administrative supervision and related administrative powers are exercised through the Court en banc or Divisions, and not by the Chief Justice acting alone absent proper collegial authorization. The Court emphasized the collegial nature of the Supreme Court, citing its jurisprudence that the Chief Justice cannot decide administrative matters alone.

The Court further reasoned that even if power had been delegated to the Chief Justice, re-delegation to another official could not occur because delegata potestas non potest delegari. It held that Atty. Candelaria did not demonstrate any valid written delegation from the Supreme Court En Banc or from the Chief Justice that would vest in her full authority to sign this particular consultancy contract.

Legal Basis and Reasoning: Qualification Requirements for “Highly Technical Consultants”

The Court next concluded that Ms. Macasaet did not meet the qualifications required for engagement as a Highly Technical Consultant under the Updated EISP consultancy scope. While the procurement was treated as highly technical under Section 53.7 of the IRR, the Court found that Ms. Macasaet lacked an educational degree directly related to ICT and had only short-term non-degree ICT training. Her academic background, as found by the Court, focused on mathematics and education, with her graduate degree being in Business Administration, plus certification in Customer Relationship Management (CRM).

The Court relied on the Scope of Work and found that the terms required the consultant t

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.